Pakka Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/viefwuvukhj8nn6ujlojhlov.pdf

Key Takeaways


The Funding Reset

A planned equity raise faltered when one investor did not honor warrants due to the falling share price, forcing a scramble. The resulting structure with Neo Group is expensive but, management argues, necessary to get the project running rather than starve it for capital.

ElementDetail
Facility₹500 crores in NCDs
Effective rate~16.95% (12% coupon plus gap funding)
Moratorium4 months on principal; no repayment for 16 months
Promoter equity₹85 crores at ₹110/share (20% premium to ₹109 book value)
Neo Group equity₹30 crores
SecurityFirst charge on fixed assets, second on current assets, personal/corporate guarantees, promoter share pledge
Exit pathReplace with cheaper debt within 15–18 months; Neo does not want to stay long-term
Himanshu Kapoor: "The essence of the project lies in the project getting started rather than just starving for money in the entire project. And all our wealth and everything lies only in the fact faster the project is implemented and it starts generating revenue."

Project Jagriti: Timelines, Products & Economics

The new machine is the company's entire growth thesis compressed into one asset. Commissioning timelines have slipped on funding delays, but management insists the end-of-September target for first paper holds.

Ved Krishna: "The machine that we are expecting, though there was some delay in the funds availability, but we are still expecting by end of September, this machine will also be producing."

Wrap & Carry: The Near-Term Fix

The legacy business absorbed a double hit: a PM3 modification shutdown that stretched from a planned 20 days to 40 days, and a pricing war from new waste-paper-based entrants that compressed net sales realization.


Food Services: Growth Without Profit

Revenue grew significantly YoY (₹17 cr vs ₹11.5 cr), but QoQ growth was muted because Q3 is the festive peak and Q4 included re-rationalization and stock-taking impacts. PBT was negative, driven by one-off items rather than core operational weakness.


Flexible Packaging: Still in the Lab

The chemistry for non-metallized flexible packaging is not yet production-ready. Viscosity and drying challenges with new-age chemicals persist, and management cannot be totally sure it will achieve the desired production.

Ved Krishna: "It is a delicate, interesting, difficult, and possible chemistry that we've been working with. But we are close to at least doing some significant trials at the global stage, and we are hoping for more significant news in the coming quarters."

Cost, Debt & The Path Back to Margin

The company is attacking costs on multiple fronts while carrying expensive debt that will take at least 15–16 months to clear. Management is explicit that margin recovery is an effort, not guidance.

Ved Krishna: "We are totally responsible for eroding your wealth. And we want to make sure that we do right by you."

Guidance & Commitments

CommitmentSpecificsTimeline
PM3 modificationIncrease production by 10 tons/day, boost PBT by ~₹8 crFourth week of June
Power plant & recovery boiler commissioningCommissioning and testingJuly
Project Jagriti paper machineFirst paper productionEnd of September, plus 2 months stabilization
New facility capacity ramp-up60%+ utilizationEnd of FY27
New facility capacity ramp-up75%+ utilizationFY28
Outsourced OGR scale-upFrom ~300 tons to 500 tons/monthGradual ramp
High-cost debt exitReplace with cheaper debt; exit without premium possibleWithin 15–18 months
Minimum EBITDA₹125–130 cr bare minimumNext two years (by FY28)
Food services market share15% (~₹680 cr)By 2028
Revenue ambition\$1 billionBy 2030

Key Metrics

MetricQ4 FY26
RevenueImproved 8% YoY and 4% QoQ
Full-year revenueDip of around 13% YoY
Wrap & carry Q4 revenueUp 4% YoY and 6% QoQ
Wrap & carry full-year volumeDrop of 17% YoY
Wrap & carry full-year PBTDrop of almost 50% YoY
PM3 outage impact on PBT₹11 cr negative impact
Pricing impact (NSR) on PBT₹16 cr negative impact from new entrants
Food services Q4 revenueApproximately ₹17 cr, vs ₹11.5 cr in Q4 FY25
Food services full-year volume3,100 tons, grew 20% YoY from 2,600 tons
Food services B2C channel revenue₹6.5 cr in FY26, grew 2.5x from ₹2.5 cr in FY25
Food services plant-level lossesRoughly ₹3 cr in FY26
Outsourced greaseproof volumeOver 300 tons per month, targeting 500 tons per month
Project Jagriti funding shortfall₹300 cr total (₹73 cr warrant, ₹146 cr bank, ₹75 cr escalation)
NCD facility drawn₹500 cr (plus ₹40 cr green shoe option)
Promoter equity infusion₹85 cr
Neo Group equity infusion₹30 cr
Effective interest rate on NCDs16.95%, with 12% payable for 12–18 months
Moratorium and principal repayment4-month moratorium, no principal repayment for 16 months
EBITDA in FY23–FY25Consistent ₹80–85 cr per year
Bare minimum EBITDA target (next 2 years)₹125–130 cr
Current operations revenueApproximately ₹420 cr
Food services current revenueApproximately ₹60 cr
Historical EBITDA margins22–25%
PM4 expected production capacity by FY27 end60%+ of full capacity
PM4 expected production capacity by FY28 end75%+ of full capacity
Base paper NSR range₹110–120 per kg
Glassine paper NSR range₹130–150 per kg
Flexible packaging NSR range₹250–300 per kg
Potential turnover from new facility (base case)₹700–750 cr, up to ₹900 cr with molded growth
Potential turnover if flexibles commercialized₹1,400–1,500 cr
Time to replace high-cost debtMinimum 15–16 months