Key Takeaways
- Flat quarter, execution held steady: Revenue was broadly flat YoY at ₹1,211 crores, with H1 net profit up 16% on disciplined project management, even as heavy monsoon rains disrupted construction activity.
- The order pipeline is the story: Bids aggregating ~₹30,000 crores are already submitted, with another ~₹50,000 crores expected over the next 12 months, setting up a potential FY’28 growth inflection.
- Margins dipped on mobilization and weather: Consolidated EBITDA margin fell to 12.42% from 13.13% YoY, squeezed by lower revenue booking, cost inflation, and the initial low-work phase on new projects.
- Balance sheet stretched temporarily: Receivables and debt both rose as milestone payments were deferred, but management calls it a timing issue and expects normalization to 40–50 receivable days.
- What to watch next quarter: Whether the ~₹30,000 crores of submitted bids begin converting to LOIs by Q4, and whether receivables normalize as promised.
Order Pipeline & Growth Outlook
- A bridge to FY’28: Management expects only marginal revenue growth (~7–8%) in FY’27, with a pickup in FY’28 once newly bid projects are awarded and pass through a 6–7 month mobilization phase. The ~₹30,000 crores of bids already submitted across ~15 projects are expected to open over the next few months, with the majority possibly opening by March.
- The next wave is large: An additional ~₹50,000 crores of projects are expected to come up for bidding over the next 12 months, spanning road and tunnel projects in Ladakh and J&K, railway infrastructure, pumped storage projects in Maharashtra, MP, and AP, and hydropower projects in various clearance stages.
- Hydropower drought, but confidence intact: No hydropower projects were finalized in the last six months, and out of 3–4 projects last year, Patel secured only one (~₹700 crores) while a large ~₹14,000–15,000 crore project went to new entrants. Management sees less competition in large hydropower versus other sectors and remains confident of winning its share.
- Bidding discipline pledged: The approach to bidding will remain selective, focusing on projects where the company can leverage its strengths and achieve sustainable returns.
- Segment expansion underway: The company is exploring road tunnel projects, high-speed rail, and pumped storage as natural extensions of existing capabilities, with no additional pre-qualification required.
Kavita Shirvaikar: “There are four, five bidders in this segment, particularly in large hydropower projects. So, compared to other sectors, we see here less competition and opportunities available in future are huge. So, we see, we are fairly confident we will get our share of work.”
Project Execution & Milestones
- Subansiri nearing the finish line: Unit 5 achieved wet commissioning and was integrated with the National Grid, bringing five of eight units online. The remaining three units are on track for completion within FY’27.
- Kwar advancing: Dam concreting crossed 4 lakh cum, the TRT outlet bridge was completed, powerhouse excavation is finished, and concreting is underway.
- Kiru approaching completion: Dam concreting reached ~12 lakh cum out of a total 12.5 lakh cum, with powerhouse slab concreting up to the service floor for all four units.
- Sleemanabad landmark: Breakthrough of India’s longest irrigation tunnel (~12 km) was achieved at the Sleemanabad project in Madhya Pradesh.
- New starts delayed: Commencement of certain new projects was delayed due to pending forest clearances, contributing to the subdued revenue booking. Management revised FY’27 revenue growth guidance to marginal, maybe 7-8%.
Margins & Profitability
- Multiple drags on margin: The Q2 consolidated EBITDA margin decline to 12.42% (from 13.13% YoY) reflects lower revenue booking, some cost inflation, monsoon disruptions, and the initial mobilization phase on projects where work volumes are still low.
- Cost pass-through with a lag: Most projects carry escalation clauses, so cost inflation is largely pass-through, but management acknowledged there may be some lag in realization.
- Profit held up despite top-line pressure: Q2 net profit rose 7.64% YoY to ₹83 crores, and H1 net profit rose 15.94% to ₹177 crores, driven by execution efficiency, cost control, and disciplined project management.
Balance Sheet & Cash Flow
- Receivables spike flagged as temporary: Receivables rose in H1 due to the timing of milestone payments on certain projects. Management characterized it as a purely temporary issue, not structural, and expects to remain on track with normal receivable days of 40–50.
- Debt ticked up on working capital: Consolidated debt increased from ₹1,187 crores (March) to ₹1,312 crores (September), partly reflecting utilization of working capital limits due to deferred milestone realizations. Some further increase is possible when new projects come, but with land sales and award monetization, no substantial year-on-year increase is expected.
