Key Takeaways
- Flat profit despite higher capex: Capitalization rose to Rs. 4,587 crores, but revenue and PAT stayed flat as old projects rolled off their 12-year depreciation cycle and the mix shifted toward TBCB projects with different revenue models.
- Capex trajectory steepens sharply: FY26 capex guided to Rs. 28,000–30,000 crores, rising to ~Rs. 35,000 crores in FY27 and Rs. 45,000 crores in FY28, with capitalization following on a two-year lag.
- Leh-Ladakh project pivots from HVDC to AC: The HVDC plan was scrapped after bid costs came in at Rs. 42,000 crores, more than double the original estimate; a 400 kV AC alternative costing ~Rs. 30,000 crores is under discussion, with commissioning expected by 2029.
- Brahmaputra Basin opens a multi-decade opportunity: A Ministry of Power scheme outlines Rs. 6,42,944 crores in transmission investment through and beyond 2035, including 42 GW of HVDC corridors, though the projects are still in study and likely to go the TBCB route.
- What to watch next quarter: Whether the Rs. 45,000-crore bid pipeline converts into awards, the final Government decision on the Leh-Ladakh AC network, and any progress on the Rajasthan JV that remains stalled by regulatory limits on nomination projects.
Capex & Capitalization Trajectory
- FY26 capex: Rs. 28,000–30,000 crores, split across TBCB projects (Rs. 19,062 crores), RTM projects (Rs. 3,554 crores) and others (~Rs. 5,384 crores). The range reflects uncertainty around the exact degree of upside.
- FY27–28 step-up: Capex is expected to reach ~Rs. 35,000 crores in FY27 and Rs. 45,000 crores in FY28, driven by a growing pipeline of ISTS, intrastate, green hydrogen and data center transmission demand.
- Capitalization lag: Management targets ~Rs. 20,000 crores of capitalization by March 2026, with FY27 at ~Rs. 25,000–26,000 crores and FY28 at ~Rs. 28,000 crores. A two-year lag from capex to capitalization is normal due to right-of-way and other execution challenges.
- Bid pipeline: The balance-of-year bid pipeline stands at ~Rs. 45,000 crores, possibly higher if HVDC projects are included, though management cautioned the figure was not yet confirmed and promised to revert.
- Equipment pre-buying: The company is procuring transformers and reactors in bulk well in advance, allocating them to future projects, to manage supply constraints where transformer delivery times now exceed one year.
Tyagi: "As far as challenges of the supply of various equipment because of lot of demand in power sector, in ISTS, intrastate, then RE generation, and now we will be having more demand because of green hydrogen transmission network, data center transmission network. So, these challenges are going to increase in days to come."
Revenue & Profitability Mechanics
- Flat top line explained: Revenue and PAT remained flat despite higher capitalization because projects commissioned in 2010–2013 are completing their 12-year loan tenure, causing depreciation to drop from 5.28% to ~1.2% and interest on loan to approach zero, which together reduce revenue by ~9% per project.
- TBCB mix shift: The growing share of TBCB projects versus RTM projects changes the revenue recognition model, further muting the visible top-line impact of rising capex.
- EBITDA is the wrong yardstick: Under the regulatory framework, EBITDA declines from 89% for a new project to 74% at the end of its 35-year life, but profit remains constant because return on equity is fixed for the entire period. Consolidated EBITDA is also dragged by the smart metering business, which carries a 10–15% margin.
- Other income variation: The drop in consolidated other income reflects interest and differential tariffs from CERC orders that are normally one-time; a yearly swing of Rs. 100–200 crores is routine.
- Other expenses: The increase is driven by FERV, which is a pass-through covered in the regulatory deferral account, and by the smart metering business accounted via service concession agreements where both income and expense sides rise together.
- CSR drag: CSR spend was Rs. 100 crores higher in the current half versus the prior half, and the prior half also benefited from a one-time Rs. 209-crore penalty-waiver order from POWERGRID Southern Interconnector Transmission System Limited.
Ravisankar: "Actually, you see in the regulatory framework, EBITDA is not actually a right parameter to monitor in the sense that when we commissioned a new project as the Chairman was explaining, the EBITDA used to be in the range of 89%. And when you complete the life for the 35 years, the EBITDA will come down to 74%. But your profit will remain same because I have a return on equity constant for the entire period."
Tax Rate Dynamics
- Sub-20% rate is temporary: The effective tax rate has stayed below 20% for eight to nine quarters because the company is under the MAT regime while capitalization remains high and income-tax profit trails CERC profit.
- Normalization trigger: The rate will normalize to ~25% when capitalization comes down and income-tax profit exceeds CERC profit, but management does not foresee that happening soon because once capitalization picks up again, the company will switch back to MAT.
