Key Takeaways
- Execution engine running hot, but revenue stalled: Record project commissioning (Dausa in 8 months) and a 51% YoY capex jump to ₹6,981 Cr sit alongside stagnant transmission revenue, as new TBCB additions barely offset the natural decay of older regulated assets.
- The order pipeline is enormous, not the backlog: Work in hand stands at ~₹1,48,000 Cr, but management points to a further ~₹1,40,000 Cr of projects up for grab and a ~₹5.5-6 lakh Cr market over 5 years. The story is about future awarding, not just current backlog.
- Consolidated profit dipped ~2% YoY on one-offs: A ₹70 Cr CSR spike and a ₹70 Cr loss from the EESL JV masked a 7% rise in standalone profit. The core transmission business is healthier than the headline suggests.
- Supply chain is the critical path, not demand: With only 2 transformer suppliers per tender and full order books, management is pre-ordering 30 transformers at a time to secure capacity, calling it a "very big risk for every one of us."
- What to watch next quarter: The Kenya agreement signing, the Leh HVDC bid award decision, and whether the ₹22,000 Cr FY26 commissioning target stays on track after a light ₹3,000 Cr guided for Q2.
The Revenue Stagnation Puzzle
Despite adding ~₹9,000 Cr in capitalization, transmission revenue was flat because ~90% of assets are under the RTM (regulated) model. After the initial 12-year period, depreciation drops from 5.28% to ~1.8%, and once loans are repaid in 10-12 years, the interest pass-through also falls away. This structural decay must be offset by new TBCB projects; if annual TBCB commissioning falls below ₹20,000 Cr, revenue may stay constant or even decline.
- The math is unforgiving: Management did not quantify how much of the stagnation is explained by RTM decay versus other factors, but the mechanism is clear: every year of low commissioning digs a deeper hole that future projects must fill.
- The offset is in the pipeline: FY26 commissioning is targeted at ₹22,000 Cr, and FY27 at ₹20,000-25,000 Cr, both above the ₹20,000 Cr threshold needed to hold revenue flat. The risk is execution slippage, not a lack of projects.
Tyagi: "If we commission more and more projects, then only our revenue will become more and more. Otherwise, if we are not able to commission more than ₹ 20,000 Crore projects in TBCB, our revenue model, it will be almost constant or sometimes it may reduce also."
Capex & Execution: Records and Risks
- Capex surged 51% YoY to ₹6,981 Cr, with commissioning at ₹2,800 Cr. Key RE evacuation stations at Khavda-II, Khavda-III, and Kurnool III were commissioned.
- Dausa substation set a new speed record: a 765 kV/400 kV station commissioned in ~8 months (Dec '24 to Jul '25), beating the earlier Sikar record of ~9 months. The Namsai-Kathalguri TBCB line was commissioned 5 months ahead of schedule.
- FY26 commissioning is back-loaded: Q2 is guided at only ₹3,000 Cr, with Q3 at ~₹7,000 Cr and Q4 at ~₹8,000 Cr. Any Q3/Q4 delay concentrates risk in the second half.
- Right of Way remains the binding constraint: Management called RoW "a very big problem in India" and "very very challenging." Government guidelines from June 2024 and March 2025 have improved compensation (market rate replacing circle rate, dual valuer mechanism), and progress is visible in Maharashtra and Gujarat, but Delhi and Haryana remain difficult.
- Mechanization is accelerating: Cranes, mobile tower cranes (team sent to China), drones for cement and component transport, and drone-based pilot stringing are being deployed to speed up execution.
Tyagi: "Let us agree that RoW is a very big problem in India and making a transmission line is very very challenging."
The Opportunity: Pipeline, Not Backlog
Management pushed back on the narrative of a declining work-in-hand, arguing the real story is the forward pipeline. Work in hand is ₹1,48,000 Cr plus ₹41,000 Cr work in progress, totaling ~₹1,90,000 Cr. Beyond that, ₹29,000 Cr of projects are approved but yet to be floated, ₹39,000 Cr are already bid out, and ₹75,000 Cr were recently approved in the NCT, summing to ~₹1,40,000 Cr up for grab.
