Key Takeaways
- Revenue halved sequentially, but that is the plan: Q1 revenue of ₹555 crore fell from ₹1,097 crore in Q4 on milestone-based recognition timing, while YoY growth stayed strong at +51.3%. Management is deliberately shifting revenue into H1, targeting 40–45% of FY27 revenue in H1 versus 35% last year.
- PAT margin held at 11.3% despite the revenue drop, with EBITDA margin improving sequentially to 15.5% on project mix.
- BESS competitive intensity is correcting: Bidder counts collapsed from 51 in Rajasthan to 7–8 in recent NTPC Green tenders, and a major Maharashtra project was cancelled after aggressive bidders found execution unviable. Management sees only serious players remaining.
- Capacity is scaling fast: Operational BESS capacity doubled to 5 GWh, with 10 GWh expected by early December 2026, plus in-house container manufacturing starting batch production next month.
- What to watch next quarter: Whether Q2 revenue actually jumps as promised, the pace of container production ramp toward 210 units, and any concrete revenue plan from the Megmeet AI data center tie-up.
Revenue Trajectory & Seasonality
- The QoQ drop is structural, not demand-driven: Q4 had exceptionally strong execution as multiple energy projects kicked off, creating a high base. In Q1, several projects were still at initial execution stages, so milestone-based revenue recognition produced a much smaller number.
- Q1 is always the slowest quarter for infrastructure companies because government-funded projects concentrate execution toward Q4 when payments arrive. Q1 involves government approvals and processes that slow revenue recognition.
- YoY momentum is intact: Revenue rose from ₹367 crore to ₹555 crore, roughly a 50% increase, driven by a strong execution pipeline and order book.
- H2 concentration is being unwound: The company plans to reduce the revenue concentration seen in H2 of the previous financial year, targeting 40–45% of overall revenue in H1 FY2027 versus 35% in H1 FY2026.
- BOO accounting suppresses reported revenue: Solar-plus-BESS BOO projects are treated as fixed assets on the balance sheet, so physical execution on the ground does not translate into revenue in the same period. That is one reason the FY27 estimate is ₹3,400 crore rather than higher.
Rajavendhan P: "The solar plus BESS project of BOO will not be treated as a revenue as it goes as a fixed asset. So, even though the physical execution on the ground will be higher, not all of it will be reflected as revenue in the same period. So, that's the reason that we have Rs. 3,400 crore of estimated revenue."
BESS Market & Competitive Intensity
- The bidding landscape is correcting sharply: In the six months to March, many non-energy players bid aggressively seeing BESS as lucrative, but have since realized execution is difficult.
- A major Maharashtra project was cancelled: Three to four players had won a 4 GWh project about six to eight months prior, realized execution at those rates was not possible, found a lacuna in the contract, approached APTEL, won the case, and the project was cancelled. The customer lost almost one year of time.
- Price discovery is improving: In Punjab, only one bid was opened in the last three months and prices were discovered at a far better level compared to previous bids.
- Bidder counts have collapsed: Last week, three major NTPC Green tenders saw only seven bidders in one or two tenders and eight in another, versus as many as 51 bidders in Rajasthan and 32 in Maharashtra previously.
Venugopal Maddisetty: "There is a bit of correction in the bidding side. In the last six months till March, many people had bid aggressively. Though they are not from the energy sector or do not have background in this area. They were basically trying to see battery energy storage system as a very new and lucrative business. But now, they have all realized that it is not that easy to execute such projects."
Capacity Expansion & Manufacturing
- Operational BESS capacity doubled to 5 GWh with the commissioning of an additional 2.5 GWh line.
- 10 GWh expansion is on track: Construction is completed and all equipment is ordered, with equipment expected to arrive end of September 2026. The facility is expected to be operational by the first week of December 2026, making it the biggest operational plant in India at that time.
- Container manufacturing has been insourced: The company started container manufacturing within its own factory to address the bottleneck of sourcing containers from outside India due to the lack of an established ecosystem. Trial runs are ongoing, with trials targeted for completion within this month and batch production starting next month.
- Monthly container run rate is scaling: Q2 is planned at 210 containers, and from January the facility is expected to be fully operational at 10 GWh capacity. The run rate is expected to reach at least 125 containers per month in the next calendar year, scaling to 140–150 per month at 90% efficiency.