Ravisankar: "It will come to normal when the capitalization comes down and when the income tax profit is more than your profit as per the CERC rates. But again, we don't foresee that because once the capitalization picks up again, we'll be going into the same MAT."
Major Project Updates
Leh-Ladakh: HVDC scrapped, AC alternative emerges
- HVDC bid failed: The company went to market for the Leh-Ladakh HVDC project but received only one bid, which was not acceptable. Cost estimates from suppliers came in at Rs. 42,000 crores, more than double the original Rs. 20,000-crore estimate from three years ago, driven by supply-chain constraints and manufacturer challenges.
- AC replacement under discussion: The Government is considering replacing the HVDC project with a 400 kV AC transmission line from Leh-Pang to Kaithal, with an estimated cost close to Rs. 30,000 crores and commissioning expected by 2029. No formal direction has been received yet.
Tyagi: "This project when we considered HVDC project about three years back, that time cost was about Rs. 20,000 crores and now considering this supply chain constraint, even if we consider that this is a feasible project, we took even cost estimate from our various bidders. Now, cost is coming about Rs. 42,000 crores, considering various challenges and constraints shown by manufacturers or suppliers."
Brahmaputra Basin scheme
- Total opportunity: The Ministry of Power scheme envisions Rs. 1,91,000 crores of investment up to 2035 and Rs. 4,51,935 crores beyond 2035, for a total of Rs. 6,42,944 crores. It includes 42 GW of HVDC corridors at six locations and pumped-storage integration of 3.7 GW by 2035 and 7.4 GW beyond.
- Awarding route: The projects are still in the study stage and, being normal HVDC in plain areas, are unlikely to be nominated to POWERGRID; they will probably go the TBCB route.
Other projects
- Sasaram HVDC upgradation: In-principle approval for upgrading from 500 MW LCC-based to 1,000 MW VSC-based at an estimated cost of Rs. 3,440 crores under RTM, featuring indigenous semiconductors and an Indian supply chain for HVDC technology.
- Khavda to South Olpad HVDC: Already finalized.
- Barmer to South Kalamb HVDC: Approved in the NCT, likely to be finalized this financial year.
- Andaman-Paradeep undersea HVDC: No clear approval or direction from the Government so far.
- Data center: Commissioning of 1,000 racks delayed from Q3 to Q4.
Operational & Commercial Highlights
- Asset management score rises: POWERGRID was ranked in the first quadrant with a score of 4.14 out of 5, against a global average of 3.68, up from 3.22 in 2023, in a benchmarking exercise by OHROS Consulting Group covering 12 major utilities.
- Commissioning momentum: Multiple transmission lines and substations were commissioned, including the Khavda II and III lines, the Banaskantha-Ahmedabad 765 kV line, the Jeypore-Jagdalpur inter-regional link, and the Namsai-Kathalguri circuits (five months ahead of schedule). Substations included Khavda III, Khavda II, Ahmedabad, Dausa, and Narela.
- Commercial discipline: Realization stood at 102% of billing, and outstanding dues fell from Rs. 3,151 crores in Q1 to Rs. 2,899 crores, with major dues concentrated in Tamil Nadu, Uttar Pradesh and Telangana.
- Right-of-way compensation boost: The Government of India issued guidelines on 21 March 2025 increasing land compensation rates for right-of-way from 30% to 60% in urban areas and to 45% in semi-urban areas. A valuer is expected to be finalized within about one month, and states including Rajasthan and Gujarat are being urged to adopt similar guidelines.
- Telecom and consultancy growth: Telecom revenue rose to Rs. 570 crores from Rs. 544 crores in H1, with 22 customers added and 100% backbone availability. Consultancy income jumped to Rs. 821 crores from Rs. 255 crores, mainly from the smart meter business via PESL.
- Innovation milestones: The company developed an insulated cross arm for 400 kV lines that reduces right-of-way by 20% and saves trees, and India's first 220 kV mobile GIS in collaboration with Toshiba, deployable within 48 hours for emergencies or as a spare bay for renewable evacuation.
Tyagi: "Government of India is very positive. They are helping us. We have got one guideline issued by Government of India on this 21st March, 2025 for increasing land compensation rates as against 30% for RoW in urban areas from 30% to 60% and 45% in semi-urban area."
Strategic Initiatives & Adjacencies
- Rajasthan JV stalled: There has been no progress because the regulator has placed limits on nomination-basis projects. The Rajasthan government is trying for an exemption, but no communication has been received.
- Battery storage: The company participated in a tender but lost; it will continue to participate in other projects without providing further strategic detail.
- EESL losses: The half-year loss widened to ~Rs. 126 crores from ~Rs. 92 crores in the prior half, with an additional Rs. 29-crore adjustment booked in the last quarter.
