Key Takeaways
- Steady quarter, capex inflection ahead: Standalone PAT grew to ₹3,834 crores from ₹3,651 crores YoY, but the real story is capex guidance jumping from ₹8,800 crores to ~₹10,000 crores this year, with next year targeting ₹12,500 crores or higher.
- The bidding pipeline is the growth engine: ₹59,700 crores of projects are currently under bidding, with another ₹67,000 crores approved and ₹45,000 crores in planning, all feeding a 9-year capex vision of ₹1,80,000 crores.
- Leh Ladakh is the signature project: Cabinet approved the ₹20,700 crore Phase-II HVDC line (40% grant, 5-year timeline), but high-altitude working windows of only 5-6 months and unproven HVDC equipment performance add execution risk.
- New businesses are small but real: Telecom carved out into a subsidiary, a ₹713 crore hyperscale data center pilot approved, and 69 lakh smart meter contracts won, diversifying beyond pure transmission.
- What to watch next quarter: Whether the CERC draft tariff regulations (due November/December) change the return framework, how quickly the ₹60,000 crore pipeline converts to wins, and any progress on the Raigarh-Pugalur dues collection from Tamil Nadu and Telangana.
Capex Trajectory & the Transmission Super-Cycle
- FY24 capex revised up sharply: Originally guided at ₹8,800 crores (₹5,000 RTM + ₹3,800 others), now expected to cross ₹10,000 crores because of new project wins. Capitalization target for the year is ₹10,000 crores, with ₹4,000 crores already achieved in H1.
- FY25 set to be materially larger: Initial target of ₹12,200 crores now projected at ₹12,500 crores, with management hoping it crosses ₹15,000 crores if bigger HVDC projects are won. Capitalization target for FY25 is above ₹15,000 crores, projecting ~₹17,000 crores including TBCB.
- The 9-year vision: PowerGrid envisages ₹1,80,000 crores of capex through 2032, capturing ₹1,16,500 crores of the ₹2.4 lakh crore investment needed for 500 GW of renewable energy by 2030. The conservative TBCB share is ₹37,000 crores, with cross-border at ₹10,000 crores, international projects at ₹7,500 crores, and new businesses adding another ₹17,000 crores.
- Pipeline depth supports the ambition: ₹59,700 crores of projects are currently under bidding, expected to be bid out in 12-18 months. Beyond that, another ₹67,000 crores is already approved in NCT and awaiting bidding, plus ₹45,000 crores in the planning stage. Execution timelines run 24-30 months, longer for HVDC.
- Intra-state transmission is an uncounted opportunity: States are executing via TBCB, JV, or EPC; Uttar Pradesh has come up with 2-3 TBCB projects and executed three, while Madhya Pradesh executed one. PowerGrid conservatively assumes a 50% strike rate on the TBCB portion, targeting ₹30,000-35,000 crores over 9 years, but this is not yet included in projects-in-hand.
Ravisankar: "company there is no change in the basics and the operational maintenance and the availability continue to be above 99.75 and then the lot of CapEx is on the growing side and we hope that it crosses at least 15,000 next year. This is what is our aspiration and then a lot of outlook is bright"
Leh Ladakh: The Marquee Project with Real Constraints
- Project scope and economics: Cabinet approved Phase-II of the 13 GW RE project, covering the Pang to Kaithal HVDC line at an envisaged cost of ₹20,700 crores, with 40% financial assistance as a grant (₹8,000 crores) and PowerGrid's capex portion at ₹13,000 crores. The earlier figure of ₹27,000 crores was incorrect.
- Timeline and terrain risk: The 5-year completion timeline is ambitious given the site sits at 4,700 meters above sea level with sub-zero temperatures, leaving a working window of only 5-6 months per year. Front-end engineering design studies have started with two HVDC players, with the first phase report expected by March-April 2024.
- Award timing is uncertain: Management is targeting an award in FY25 Q4 or FY26 Q1, but this depends entirely on completing both phase 1 and phase 2 feasibility studies, plus validating HVDC equipment performance in high-altitude conditions. Formal communication from the government is still pending.
Ravisankar: "It envisages 40% of the financial assistance in the form of grant, and it has a timeline of 5 years for completion. And, being a difficult terrain at a high altitude of 4,700 mts above sea level with sub-zero temperatures, the working conditions there are hardly 5-6 months in a year."
TBCB Wins & the Competitive Position
- Wins are stacking up: PowerGrid won two TBCB companies this quarter (Rajasthan Phase-III, Part C1 and Part H) with an annual tariff of ₹361 crores, bringing the H1 total to four projects. One more was won subsequent to Q2 (Phase-IV Part A). Management expects to acquire 1-2 more SPVs in the next few months, with two additional bids submitted and awaiting ERA.
- Supply chain is manageable for now: Since many projects are coming up suddenly, there are challenges in transformers, HVDC equipment, and other gear, especially with RE integration demand in Europe. However, for timelines of 18 months and above, suppliers are available. Most TBCB contracts are on firm price, insulating PowerGrid from price escalations, and the company predominantly uses its own structures, conductors, and insulators.
