Key Takeaways
- Volume recovery, pricing soft: 15% YoY volume growth matched the industry, but flat H1 realizations and a slight QoQ dip kept the top-line story muted.
- Cost tailwinds are turning: Power and fuel costs fell YoY to ₹1,508/tonne, but international pet coke prices are firming and the benefit of two cheap shiploads will fade after Q3.
- WHR plant is live, margin lift ahead: The new waste heat recovery plant is already delivering 80% of target power, promising a ₹45/tonne benefit in Q3 and ₹60+ in Q4.
- Expansion timeline is slipping: The Devapur Line 4 start is "at risk" because the forest clearance file is stuck with the State Government, pushing significant capex into the next financial year.
- What to watch next quarter: Whether the WHR benefit lands as guided, the pace of pet coke cost pass-through, and any movement on the Devapur forest clearance file.
Volume & Demand
- Monsoon quarter held up: Q2 is traditionally soft, but August was strong for construction activity even though July and September were not, and total volume of 14.25 lakh tonnes grew 15% YoY in line with served markets.
- B2C share recovered: Trade sales returned above 50% of the mix after dipping below that in Q1, while B2B sales stayed higher than desired but with customers who accept a premium for the product.
- FY24 volume target on track: H1 already crossed 30 lakh tonnes, so the 63–65 lakh tonne full-year target needs 33–34 lakh tonnes in H2, which management sees as feasible barring a market surprise.
- FY25 ambition: Management will look for another 10% volume growth next year, in line with the industry growth rate.
Pricing & Premiumization
- Realizations stayed subdued: Prices were largely flat through H1 despite 15% demand growth, and Q2 saw a small dip from Q1, which management called a dampener.
- Premium push is working: Within a weak trade environment, the share of premium products kept increasing, and the strategy of multiple brands at multiple price points is gaining traction.
- Premium price leadership: Management claims its premium brand prices are "far higher than what the industry has seen from other players," and the OPC segment is remunerative, even better than PPC in many markets.
- Exit target: The company expects to exit the year with about 25% premium cement sales.
Khetrapal: "We do believe that by end of the year, we should be exiting with about 25% premium cement sales, with the prices of our premium cement seen are far higher than what the industry has seen from other players."
Costs & Margins
- Power and fuel costs fell YoY: The blended cost declined to ₹1,508/tonne from ₹1,647 last year, but the composition matters: power cost rose due to Coal India/Singareni price hikes and poor-quality coal, while fuel-side savings more than offset that.
- Plant-level fuel cost gap: Devapur runs at ~₹1,800/million kcal on domestic coal with low freight from nearby Singareni mines, while Chittapur uses imported pet coke at ~₹2,140–₹2,150/million kcal, down ~14% YoY.
- Pet coke tailwind is temporary: The company bought two shiploads at a favorable \$131/tonne, covering nearly three months, so the impact of firming international and domestic pet coke prices will be marginal in Q3 and significant only when a new shipload is booked.
- Maintenance costs are recurring: One kiln maintenance at Devapur was completed in Q2 and another in October, each costing ~₹10 crores, a normal annual pattern that will hit Q3.
- Efficiency metrics stable: Power consumption held at 62–63 units per tonne and heat consumption under 690, with the newer plant significantly lower.
Khetrapal: "Fortunately, we ended up buying two shiploads at a cost, which is now proving to be favorable to us."
WHR & Renewable Energy
- WHR plant commissioned: The waste heat recovery plant came online in the last two days of Q2, with 80% of target power already available and used in October; the remaining 20% will be ready in January.
- Margin benefit quantified: Q3 will see a ~₹45/tonne benefit, rising to ₹60+/tonne in Q4 once the plant runs at full capacity.
- Devapur WHR work started: An internal project report is done and vendors are visiting sites for commercial bids; Line 3 is confirmed, Line 1 is being debated because of higher capex and a 5-year payback versus the 3-year target, and Line 4 will include WHR when built.
- Solar power approved: The board approved solar capacity at Jalgaon and Chittapur, keeping the company on track toward 50% renewable power in operations.