- Non-core monetization progressing: ₹80 crores of the ₹100–150 crore target for the year has already been realized, via a ₹26 crore land parcel sale and a ₹55 crore SPV stake sale (ACP Tollways). The balance is expected by March through further land sales or arbitration award realization.
- Land sales: a slow grind: Management stated they are working continuously on land sales, but the pace depends on market conditions, noting that over ₹1,000 crores of land has been sold over the last four to five years. Specific location details for Panvel and Hyderabad parcels were not provided on the call.
Rahul Agarwal: “We primarily work for central PSUs. So, there, you know, cash flow realization is not a problem. Only some projects where there are some milestone payments. So, temporarily you may see cash flow up-down and that is what is being reflected in this quarter.”
Capital Allocation & Promoter Updates
- No distribution this year: Management ruled out any dividend or capital distribution in FY’27, citing the need to conserve capital for multiple bid projects that, when awarded, will require funding. A call on distribution will be taken next year based on new project awards and progress.
- CAPEX steady at ~₹150 crores per year: Planned CAPEX of ~₹150 crores annually for the next 2–3 years will be funded from client advances. The company owns four TBMs and is open to buying from India or sourcing from Germany if China export restrictions persist, though it expects those restrictions to lift soon.
- Promoter pledge reduced, more to come: Promoter pledge was reduced from ~88–90% to 67%. Management indicated it will approach lenders next year, after this year’s performance, to seek further reduction, though no specific target or timeline was given. On the question of increasing promoter stake back toward ~40%, management declined to comment on promoter sentiment.
Rahul Agarwal: “Right now, because there are multiple projects which are bidded and when they open, we will need capital for that. So, we are not looking at, you know, any sort of distribution this year. Next year, we will take a call once these projects come and how these are proceeding.”
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Subansiri completion | Remaining three units to be completed | Within FY’27 |
| Revenue growth | Marginal (~7–8%) growth | FY’27 |
| Revenue inflection | Pickup once newly bid projects are awarded and mobilized | FY’28 |
| Receivables normalization | Return to normal 40–50 receivable days | Ongoing (timing issue) |
| Non-core monetization | Balance of ₹100–150 crore target (~₹20–70 crore remaining) | By March |
| CAPEX | ~₹150 crores per year, funded from client advances | Next 2–3 years |
| Capital distribution | No dividend or distribution | FY’27 |
| Promoter pledge reduction | Approach lenders for further reduction | Next year (post FY’27 performance) |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | ₹1,211 cr, vs ₹1,208 cr in Q2 FY26 |
| Operating EBITDA | ₹150 cr, margin 12.42% vs ₹159 cr, margin 13.13% in Q2 FY26 |
| Net profit after tax | ₹83 cr, up 7.64% YoY vs ₹77 cr in Q2 FY26 |
| H1 FY27 revenue | ₹2,491 cr, vs ₹2,442 cr in H1 FY26 |
| H1 FY27 operating EBITDA margin | 13.24%, vs 13.27% in H1 FY26 |
| H1 FY27 net profit after tax | ₹177 cr, up 15.94% YoY vs ₹152 cr in H1 FY26 |
| Order book | ₹13,546 cr as of Sep 30, 2026; composition: Hydropower 64%, Irrigation 14%, Tunnelling 4%, Roads, Urban Infrastructure, and other segments 18% |
| Bids submitted | ~₹30,000 cr across ~15 projects; majority expected to open by Mar 2027 |
| Pipeline of projects coming for bidding | ~₹50,000 cr over next 12 months |
| Consolidated debt | ₹1,312 cr as of Sep 2026 vs ₹1,187 cr as of Mar 2026; term debt ₹350 cr, working capital debt ₹960 cr |
| Debt-equity ratio | 0.28 |
| Non-core asset monetization (H1 FY27) | ₹81 cr realized: ACP Tollways stake sale ₹55 cr plus land parcel sale ₹26 cr |
| Promoter pledge | 67%, reduced from ~88–90% |
| FY27 revenue growth guidance | Marginal, maybe 7–8% |
| Subansiri hydropower project | 5 of 8 units operational, supplying 1,250 MW to National Grid; remaining 3 units on track for completion within FY27 |