- STATCOM demand is a structural tailwind: The 500 GW non-fossil fuel target requires extensive dynamic compensation for renewable intermittency, meaning a lot of STATCOMs must be set up. Execution is not a major problem, though final commissioning takes time because the technology is relatively new. Suppliers include Siemens, Hitachi, Hyosung, with GE trying to enter.
Ravisankar: "if the normally, when the timeline is 18 months and above, there are players who can supply the equipment. This is one part and as far as TBCB and most of our contracts are on firm price, we are somewhat insulated from the price escalations"
New Business Diversification
- Telecom carved out and on track: The telecom business was transferred to PowerGrid Teleservices Ltd (100% subsidiary) effective 1st October 2023, shown as discontinuing operations under Ind AS. Q2 telecom income was ₹202 crores, with cumulative H1 at ₹393 crores, on track for the ₹800 crores annual target.
- Data center pilot approved: The board approved ₹713 crores for a hyperscale data center in Manesar, initially two floors with scalability to six. Award is under progress and completion is expected in 12-15 months. Management is exploring data centers in other areas and believes being a government entity may give an edge on storage orders, though no specific tenant commitments were disclosed. The 10-year target is ₹1,000 crores, with upside if the pilot succeeds.
- Smart metering entry: Contracts for 69 lakh smart meters were won from two Gujarat discoms, with a back-to-back vendor tie-up for execution. Supply will start by end of December or early January; technical parameters are finalized and meters are under manufacturing. The 9-year target for smart metering is ₹15,000 crores.
- International ambitions are early-stage: A proposal was submitted to the Kenyan government in association with Africa 50 for a transmission line via a 40:60 JV SPV, with similar talks ongoing in Tanzania. PowerGrid is also preparing the DPR for India-Sri Lanka connectivity. Undersea cable projects connecting Oman, Singapore, Maldives, and Sri Lanka are in very preliminary feasibility studies with no concrete agreement or order yet.
Ravisankar: "As regards this undersea cable, it is in a very preliminary stage. There are talks about connecting Oman or connecting Singapore or connecting Maldives, Sri Lanka. So, there are some inter-country connections, sea cable projects are understudy. As of now, there is no concrete agreement or order from any of the countries."
Financial Health & Dues Resolution
- Balance sheet strengthening: The debt-to-equity ratio improved from 61:39 last year to 58:42 now. Average borrowing cost ticked up slightly to 7.61% from 7.59% last quarter due to hardening domestic rates, though most interest rates in RTM are pass-through.
- Realisation and dues: Realisation stands at 92.37%, with payments received under LPS Rules of 2022. Against ₹2,400 crores of dues from six discoms, ₹1,383 crores has been received. Major outstanding dues are from Tamil Nadu, Jammu & Kashmir, Telangana, and Uttar Pradesh.
- Raigarh-Pugalur dispute nearing resolution: On 27th October, CERC issued an order making the Raigarh-Pugalur line a 50-50 national-regional component split, versus the earlier 30-70. Telangana adjusted ~₹450 crores against this and will now pay; Tamil Nadu also has to pay. Billing at 50:50 will apply from 27th October. Management feels this should see an end, which would bring down the Tamil Nadu and Telangana dues meaningfully.
- H1 PAT comparison note: Standalone H1 PAT of ₹7,377 crores and consolidated H1 PAT of ₹7,379 crores were slightly lower than the previous H1 (₹7,417 crores and ₹7,452 crores respectively) because the prior year included one-time income from tariff orders for Raigarh-Pugalur accounting for previous years.
Ravisankar: "we have again requested them to make the payment of whatever the adjustment and Telangana will be paying now. So, they have adjusted around 450 crores which they will be paying now and Tamil Nadu also has to pay... As of now, we feel that yes, it should see an end."
Regulatory & Structural Watchpoints
- CERC tariff regulations are the near-term overhang: The approach paper has been published and PowerGrid has submitted its comments. Draft regulations are expected in November/December 2023. The outcome will set the return framework for the next control period and is a material input to future earnings visibility.
- InvIT monetisation is constrained by policy: Management declined to comment substantively on PowerGrid InvIT, citing its status as a separately listed entity. On the question of why stake transfers have not followed the scheduled timeline, management pointed to NMP guidelines that do not permit permanent share transfers to any SPV, including PG InvIT. Securitization of cash flows has been adopted as an alternative monetization method. One project (Kala Amb, ~₹20-30 crores) completed five years last FY; two more will complete five years this year, and one more by December 2023. A decision on the balance 26% stake transfer is likely in Q4 after valuation of all four.
- Consultancy income is declining: Consultancy revenue is slightly down compared to previous years because major elements of the NERPSIP scheme have been commissioned. Management is looking for other business opportunities to improve this line, with two new international assignments won in Fiji and new domestic assignments in bay maintenance.
