Legacy Clean-Up: The Quarter That Changed the Book

Balaji: "We are happy to state that all the 3 cases have more or less achieved closure in the first quarter itself."

Disbursement Trajectory: Slow Start, Steep Ramp

Sanjeev Kumar: "During the month of July, already, we have sanctioned something around INR600 crores of loans proposals and proposals amounting to maybe a little more than INR1,000 crores are already in pipeline at different stages of sanction and due diligence processes."

Strategic Shift: Private Sector Becomes the Engine

Balaji: "So actually what we did in the entire financial year in private sector entities; close to 45% of that we achieved it in the first quarter."

Funding & Ratings: The Next Catalysts

Balaji: "Rating agencies don't give any conditions. It's a function of a few parameters. One, the intrinsic health of the business; Two, the surround effects... Three, what's happening in the external environment."

Team & Infrastructure Build-Out


Guidance & Commitments

CommitmentSpecificsTimeline
Full-year disbursement₹4,000 cr target; management confident despite Q1 shortfallFY26
Q2 disbursement catch-up₹1,000-1,200 cr targeted; shortfall covered by SeptemberQ2 FY26
Vento final closureBalance payment of ~₹95 cr expected; would remove ~10% of Gross NPAEnd of August
AUM growth7-9% quarter-on-quarter growth committedOngoing
Fundraising sanctionsExpecting sanctions from existing, new and overseas lendersThis quarter (Q2 FY26)
Rating improvementExpecting upgrade at renewal, driven by cleaned-up book and no qualificationsAugust/September
Disbursement case volume8-12 cases sanctioned and disbursed per quarterOngoing

Key Metrics

MetricQ1 FY26
Total income₹142 cr, down from ₹155 cr in Q4 FY25
Profit after tax₹137 cr, up from ₹58 cr in Q4 FY25
Gross Stage 310.22%, improved from 15%
Net Stage 34.13%, improved from 6.56%
Return on assets (annualized)9.77%, improved from 4.02%
Cost of borrowing9.67%, reduced from 9.69% in Q4 FY25
Disbursements₹138 cr, entirely to private sector; up from ₹50 cr in Q4 FY25
Full-year disbursement target₹4,000 cr, management confident of achieving despite Q1 shortfall
Q2 FY26 disbursement target₹1,000–1,200 cr
AUM growth target7–9% quarter-on-quarter, management reaffirmed
Average disbursement ticket size~₹35 cr
Proposals evaluated in Q1~₹1,200–1,300 cr
July sanctions~₹600 cr of loan proposals sanctioned
Proposals in pipeline (as of July 31)>₹1,000 cr at various stages of due diligence
Scheduled repayments in Q1₹553 cr
Full-year expected prepayments and repayments₹1,000–1,500 cr (scheduled and unscheduled)
Gross Stage 3 resolved in Q138% of Gross Stage 3 resolved
Remaining Gross Stage 3 in advanced resolution30% of remaining Gross Stage 3
NSL resolution recovery₹125 cr entire principal received back
Vento resolution recovery₹115 cr winning bid; ~₹20 cr performance guarantee paid, balance expected by end of August
IL&FS resolutionUpgraded to Standard post RBI approval and investment-grade rating from two agencies
FY25 private sector disbursement (full year)₹296 cr
FY24 private sector disbursement (full year)₹80–90 cr
Quarterly cases sanctioned and disbursed (expected run-rate)8–12 cases per quarter
Target ticket size: core infrastructure₹120–150 cr