Key Takeaways
- Execution milestones hit, margins softened: Multiple complex hydro and underground projects reached key commissioning and excavation milestones, but margins moderated slightly on project mix and execution phasing.
- Order inflow slowed on deliberate discipline: Management walked away from large tenders where pricing turned aggressive, prioritizing margin quality over volume in technically complex work.
- Balance sheet strengthened further: Total debt reduced by INR 170 crores during the quarter, a INR 400 crores rights issue was completed, and ~INR 185 crores was realized from non-core asset monetization.
- FY27 guided for 10% revenue growth at ~13% margins: Growth reflects mobilization-phase drag on new hydro orders; margins are reset to align with new project bid realities.
- What to watch next quarter: Whether the INR 7,000–8,000 crores of expected near-term order inflow materializes, the pace of rights issue fund deployment for debt reduction, and any further evidence on competitive intensity as more large tenders open.
Order Book & Bidding Environment
- Disciplined walk-away from large tenders: In a few large tenders, pricing turned very aggressive, so the company chose not to compromise on margin standards for technically complex hydro and underground projects. The INR 15,000 crores+ project that was bid did not go to Patel; management confirmed it was not L1 and will probably not take that project.
- Near-term pipeline is substantial: INR 12,000 crores worth of bids already submitted and under evaluation, expected to open in the coming 1–2 months. Management expects to secure INR 7,000–8,000 crores in the next 6 months and INR 8,000–10,000 crores in the coming year.
- Sector pipeline building fast: INR 50,000 crores of identified pipeline expected to come up for bidding in the next 6–8 months, with another INR 30,000 crores in the following year. Projects like Sawalkote and Kamala have CC clearance and RFPs out; Etalin (3,000 MW, ~INR 30,000 crores) is advancing.
- Competitive intensity is a watchpoint: One large project saw a private, unlisted player bid at a very aggressive price. Management will comment further on competitive intensity only when more projects open.
- Order inflow timing is uncertain: Management declined to confirm the INR 8,000 crores FY26 target, stating March cannot be a cut-off and timing may slip a few months.
Rahul Agarwal: "March, we cannot give a cut-off that by March, it may happen. It may go a few months here and there, but we have INR12,000 crores, which we have already bidded and it will open in next 1, 2 months."
Project Execution & Milestones
- Major commissioning and excavation achievements: Subansiri Units 2 and 3 were fully commissioned in December 2025 and February 2026, adding 500 MW. Surge Gallery-2 excavation at Kwar was completed, concrete pouring at Kiru crossed 10 lakh cubic meters, and a 9.2 km Head Race Tunnel breakthrough was achieved at Parnai. The entire NATM tunneling scope at the PGRW underground water tunnel in Mumbai was also completed.
- Gongri Hydropower Project revived: An MOA was signed for the 144 MW Gongri project under the BOOT model. The project was revived based on government discussions; after completion, expected revenue is around INR 300 crores per annum, with a 4-year construction period and 40-year project life. A PPA is yet to be entered.
- Revenue phasing reflects hydro project lifecycle: Hydro projects typically have a 5-year tenure; the first year is mobilization, so order execution will be low. The pace is expected to pick up from FY28 onwards.
- Cost optimization pilot underway: IoT has been implemented on a pilot basis at a couple of projects, saving on diesel consumption costs and equipment running efficiency. The intent is to implement across all projects; management estimated savings at maybe 0.5% of revenues when pressed.
Financial Position & Capital Allocation
- Debt reduction continues: Total debt reduced from INR 1,603 crores (March 2025) to INR 1,433 crores (December 2025). Serviceable debt reduced by INR 200 crores during the 9-month period. Finance costs declined YoY from INR 80 crores to INR 68 crores.
- Rights issue completed at INR 400 crores: Subscribed 1.1x, primarily aimed at debt reduction. Promoters participated but not fully. Around INR 250-odd crores remained unutilized at quarter-end, expected to be deployed in the next quarter, though some may go beyond March. Rights issue expenses were INR 50 crores (~10%), which an analyst flagged as unusually high; management cited consultants and roadshows, noting it was disclosed in the offer document.
- Non-core asset monetization delivering: Approximately INR 185 crores realized during the quarter. Management expects to continue realizing another INR 100–200 crores in the next year.
- Net cash ambition: Per an analyst's math confirmed by management, the company could become net cash (leaving apart working capital debt) by FY27.
- One-time items in the quarter: An exceptional item related to new labor codes (not recurring) and a tax write-back from completion of earlier tax assessments at ITAT and CIT levels.
Margin Outlook & Competitive Dynamics
- Margins moderated on mix and phasing: Margins softened slightly compared to the previous period, driven primarily by project mix and execution phasing. Cost of materials increased as a percentage due to a change in the mix of works being executed, though corresponding cost of construction is also declining as a percentage.