- Manufacturing scale dwarfs telecom: Energy sector manufacturing output is much larger than telecom because BESS is a capital equipment product business, with each container worth ₹4–4.5 crore, while telecom is project-based with smaller manufactured product value relative to project value.
- Manufacturer advantage on cell prices: Being both manufacturer and project company means raw material price increases have lesser impact than on pure EPC players who procure from manufacturers.
Venugopal Maddisetty: "Being the manufacturer, we can absorb some of these issues in terms of the raw material price increase because if imagine someone who is executing this kind of projects, by procuring the products from manufacturers like us, he would probably have impacted significantly more than us."
Order Book & New Initiatives
- Q1 order wins totaled ~₹1,677 crore: Two EPC contracts from NLC and DVC worth about ₹1,412 crore on the energy side, plus a BSNL optical fibre project worth about ₹265 crore on the telecom side.
- Project executions have started for SECI, KPTCL, MAHAGENCO and Bondada, with work already begun on the ground.
- EPC timelines: NLC and DVC projects are to be executed over the next one year, while the BSNL OFC project runs over the next two and a half years.
- BOO commissioned projects will add ~₹750 crore annually once all four BOO projects are commissioned, representing an asset-owned revenue stream.
- BOO investor discussions are underway at the portfolio level, not just project level, to bring investors on board for BOO investments. Management is going in a balanced way on BOO due to significant investment requirements, and will move more aggressively once investor funding is secured.
- C&I products are qualified and selling: Products below 5 MWh took almost six months to get qualified including field trials, and first orders have been received from large customers in India who will market the products.
- Saudi Arabia entry has begun: An MOU was signed with a Saudi company to explore the battery storage systems market, and a small order was executed in Q1 supplying a few containers. Some portion of revenue from exports is expected this year.
- Pune research center is operational: Inaugurated about three weeks ago, led by Professor Ogale, with a team of about eight experienced PhD scientists. Planning has started for cell manufacturing including evaluating technology, chemistry and related aspects.
- PLI scheme application: The company is applying for 4 GWh under the Government of India's PLI scheme for cell manufacturing announced two or three weeks ago, with a Big 4 consulting firm assisting in preparing bids.
Venugopal Maddisetty: "On the BOO, once we commission all these four projects, they will add to almost about Rs.750 crore as a revenue, which is also going to be a good situation because that is an asset-owned business."
AI Data Center Opportunity
- Megmeet partnership is the entry point: Pace signed a cooperation agreement with Megmeet, a company that has developed power systems for data centers, particularly AI data centers, with products approved by Nvidia and other major chip manufacturers. The tie-up covers India, providing power solutions coupled with battery storage for new-age AI data centers.
- Megmeet is an existing telecom partner of four years, and the plan is to manufacture Megmeet's products in India and integrate them with Pace's BESS as a combined solution.
- Work has started on the ground with good traction from potential customers, and demo equipment is being brought in to showcase.
- Revenue plan is still unquantified: Management expects to give a concrete plan about revenue in the next one quarter, describing the initiative as a long journey with a long-term plan.
Venugopal Maddisetty: "Yes, probably it will be a long journey, but we are going with proper plan. There is a long-term plan and we are working on it."
Margins, Costs & Cash Flow
- EBITDA margin improved sequentially to 15.5% from 14.9%, reflecting project mix during the quarter while continuing to invest in manufacturing and execution capabilities.
- PAT margin was 11.3% on revenue from operations, in line with estimates, at ₹63 crore versus ₹55 crore in Q1 FY26.
- Employee expenses rose to ₹33 crore from ₹27 crore QoQ, reflecting continued investment in manpower particularly for energy projects and manufacturing operations.
- Finance cost declined to ₹28 crore from ₹34 crore QoQ, majorly due to continuous focus on treasury management and optimization of borrowing cost.
- Other income increased to ₹28 crore, majorly due to foreign exchange gains and interest income on bank deposits.
- Cell price mitigation: For Q1, inventory was stocked in March, enabling lower lithium-ion cell costs. For remaining quarters, project margins are expected to absorb cell price increases, factored into the 10.5%–11% PAT margin guidance.
- Working capital is negative driven mainly by telecom receivables with milestone-based payments and deferred revenue. The energy business only started in Q4 of last financial year and has better payment terms: advance, supply payment, commissioning payment, and retention released within maximum six months.
- Inventory and receivables have come down and are expected to reduce further by September, stabilising between December and March. Cash flow from operations is expected to be positive by March as energy projects contribute a bigger quantum to the top line and telecom receivables ease down.