Khetrapal: "We were able to commission the waste heat recovery plant. To the extent that it's 80% of the target power is already available and that we've used in the month of October."
Expansion & Capex
- Devapur Line 4 is delayed: The project is a couple of months behind schedule, and the hoped-for January construction start is "at risk" because the forest clearance file has not moved from the State Government to the Central Government.
- Chittapur expansion progressing slowly: Terms of Reference are received from the Central Government and public hearing applications are filed with the State Pollution Control Board, but delays of a few weeks to a couple of months keep happening at every step.
- MP grinding unit land: The deadline for competing bids expired with no competing bid received; the next board meeting is expected to confirm acceptance of Orient's sole proposal.
- Capex spend pushed out: No significant capex is expected in Q3, and even Q4 will be moderate, with spending shifting to the next financial year; management wants to start construction as soon as approvals are in hand, whether that is January, February, or March.
- Commissioning timeline: Once construction starts, brownfield expansion takes not more than 15 months and a greenfield split grinding unit about 18 months.
- Devapur colony relocation: Work has started on a new multi-story colony within existing land to free up space for Line 4, avoiding land acquisition in a tribal forest area.
Khetrapal: "It is looking to be at risk purely because the file for forest clearance has not moved from the State Government to Central Government, although processes and steps are proceeding all the time."
Regional & Product Mix
- West dominates, South lags: West contributed 64% of volume, while South was only 27% because of low demand and very low prices in Telangana, Karnataka, and Andhra, where management chooses to sell at higher prices than those markets.
- Product mix: Blended cement including premium brands was 59% of sales, with OPC at 41%.
- New brand launched: Birla A1 Dolphin, a water-repellent cement named for a dolphin's skin, was introduced; it is in very early days. Brand identity standardization across the Birla A1 portfolio is also underway with changes to bags and colors.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| WHR cost benefit | ₹45/tonne benefit in Q3, ₹60+/tonne in Q4 | Q3 and Q4 FY24 |
| FY24 volume | 63–65 lakh tonnes total | FY24 full year |
| Premium cement exit rate | ~25% of sales | By end of FY24 |
| FY25 volume growth | Another 10% growth | FY25 |
| Devapur expansion construction start | Start "as soon as possible" once forest clearance is in hand; January start is at risk | January–March 2024, conditional on approval |
| Commissioning post-construction start | Brownfield within 15 months, greenfield within 18 months | From construction start date |
| Renewable power share | On track toward 50% | No date given |
| Devapur WHR Line 3 | Confirmed; Line 1 under debate | No date given |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Revenue | ₹720 cr, +17% YoY and -12% QoQ |
| H1 Revenue | ₹1,550 cr, +16% YoY |
| EBITDA | ₹88 cr, +136% YoY (vs ₹37 cr in Q2 FY23) |
| EBITDA per tonne | ~₹620, vs under ₹300 in Q2 FY23; Q1 FY24 was ~₹650 |
| Realization per tonne | Little under ₹5,050; H1 level ~₹5,100 |
| Total volume | 14.25 lakh tonnes, +15% YoY and -10% QoQ |
| FY24 volume target | 63–65 lakh tonnes; H1 already >30 lakh tonnes |
| Power and fuel cost per tonne | ₹1,508, vs ₹1,647 in Q2 FY23 |
| Blended fuel cost – Devapur | ~₹1,800 per million kilocalories |
| Blended fuel cost – Chittapur | ~₹2,140–₹2,150 per million kilocalories, -14% YoY |
| Blended cement mix | 59% of product mix; OPC at 41% |
| Premium brand share of trade sales | 21–22%; target exit FY24 at 25% |
| Trade (B2C) sales share | 50%+ of total sales, recovered from below 50% in Q1 |
| West region volume share | 64%; South 27%; Central India 9% |
| Term debt | ₹170 cr; H1 FY24 repayment of ₹74 cr |
| Waste heat recovery benefit | ~₹45 per tonne in Q3; full benefit of ₹60+ per tonne expected in Q4 |