- Guidance reset to ~13%: Management guided margins around 13%, down from the 13–14% previously discussed. The reset reflects new project bid realities: the last difference in bids shows competitive intensity, and margins need to align with incoming project economics.
- Excavation project margins lower but small: The INR 800 crores excavation project carries margins 100–150 bps lower than blended, but it is a small project and the company already does excavation in hydro and tunnelling projects.
- Competitive advantage stressed: Management emphasized legacy in executing complex projects, technical soundness, and experience as moats against aggressive new entrants.
Rahul Agarwal: "What we are saying now is around 13% because when we see that new projects are coming and as I just explained, the last difference in the bids, and whatever new projects are coming, so we'll have to consider and align on the margin front."
Sector Tailwinds & Strategic Positioning
- Hydropower and PSP remain the core focus: Primary focus continues to be on hydropower and pump storage projects, with strong opportunities also seen in irrigation, water resource management, river interlinking, and tunnel projects. Budget announcements for power storage projects were cited as positive, giving a huge opportunity to bid for large projects in PSP and hydropower.
- PSP and BESS are complementary, not competing: PSP projects sometimes come along with BESS; PSP projects have long life and make more sense considering overall capital cost. Sometimes PSP is an addition to an existing hydropower project.
- Geographic and segment diversification: Projects are coming up in Bhutan and Nepal. Order inflow of similar size to the current book is expected in the next 2–3 years across hydro PSP, irrigation, tunnelling, and metro rail corridors.
- Growth strategy remains calibrated: Management reiterated that growth will remain selective and profitability-driven, with no desire to take risk in complex, long-tenure, difficult projects.
Kavita Shirvaikar: "We have our legacy of executing complex projects. So we are technically sound. We have experience considering this in this challenging, you rightly said, some of the new players are bidding aggressively and we have to navigate this situation, but we have a competitive advantage because we are technically sound, we are more experienced."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | ~10% growth in FY27 | FY27 |
| FY26 revenue | Cross INR 5,000 crores | FY26 |
| New orders | Secure INR 8,000–10,000 crores | Coming year |
| Near-term order inflow | INR 7,000–8,000 crores | Next 6 months |
| Margins | Around 13% | FY27 |
| Rights issue fund utilization | Balance ~INR 250 crores deployed for debt reduction | Next quarter (some may go beyond March) |
| Non-core asset realization | Another INR 100–200 crores | Next 1 year |
| Net cash position | Net cash company (excluding working capital debt) | By FY27 (per analyst math, confirmed by management) |
| Gongri Project revenue | ~INR 300 crores per annum | After project completion (4-year construction) |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Consolidated revenue | ₹1,239 cr |
| Standalone revenue | ₹1,227 cr |
| Operating EBITDA (consolidated) | ₹145 cr, margin of 11.7% |
| Operating EBITDA (standalone) | ₹139 cr |
| Profit after tax (consolidated) | ₹71 cr, margin of 5.69% |
| Profit after tax (standalone) | ₹89 cr |
| 9M FY26 consolidated revenue | ₹3,681 cr, up 5.7% YoY |
| 9M FY26 consolidated EBITDA margin | 12.7% |
| 9M FY26 consolidated PAT | ₹223 cr, margin of 6.06% |
| FY27 revenue growth guidance | ~10% |
| Full-year EBITDA margin guidance | ~13% |
| Order book | ₹15,123 cr as of 31 Dec 2025 |
| Order inflow, 9M FY26 | ~₹3,200 cr |
| Expected order inflow, next 6 months | ₹7,000 cr to ₹8,000 cr |
| Bids under evaluation | ~₹12,000 cr |
| Identified bidding pipeline, next 1 year | >₹50,000 cr |
| Book-to-bill ratio | 3.08x |
| Revenue mix: hydro / irrigation / tunnelling / roads & others | 57% / 22% / 13% / 8% |
| Total debt | ₹1,433 cr, reduced from ₹1,603 cr in Mar 2025 |
| Working capital debt | ₹983 cr |
| Term debt | ~₹450 cr |
| Debt-to-equity ratio | 0.33x |
| Serviceable debt reduction, 9M FY26 | ₹207 cr |
| Finance cost | ₹68 cr, down from ₹80 cr in Q3 FY25 |
| Non-core asset monetization, 9M FY26 | ~₹185 cr realized |
| Rights issue completed | ₹400 cr, subscribed 1.1x |
| Rights issue funds unutilized | ~₹250 cr |
| Land bank | ~₹800 cr |
| Total awards and claims | ~₹3,000 cr, of which ₹700 cr awarded |
| Market share, 9M FY26 | ~10% (per an analyst's math) |
| Capex required for current EPC projects | ₹100 cr to ₹150 cr |