Key Takeaways
- Growth guided down, then up: FY25 revenue growth is pegged at just 10–15% as new orders sit in mobilization, but management expects a sharp reacceleration to 20–25% in FY26 when those projects hit peak execution.
- The order book is the story: A subdued FY24 inflow (elections) gives way to an INR10,000–15,000 crore FY25 target, backed by an INR80,000–1,00,000 crore pipeline and a stated ambition to reach an ~INR25,000 crore order book by year-end.
- Balance sheet repair is working: Net debt fell another INR330 crores, the debt-to-EBITDA ratio improved to 2.42x, and INR130 crores in arbitration realizations plus a INR400 crore QIP further lightened the load.
- Margins are steady, not expanding: A one-off INR50 crore arbitration gain flattered Q4; the real run-rate is the guided ~14% blended EBITDA, with no explicit expansion commitment.
- What to watch next quarter: Whether the post-election order flood actually materializes in Q2, the pace of mobilization on the Dibang hydro project, and any progress on land bank monetization now that elections are over.
Order Book & Pipeline
- FY24 was a planned pause: Order inflow was subdued as expected because of the general elections; a large number of orders were deferred and are now expected to be received in FY25.
- The FY25 ambition: Management expects INR10,000–15,000 crores of order inflow this year, targeting an order book of ~INR25,000 crores by the end of FY25.
- Pipeline depth: The bidding pipeline stands at INR80,000–1,00,000 crores, with ~INR10,000-odd crores in bids already submitted; how much of the pipeline will be bid this year has not yet been identified.
- Recent win: A letter of acceptance for an INR525 crore irrigation project in Telangana (company share ~INR260 crores, 2-year execution) was received in Q4.
- Dibang hydroelectric project: The contract is awarded and the project is in mobilization; revenue is expected to start from Q3 FY25.
- Tunnelling order book share: Expected to remain in the range of 10% to 15% of the total order book.
Kavita Shirvaikar: "Sir, for hydropower projects for 6 to 9 months goes for mobilization of the site, and it will start giving revenue -- peak revenue at the third year. Second year, it will start picking up -- giving of the revenue. So this is the cycle for the hydro sector."
Revenue Growth Trajectory
- FY25: a mobilization year: Revenue growth is guided at 10–15% because orders take 4–5 years to execute and the first 6–9 months go into site mobilization; the maximum revenue impact from current orders comes in FY26.
- FY26: peak execution: Growth is expected to jump to 20–25% as projects received last year and in FY25 reach their peak execution phase. Some projects that were on peak cycle (Sela Pass tunnel, T-15 tunnels) have completed, creating a temporary gap.
- FY27: sustained momentum: Management expects around 20% year-on-year growth to continue into FY27.
- Hydro cycle mechanics: In hydropower, 6–9 months go to site mobilization, revenue starts picking up in the second year, and peaks in the third year, a phasing that underpins the FY26 acceleration.
Hydropower & Sector Tailwinds
- Dominant market position: The company is involved in executing work on projects totaling around 8 GW out of the 18 GW of hydropower projects currently under construction in India, representing around 45% of all projects under execution.
- Traditional share: The company has historically held around a 25% share in hydro project infrastructure, so the current 45% execution share signals a significant over-indexing on the current build-out.
- The pipeline ahead: 19 GW of projects have been concurred by the Central Electricity Authority and are ready for construction; another 18 GW are under survey or investigation and expected to come up for bidding within 1–2 years, with a target completion by 2030.
- Pumped storage: 39 hydro pumped-storage projects totaling 47 GW are being pursued for commissioning by FY29–30.
- Tunnelling: A pipeline of at least 875 tunnels spanning ~2,600 km represents enormous potential in the coming years.
- Irrigation: The PM Krishi Sinchayee Yojana has an outlay of INR93,068 crores for 2021–26, and the Ministry of Jal Shakti received INR98,000 crores in the interim budget, with interlinking rivers projects offering huge potential.
- Competitive moat: Management does not see new companies entering the hydropower space to offer stiff competition.
Kavita Shirvaikar: "Out of the 18 gigawatt of hydropower project under construction in India, we are happy to share that our company is involved in executing work in projects of around 8 gigawatts, which is around 45% of the total projects currently under execution."
Balance Sheet & Capital Allocation
- Debt reduction trajectory: Net serviceable debt was reduced by INR330 crores in FY24; debt-to-equity improved from 0.61 to 0.6, and debt-to-EBITDA from 2.8 to 2.42.
- Five-year deleveraging: Debt has been reduced from INR5,500 crores to INR1,800 crores over five years through the sale of non-core assets (INR1,500 crores sold) and claims (INR2,000 crores).
- QIP deployment: The INR400 crore QIP proceeds will first park in working capital limits, then be redrawn for new projects, a mix of debt reduction and working capital for new projects.
- Future debt reduction: Management expects to reduce term debt by ~INR700–800 crores over the next 3–4 years, with ~INR200 crores targeted for FY25.
- Net debt-to-EBITDA target: A target of around 2.25x for FY26, excluding client advances.
- Finance cost outlook: Overall finance costs are not expected to rise even with increased projects, as debt will be consistently reduced.