- Telecom margins are better than BESS, but volume is not there in telecom.
Rajavardhan P: "When we have given the margin guidance for this financial year, which is about 10.5% to 11%, we have taken care of the increase in the lithium-ion prices, we which we which we have anticipated during the starting of the financial year."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue | ₹3,200–3,400 crore | FY27 |
| H1 revenue share | 40–45% of overall revenue | H1 FY27 |
| Segment mix | Energy:telecom at 65:35 or 70:30 | FY27 close |
| BESS PAT margin | 10.5%–11% for mix of products and projects | FY27 |
| 10 GWh operational facility | Biggest operational plant in India | First week of December 2026 |
| Container batch production | Start after trials complete within August | September 2026 |
| Container run rate | At least 125 per month, scaling to 140–150 at 90% efficiency | Next calendar year |
| Q2 container production | 210 containers | Q2 FY27 |
| BOO commissioned revenue | ~₹750 crore annual revenue once all four projects commissioned | On commissioning |
| EPC execution | NLC and DVC over one year; BSNL OFC over two and a half years | From Q1 FY27 |
| Cash flow from operations | Positive | By March |
| Working capital | Inventory and receivables reduce further | By September, stabilising December–March |
| AI data center revenue plan | Concrete plan to be shared | Next one quarter |
| Indigenous cell manufacturing | Planned | Probably two years from now |
| PLI scheme application | 4 GWh under Government of India PLI scheme | Application in process |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Revenue | ₹555 crore, +51.3% YoY; declined from ₹1,097 crore in Q4 FY26 |
| Gross profit | ₹155.5 crore, gross margin of 28% |
| EBITDA | ₹86.1 crore, margin of 15.5% vs 14.9% in Q4 FY26 |
| Profit after tax | ₹63 crore, vs ₹55 crore in Q1 FY26; PAT margin of 11.3% |
| Employee expenses | ₹33 crore, vs ₹27 crore in Q4 FY26 |
| Finance cost | ₹28 crore, vs ₹34 crore in Q4 FY26 |
| Other income | ₹28 crore, majorly due to foreign exchange gains and interest income on bank deposits |
| FY27 revenue guidance | ₹3,200 to ₹3,400 crore, management confident of achieving |
| Executable order book | ₹10,803 crore, as of 30th June; energy ₹8,453 crore, telecom & ICT ₹2,350 crore |
| Q1 order inflow | ₹1,677 crore, comprising ₹1,412 crore energy EPC from NLC and DVC, and ₹265 crore BSNL optical fibre |
| Energy revenue share | 79.5% of overall revenue; Telecom & ICT contributed 20.5% |
| BESS capacity operational | 5 GWh, with expansion to 10 GWh expected operational by first week of December 2026 |
| Containers supplied | Over 300 cumulative; 90-plus delivered in Q1 vs 178 in all of FY26 |
| Q2 planned container supply | 210 containers, up from 90-plus in Q1 |
| Kavach project completion | ~30% work completed |
| BOO cumulative commissioning | 975 MWh as on date, with annuity revenue of about ₹120 crore |
| BOO revenue recognised to date | ~₹900 crore from MSEDCL project including previous financial year |
| Standalone BESS rental tariff | ₹2.19 lakh per MW per month |
| BESS container value | ₹4 to ₹4.5 crore each |
| Grid-scale BESS product EBITDA margin | 13% to 15% |
| C&I BESS EBITDA margin | 4% to 5% higher than grid-scale product margin |
| BESS PAT margin target | 10.5% to 11% for mix of products and projects |
| EPC overall margin | 12% to 15% at manufacturing plus project level |
| BOO SPV annuity IRR | 12% to 13% |
| Cell cost share | ~60% of total cost |
| Total capex for 10 GWh plus container fabrication | ~₹300 crore across three phases |
| Energy net working capital | 90 to 100 days |
| Telecom net working capital | 4 to 5 months, approximately 150 days |
| H1 FY27 revenue target | 40% to 45% of full-year revenue, vs 35% in H1 FY26 |
| Expected FY27 order book mix | 65:35 or 70:30 energy to telecom by year-end |
| BOO projects once commissioned | ~₹750 crore annual revenue addition |
| Tenders being bid | ~27 GWh of tenders |
| PLI scheme application | 4 GWh under PLI scheme for cell manufacturing |
| C&I first trial order | 25 units, with customer looking at thousands of units per year |