Key Takeaways
- Regulatory drag masked underlying growth: Operating income grew 7.7% on transmission, but tariff trajectory and one-off timing differences shaved ~₹550 crore off revenue, pulling effective growth to ~3%. Underlying PAT growth was 9% before similar regulatory items.
- CapEx guidance held firm, with an upward bias: FY27 CapEx pegged at ₹37,000–₹40,000 crore, and management expects it to stay "much beyond ₹40,000 crore" thereafter, driven by HVDC projects, synchronous condensers, and Intrastate work.
- The order book is about to get a lot bigger: The Pang evacuation scheme (~₹31,000 crore) will push the total order book to roughly ₹2.5 lakh crore, with a ₹67,000 crore bidding pipeline and GEC-III (₹1.36 lakh crore) still to come.
- Right-of-way is the acknowledged bottleneck, with a fix in motion: New market-rate compensation guidelines are being adopted state by state, which management expects will ease land access but also drive CapEx higher by an as-yet unknown amount.
- What to watch next quarter: Whether the Pang scheme formally enters the order book, any state-level progress on the new ROW compensation rules, and the commissioning of the Manesar data centre.
Financial Performance: The Regulatory Overlay
- Revenue bridge: Transmission revenue grew 7.7%, but a -₹354 crore drag from regulatory tariff trajectory and a -₹193 crore hit from a one-off differential tariff order timing difference brought effective growth down to ~3%.
- Profit bridge: Underlying PAT growth was 9%, reduced to a reported 8% by regulatory asset trajectory and other items totalling -₹82 crore.
- Other income shifts: Interest from subsidiaries rose sharply from ₹794 crore to ₹1,201 crore, while incentive income halved from ₹159 crore to ₹98 crore. Dividend from JVs more than doubled to ₹60 crore, and subsidiary dividends edged up to ₹345 crore.
- Collections improved: Receivable days dropped to 10.54 days, and outstanding dues older than 45 days came down significantly.
CapEx & Capitalization: The Build Cycle
- FY27 guidance: CapEx of ₹37,000–₹40,000 crore, with capitalization of ₹25,000–₹30,000 crore.
- Beyond FY27: Management expects CapEx to continue "much beyond ₹40,000 crore," with numbers getting "much better" as large HVDC projects, synchronous condensers, and Intrastate schemes materialize.
- The land-compensation wildcard: New market-rate compensation guidelines will drive CapEx higher, but the quantum is unknown and clarity will come only as states adopt and implement the rules.
- Equipment supply: No challenges reported; a bulk procurement approach has given transformer manufacturers certainty, and supplies are in position.
- Project timeline extension: The government has approved increasing transmission project timelines from 18–24 months to 24–30 months for new projects, though this does not apply retrospectively.
Burra: "the CapEx would be continuing to be in the range much beyond ₹40,000 Crore. It should continue to be."
Order Book & Pipeline: The Denominator Effect
- Current order book: With the Pang evacuation scheme (~₹31,000 crore) added, the total order book will be roughly ₹2.5 lakh crore.
- Bidding pipeline: ₹67,233 crore is currently under bidding or to be floated. Beyond that, Green Energy Corridor III (₹1.36 lakh crore Intrastate) and BESS (₹50,000 crore) are expected to come mostly under the TBCB route, facilitating about 135 gigawatt of RE across the states.
- HVDC project awards: A couple of HVDC projects are under active consideration and could be placed for bidding or discussed in the NCT; FY28 could see two such projects awarded.
- Intrastate picking up: Tender activity is increasing, and POWERGRID is evaluating projects based on merit and where better operational sync exists.
- Bidding pipeline fluctuation: The pipeline moves in chunks: one HVDC project moving forward takes a big bite out of the total, and new HVDC materialization pushes it back up.
Burra: "Transmission system is a common denominator for every single megawatt which is going to be put into the grid. For that you need a transmission system. So, it is a common denominator."
Project Execution: Delays, Not Derailments
- H1 FY27 commissioning: Two full TBCB SPV projects (Ramgarh-II Transmission system and Bidar transmission system) were fully commissioned. Post-September, the 765 kV Koppal-II–Narendra line, 400 kV Koppal-II–Gadag-II line, and Gadag-II substation were also commissioned.
- Khavda-Nagpur progress: Works are on schedule, with transformers being supplied and firewalls being built. KPS-II will be the epicentre, housing HVDC alongside the existing AC substation.
- ROW challenges: Compensation now includes diminishing land value between towers and across the corridor, not just crop damage. Identifying exact landowners and determining market rates remain ongoing challenges, and state governments need time to adopt central guidelines and realign machinery.