- Arbitration realizations: INR130 crores was realized in Q4 under the Vivad se Vishwas Scheme; INR150–200 crores is expected in FY25, with INR200–300 crores per annum on average continuously thereafter.
- Land bank monetization: No material progress last year; management expects traction post-elections and will look to sell land parcels in the next two years if right values are obtained, selling upfront only rather than tying up with a developer.
- No further equity dilution: Management stated explicitly there are no plans to raise more equity in the near future.
Kavita Shirvaikar: "If you see last 5 years, we have been consistently reducing the debt. From INR5,500 crores, it is now INR1,800 crores. So now balance noncore asset is INR1,000 crores. We already sold in the past is around INR1,500 crores. And claim also, INR2,000 crores. So INR3,500 crores, we already sold and reduced the debt, and balance is INR1,000 crores. And like dilution also, we have no further plans to raise equity -- more equity in near future."
Margins & Working Capital
- Q4 margin one-off: Consolidated Q4 EBITDA margin expansion to 17% included a one-off INR50 crore Vivad se Vishwas arbitration income flowing through the P&L in one SPV, making consolidated EBITDA higher than standalone.
- Steady-state guidance: Operating EBITDA margins are expected to be maintained at ~14% on a blended basis; management said if they can improve, that is better, but offered no explicit expansion commitment.
- Working capital improvement: The net working capital cycle has been reduced from 250-odd days to 180 days, driven by an improved collection cycle and a government focus on clearing payments faster.
- New project dynamics: New projects carry a net working capital cycle of only 3 to 4 months, which is bringing down the overall reported working capital number as the mix shifts toward newer contracts.
- Project completions: Some 4–5 projects in the 90–100% completion range may get completed this year, though the timing depends on whether additional works are awarded.
Strategic Moves & Other Updates
- Sela Pass milestone: The Sela Pass Project, the world's longest bi-lane tunnel at an altitude over 13,000 feet, was inaugurated by the Prime Minister on March 9 and officially recognized as the highest tunnel in India by the International Book of Honour, England.
- Tunnelling startup stake: The company invested in a 10% strategic stake in a startup specializing in servicing tunnel boring machines, as an ancillary business to its EPC operations; any increase in stake depends on future performance.
- Promoter pledge: Management will touch base with lenders to reduce the pledge cover as company progress has improved.
- 75th year: FY24 marks the company's 75th year of existence.
Kavita Shirvaikar: "The project is of national importance, as it will benefit both strategically, as our troops and machinery can now reach the border, as well as self-economic progress of the region."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 10–15% YoY | FY25 |
| Revenue growth | 20–25% YoY | FY26 |
| Revenue growth | ~20% YoY | FY27 |
| Order book | ~INR25,000 crores | End of FY25 |
| Order inflow | INR10,000–15,000 crores | FY25 |
| EBITDA margin | Maintain ~14% blended | Ongoing |
| Term debt reduction | ~INR200 crores | FY25 |
| Term debt reduction | ~INR700–800 crores cumulative | Over next 3–4 years |
| Net debt-to-EBITDA | ~2.25x (excluding client advances) | FY26 |
| Arbitration realizations | INR150–200 crores | FY25 |
| Arbitration realizations | INR200–300 crores per annum | Ongoing average |
| Land monetization | Sell land parcels if right values obtained | Next 2 years |
| Dibang hydro revenue start | Revenue to commence | Q3 FY25 |
Key Metrics
| Metric | Q4 FY24 |
|---|---|
| Consolidated revenue | ₹1,343.18 cr, up 11.5% YoY |
| Standalone revenue | ₹1,256.9 cr, up 5.5% YoY |
| Consolidated operating EBITDA | ₹237.6 cr, up 42.3% YoY; includes ~₹50 cr one-off from arbitration settlement |
| Consolidated operating EBITDA margin | 17.7% (per an analyst's math); ~14% normalized excluding one-off |
| Consolidated net profit | ₹123.37 cr, up 46% YoY |
| Standalone net profit | ₹73.18 cr, down 12.9% YoY |
| Consolidated finance cost | ₹93 cr, down from ₹103 cr in Q4 FY23 |
| Consolidated diluted EPS (continuing ops) | 3.54 for FY24, up from 2.23 in FY23 |
| Order book | ~₹18,600 cr as of Mar 31, 2024 |
| New orders received in FY24 | ₹4,000 cr |
| Order inflow guidance for FY25 | ₹10,000–15,000 cr expected |
| Revenue growth guidance for FY25 | 10–15% |
| Revenue growth guidance for FY26 | 20–25% |
| Gross debt (consolidated) | ₹1,885.49 cr as of Mar 31, 2024 |
| Net serviceable debt | ₹2,645.58 cr, down ₹330 cr YoY |
| Debt-to-equity ratio | 0.6, improved from 0.61 YoY |
| Debt to operating EBITDA | 2.42, improved from 2.8 YoY |
| Net working capital cycle | 180 days, improved from ~250 days last year |
| Arbitration claims filed | ~₹4,331 cr |
| Arbitration cash realized in Q4 | ~₹130 cr under Vivad se Vishwas Scheme |
| Employee base | ~4,500 |
| Promoter pledge | 80% of promoter-held shares |