Ravisankar: "As of now, the NMP guidelines doesn't permit to transfer the shares permanently to an SPV, not only PG InvIT to any anyone. So, this is what the NMP guideline says."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY24 capex | ~₹10,000 crores (up from ₹8,800 crores guided) | FY24 |
| FY24 capitalization | ₹10,000 crores (₹4,000 crores already done in H1) | FY24 |
| FY25 capex | ₹12,500 crores, with aspiration to cross ₹15,000 crores if HVDC projects won | FY25 |
| FY25 capitalization | Above ₹15,000 crores, projecting ~₹17,000 crores | FY25 |
| Leh Ladakh Phase-I study | First phase report from HVDC players | March-April 2024 |
| Leh Ladakh project award | Targeting award | FY25 Q4 to FY26 Q1 |
| Manesar data center | Completion | 12-15 months |
| Nagda 85 MW solar plant | Commissioning | ~12 months |
| Smart meter supply start | Supply from Gujarat orders to begin | End of December 2023 / early January 2024 |
| CERC draft tariff regulations | Publication expected | November/December 2023 |
| InvIT balance stake transfer | Decision on 26% stake transfer for 4 eligible projects | Q4 FY24 |
| Bidding pipeline conversion | ₹59,700 crores under bidding to be bid out | 12-18 months |
| 9-year capex target | ₹1,80,000 crores total | By 2032 |
| 9-year intra-state TBCB target | ₹30,000-35,000 crores (assuming 50% strike rate) | By 2032 |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Standalone revenue | ₹11,206 cr, up from ₹11,004 cr QoQ |
| Standalone PAT | ₹3,834 cr, up 5% QoQ from ₹3,651 cr |
| Consolidated income | ₹11,530 cr, up from ₹11,349 cr QoQ |
| Consolidated PAT | ₹3,781 cr, up 4% QoQ from ₹3,650 cr |
| H1 standalone revenue | ₹22,094 cr, vs ₹22,094 cr in H1 FY23 |
| H1 standalone PAT | ₹7,377 cr, vs ₹7,417 cr in H1 FY23 (prior year had one-time income) |
| H1 consolidated income | ₹22,788 cr, vs ₹22,788 cr in H1 FY23 |
| H1 consolidated PAT | ₹7,379 cr, vs ₹7,452 cr in H1 FY23 |
| H1 capex | ₹4,246 cr, against full-year target of ₹8,800 cr; full-year now expected ~₹10,000 cr |
| H1 capitalisation | ₹4,000 cr, ₹1,600 cr in Q1 plus ₹2,400 cr in Q2; full-year target ₹10,000 cr |
| FY25 capex target | ₹12,500 cr, initial target as of now, could rise with HVDC wins |
| FY25 capitalisation target | ~₹17,000 cr, above ₹15,000 cr projected |
| System availability | 99.85% for H1 FY24, above 99.75% |
| Tripping rate | 0.16, improved from 0.20 in previous half year |
| Debt-to-equity ratio | 58:42, improved from 59:41 last quarter and 61:39 last year |
| Borrowing cost average | 7.61%, up from 7.59% last quarter on hardening rates |
| Realisation rate | 92.37%, up from last quarter |
| Work in hand | ~₹60,000-65,000 cr, including recently won projects; base ₹50,500 cr plus ₹8,000-9,000 cr |
| Projects under bidding pipeline | ₹59,700 cr, expected to be bid out in 12-18 months |
| TBCB projects won in FY24 (up to Q2) | 4 projects, annual tariff ₹703 cr, NCT cost ₹6,393 cr; plus one subsequent win of ₹4,700 cr NCT |
| TBCB half-yearly revenue (standalone) | ₹1,300 cr, with profit of ₹413 cr |
| Cumulative equity infused in TBCB | ₹4,100 cr, up from ₹3,600 cr in Q2 FY23 |
| Regulated equity (RTM) | ~₹82,000 cr, reserves and surplus ₹86,000 cr less ₹4,100 cr TBCB equity |
| Telecom income | ₹202 cr in Q2, cumulative H1 ₹393 cr; full-year target ₹800 cr |
| Consultancy income | ₹155 cr in Q2, declining as NERPSIP scheme winds down |
| LPS rule collections | ₹1,383 cr received against ₹2,400 cr from six discoms |
| Return on net worth | 8.51% |
| Book value per share | ₹93.22, post bonus issue; was ₹114 previously |
| Gross fixed assets (consolidated) | ₹2.73 lakh cr, standalone ₹2.57 lakh cr |
| Capital work-in-progress (consolidated) | ₹14,900 cr, closely ₹15,000 cr |
| Data center investment approval | ₹713 cr for Manesar pilot, completion in 12-15 months; ₹1,000 cr projected till 2032 |
| Smart metering contracts | 69 lakh meters from two Gujarat discoms; ₹15,000 cr projection over 9 years |
| Leh Ladakh project cost | ₹20,700 cr total, includes ₹8,000 cr grant; PowerGrid capex portion ₹13,000 cr |