- The 5-year market is estimated at ₹5.5-6 lakh Cr, implying ~₹1 lakh Cr in annual awards. Management's target is to capture a dominant share.
- Intrastate TBCB is opening up: Madhya Pradesh, Maharashtra, and Karnataka have introduced TBCB thresholds (₹250 Cr, ₹500 Cr, and ₹250 Cr respectively), creating a new layer of opportunity below the interstate level.
- Capex guidance steps up sharply: ₹28,000 Cr in FY26, ₹35,000 Cr in FY27, and ₹45,000 Cr in FY28. Financing is not a constraint: 20% equity for TBCB (~₹7,000-8,000 Cr/year) is covered by internal profit of ~₹16,000 Cr, and debt is available at 6.9-6.95%.
HVDC: The Next Growth Engine
- Leh-Kaithal is the near-term catalyst: Only one party bid; queries are being addressed and likely resolved in ~2 months, after which an award decision is expected. Management is also exploring AC transmission as a parallel alternative, but stated HVDC is "most suitable" given the weak grid in the region.
- A deep pipeline is forming: Khavda KPS 3 to South Olpad (VSC, bid submitted, e-RA anytime); Barmer to South Kalamb (LCC, approved in NCT, bidding in 2-3 months); Bikaner V to Begunia (6,000 MW, commissioning 2029-30); plus India-Sri Lanka, Paradeep to Andaman, and Imphal to Myanmar back-to-back HVDC links.
- Inter-country projects will use VSC technology for very long distances, with Saudi Arabia, Oman, and UAE identified as target geographies.
- Management did not provide a clear LCC vs VSC split with timelines when asked, leaving some uncertainty about the mix and margin profile of the HVDC pipeline.
Tyagi: "HVDC is most suitable technology for evacuating power from Leh to Kaithal. Because there is no generation, there is no grid connectivity, transmission network is very, very weak, power system is very, very weak."
Consolidated Profit: One-Offs Obscure the Core
- Standalone profit rose ~7% YoY, but consolidated PAT fell ~2%. The gap is explained by two items: ₹70 Cr of additional CSR expenditure versus Q1 last year, and a ₹70 Cr loss from the EESL joint venture. Prior-period one-time items also contributed to the comparison.
- Consolidation mechanics: Standalone profit of ₹3,653 Cr plus subsidiary profit of ₹364 Cr, but ₹342 Cr of dividends taken to POWERGRID get eliminated on consolidation, leaving only ~₹20 Cr of subsidiary contribution before the JV loss further reduces it.
- Operating expenses rose 28% QoQ (₹1,462 Cr to ₹1,873 Cr), driven by SCA accounting for the Gujarat smart metering business (~₹135 Cr), extra CSR of ₹79 Cr, R&M expenditures, and FERV movements.
Supply Chain: The Real Bottleneck
- Transformer supply is critically tight: Management stated that tenders attract "hardly 2 manufacturers or 2 suppliers," and because "everybody's hands are full," suppliers dictate pricing. This was called "a very big challenge" and "a very big risk for every one of us."
- Advance procurement is the mitigation: The company is ordering 30 transformers in a single package, enough for 2-3 projects, even before projects are formally in hand. All packages are awarded within 3 months of winning a project, and costs are locked in at the e-RA stage.
- Management declined to disclose how much of the work in hand has already been ordered out versus what remains to be procured, and declined to comment on relative EPC contractor performance.
Tyagi: "Like whenever we are coming out with any bid, we are hardly getting 2 manufacturers or 2 suppliers for each tender and because everybody's hands are full and whatever cost they are asking, we have to give that cost. So, it is a very big challenge, and it is going to be a very big risk for every one of us."
New Business & ESG Initiatives
- Kenya project nearing signing: An agreement with the Government of Kenya for a 400 kV and 220 kV transmission project is in final approval stages and likely to mature this month (August 2025).