- Chinese imports: Management does not expect direct imports from China to continue, though approvals may be possible for Chinese manufacturers who have set up factories in India.
- Consultancy pipeline: Domestic opportunities span renewable energy, intrastate transmission, diversions, BESS and green hydrogen; internationally, the company is pursuing work across South Asia, Africa, America, Europe and Australia.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 capex | Rs. 28,000–30,000 crores | FY26 |
| FY26 capitalization | ~Rs. 20,000 crores | By March 2026 |
| FY27 capex | ~Rs. 35,000 crores | FY27 |
| FY28 capex | Rs. 45,000 crores | FY28 |
| FY27 capitalization | ~Rs. 25,000–26,000 crores | FY27 |
| FY28 capitalization | ~Rs. 28,000 crores | FY28 |
| Leh-Ladakh AC project commissioning | 400 kV AC line from Leh-Pang to Kaithal | By 2029 |
| Leh-Ladakh AC project capex | Close to Rs. 30,000 crores | Subject to Government direction |
| Barmer to South Kalamb HVDC finalization | Approved in NCT | This financial year |
| Data center commissioning | 1,000 racks | Q4 FY26 (delayed from Q3) |
| RoW valuer finalization | Finalization of valuer and report | ~1 month |
| Sasaram HVDC upgradation | Rs. 3,440 crores, 500 MW to 1,000 MW VSC-based | In-principle approval accorded |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Total income (H1 FY26) | ₹23,115 cr, consolidated |
| EBITDA (H1 FY26) | ₹19,109 cr, consolidated |
| Profit after tax (H1 FY26) | ₹7,197 cr, consolidated |
| Standalone total income (H1 FY26) | ₹22,605 cr |
| Standalone PAT (H1 FY26) | ₹7,208 cr |
| Transmission charges (H1 FY26) | ₹21,356 cr |
| Consultancy income (H1 FY26) | ₹821 cr, up from ₹255 cr YoY, driven by smart metering |
| Telecom revenue (H1 FY26) | ₹570 cr, up from ₹544 cr YoY |
| Other income (H1 FY26, consolidated) | ₹443 cr |
| Operating expenses (H1 FY26) | ₹3,903 cr |
| EPS (H1 FY26) | ₹7.74 per share |
| Book value per share | ₹106.37 |
| Return on net worth (H1 FY26) | 7.27% |
| Net worth | ₹98,932 cr |
| Gross fixed assets | ₹2,95,148 cr |
| Capital work in progress | ₹47,782 cr |
| Debt | ₹1,35,923 cr |
| Debt-equity ratio | 58:42 |
| Capex (H1 FY26) | ₹15,385 cr, vs ₹10,002 cr in H1 FY25 |
| Capitalization (H1 FY26) | ₹4,587 cr, vs ₹4,006 cr in H1 FY25 |
| Full-year capex guidance | ₹28,000 cr to ₹30,000 cr for FY26 |
| Full-year capitalization guidance | ₹20,000 cr for FY26, revised from earlier ₹22,000 cr |
| Capex guidance FY27 | ₹35,000 cr |
| Capex guidance FY28 | ₹45,000 cr |
| Capitalization guidance FY27 | ₹25,000 cr to ₹26,000 cr |
| Capitalization guidance FY28 | ₹28,000 cr |
| Works in hand | ₹1,52,287 cr, of which ₹1,02,992 cr in TBCB |
| Transmission availability | 99.83%, above the 99.75% incentive threshold |
| Trippings per line | 0.17 |
| Billing realization | 102%, ₹18,737 cr realized against ₹18,248 cr billed |
| Outstanding dues | ₹2,899 cr, down from ₹3,151 cr in Q1; major dues from Tamil Nadu, Uttar Pradesh, Telangana |
| FERV (H1 FY26) | ₹491 cr, pass-through in other expenses |
| EESL loss (H1 FY26) | ₹126 cr, vs ₹92 cr in H1 FY25 |
| Transmission awarding pipeline (ISTS) | ₹3.5 lakh cr pending out of ₹9.15 lakh cr NEP |
| Bid pipeline for balance FY26 | ~₹45,000 cr, may be higher with HVDC |
| Brahmaputra basin opportunity | ₹6,42,944 cr total, ₹1,91,000 cr up to 2035 and ₹4,51,935 cr beyond |
| Sasaram HVDC upgradation cost | ₹3,440 cr, 500MW to 1,000MW VSC-based under RTM |
| Leh-Ladakh AC alternative capex | ~₹30,000 cr, vs earlier HVDC estimate of ₹20,000 cr and revised HVDC bid of ₹42,000 cr |
| Data center capacity | 1,000 racks, commissioning delayed to Q4 FY26 |
| Pink stations | 8, four added in FY26 |
| Green power share | 29% from green tariff, 33% renewables in total consumption |