- ROW digitization: POWERGRID has digitized landowner identification to maintain a clear track of payments.
- Quarterly lumpiness is structural: Transmission projects have gestation periods not linked to the financial year; a delay of a couple of weeks pushes a project into the next quarter, but no project has been left incomplete.
Burra: "You are concerned that, 'Sir, what will happen next year? Should we miss the bus?' There is next bus immediately which we are going to board that. No issue. Because our projects are not definitely quarterly wise a project should come. That is not the way how the industry is."
New Business Lines: Data Centre & Storage
- Data centre: The pilot facility in Manesar is fully ready, built predominantly by POWERGRID engineers on its own premises. It is a 100% Indian-owned government infrastructure asset with 7-layer security, ~1,000 racks, 14 MW capacity, Tier III certification, and MeitY empanelment as a cloud service provider. Commissioning is expected in a few weeks.
- Expansion plans: A second data centre in the southern part of the country is ready with land secured, and POWERGRID is actively pursuing potential in other locations. Management wanted to get a complete grip on the pilot before scaling.
- BESS under Section 62: The regulator has modified tariff regulations to allow integrated storage systems developed by the transmission service provider under RTM mode. POWERGRID has secured clearances from the Northern and Western Regions and filed petitions before the regulator. Management sees good traction and believes this can open a new window for the company to enter storage systems.
Competitive Positioning & Returns
- From regulated to competitive: Management framed POWERGRID as the one PSU that has successfully moved from an extremely regulated environment into a fully competitive domain.
- On new entrants: New parties participating in transmission are welcome; management believes the more they understand transmission, the better they will fare in their next projects.
- Returns assurance: Management assured that returns will be "very well encouraging" and not dictated by other companies' participation.
- Commodity inflation protection: Some supplies are fixed-price, while others carry price variation clauses based on predetermined indices. Appropriate cushions have been factored into multiple projects; positive movements are taken care of, and negative movements would be a windfall.
Burra: "If there is one Company which has done every project in the last part, it is POWERGRID. Check up anything. Check any data."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 CapEx | ₹37,000–₹40,000 crore | FY27 |
| FY27 capitalization | ₹25,000–₹30,000 crore | FY27 |
| CapEx beyond FY27 | Continue "much beyond ₹40,000 crore" | FY28 and beyond |
| Pang scheme in order book | ~₹31,000 crore addition, taking total to ~₹2.5 lakh crore | Imminent (post-NCT discussion) |
| HVDC project awards | Two projects could be awarded | FY28 ("it could happen") |
| Data centre commissioning | Manesar pilot facility go-live | "A few weeks" |
| Project timelines (new projects) | Extended from 18–24 months to 24–30 months | Applicable to new projects only |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Consolidated PAT growth | 8% reported; 9% underlying growth offset by regulatory asset trajectory and one-offs |
| Standalone PAT growth | ~7% |
| Transmission operating income growth | 7.7%; effective growth ~3% after regulatory tariff impact of -₹354 cr and one-off differential tariff of -₹193 cr |
| FY27 CapEx guidance | ₹37,000 cr to ₹40,000 cr |
| FY27 capitalization guidance | ₹25,000 cr to ₹30,000 cr |
| Total works in hand | ₹2.20 lakh cr, comprising TBCB ₹1.95 lakh cr and RTM ₹0.25 lakh cr |
| H1 FY27 TBCB wins (annual tariff) | ₹8,107 cr, from 9 ISTS projects (₹7,664 cr) and 2 Intrastate projects (₹443 cr) |
| Bidding pipeline | ₹67,233 cr, with ₹63,086 cr under bidding and ₹4,147 cr to be floated (ISTS only) |
| Q2 FY27 commissioned | 981 circuit km of transmission lines and 14,600 MVA transformation capacity |
| H1 FY27 commissioned | 2,616 circuit km of transmission lines and 25,100 MVA capacity |
| Transmission availability | 99.81%, tripping per line at 0.17 |
| Receivable dues | 10.54 days |
| Debt-equity ratio | 59.41, with headroom up to 1:1.5 |
| Gross fixed assets (consolidated) | ₹3.29 lakh cr |
| Data centre capacity | 1,000 racks, 14 MW, Tier III certified, commissioning in weeks |
| Interest from subsidiaries | ₹1,201 cr, up from ₹794 cr |
| Dividend from subsidiaries | ₹345 cr, up from ₹300 cr |
| Telecom revenue | ~₹283 cr |
| Consultancy revenue | ~₹400 cr |