- Green hydrogen pilot at Neemrana: Solar panels will generate green hydrogen during the day; at night, the hydrogen will be used to generate electricity back to the grid. The order has been placed.
- BESS participation planned: The company is likely to bid for Rajasthan's 2,000 MW/4,000 MWh tender, and aims to become "a big player" in BESS and green hydrogen over the next 2-3 years.
- ESG milestones with hard dates: 50% electricity consumption from RE by December 2025; rooftop solar on all buildings by December 2025; 4 more all-women "Pink" substations by October 2025; Net Zero by 2047.
- Telecom and consultancy are growing: Telecom income rose from ₹246 Cr to ₹289 Cr, with the first international ILD link of 10G commissioned. Consultancy income reached ₹329 Cr, including ₹153 Cr from the new smart meters business.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 capex | ~₹28,000 Cr | FY26 |
| FY27 capex | ~₹35,000 Cr | FY27 |
| FY28 capex | ~₹45,000 Cr | FY28 |
| FY26 commissioning | ~₹22,000 Cr (Q2: ₹3,000 Cr, Q3: ~₹7,000 Cr, Q4: ~₹8,000 Cr) | FY26 |
| FY27 commissioning | ₹20,000-25,000 Cr | FY27 |
| Kenya project signing | Agreement with Govt of Kenya | August 2025 |
| Leh HVDC bid decision | Queries resolved, award decision | ~2 months |
| Barmer-South Kalamb HVDC bidding | LCC HVDC, approved in NCT | 2-3 months |
| Bikaner V-Begunia HVDC commissioning | 6,000 MW | 2029-30 |
| Pink substations | 4 more (total 8) | October 2025 |
| Rooftop solar on all buildings | Installation complete | December 2025 |
| 50% RE electricity consumption | Target | December 2025 |
| Net Zero | Corporate target | 2047 |
| ₹67,000 Cr projects finalization | Likely within FY26 | FY26 |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Total income (consolidated) | ₹11,444 cr |
| EBITDA (consolidated) | ₹9,527 cr |
| Profit after tax (consolidated) | ₹3,631 cr, declined ~2% YoY |
| Profit after tax (standalone) | ₹3,653 cr, increased ~7% YoY |
| Earnings per share | ₹3.9 |
| Book value per share | ₹103 |
| Return on net worth | 3.76% (for Q1) |
| Net worth | ~₹96,000 cr |
| Gross fixed assets | ~₹2,92,000 cr |
| Debt-equity ratio | 58:42 (58% loan, 42% equity) |
| CAPEX incurred | ₹6,981 cr, vs ₹4,615 cr in Q1 FY25 |
| Capitalization | ₹1,800 cr |
| Commissioning | ₹2,800 cr, vs ~₹2,400 cr in Q1 FY25 |
| Projects in hand | ~₹1,48,000 cr (TBCB ~₹99,000 cr, RTM ~₹9,000 cr, new RTM ~₹37,000 cr, others ~₹2,600 cr) |
| Capital work in progress (incl. advances) | ~₹41,000 cr |
| Billing | ₹8,434 cr |
| Realization | ₹8,671 cr |
| Outstanding | ₹3,151 cr, vs ₹5,548 cr in Q1 FY25 |
| System availability | 99.84% |
| Tripping per line | 0.27 (last year; 1 line trip in almost 4 years) |
| Telecom income | ₹289 cr, vs ₹246 cr in Q1 FY25 |
| Consultancy income | ₹329 cr, includes ₹153 cr from smart meters |
| CSR expenditure increase (distortion) | ₹70 cr more than Q1 FY25; JV loss (EESL) of ₹70 cr |
| FY26 CAPEX target | ~₹28,000 cr (RTM ~₹3,500 cr, TBCB ~₹19,000 cr, others ₹5,300 cr) |
| FY26 commissioning target | ~₹22,000 cr (Q2: ₹3,000 cr, Q3: ~₹7,000 cr, Q4: ~₹8,000 cr) |
| FY27 CAPEX plan | ~₹35,000 cr |
| FY28 CAPEX plan | ~₹45,000 cr |