Power Grid Corporation of India Ltd Q3 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/0zddwzowzbrmk19j1f1te5gs.pdf

Key Takeaways


Financial Performance & Receivables

K. Sreekant: "Otherwise, beyond 75 days nobody is holding up any amount."

Capex, Capitalisation & Works in Hand


TBCB: Competition, Pipeline & Margin Strain

K. Sreekant: "The moment you see a bid, you feel that if somebody else can do it at this price, I can always do it less than 0.25% and then the race starts. So, there is this issue which we are facing."

Renewable Energy & Future Growth Opportunities

K. Sreekant: "But, the opportunity set there is a bit limited, because some of the states are doing it on their own. They're doing it at a slow pace, but they're doing it on their own, they're now doing any bidding process. Few states like UP, Rajasthan, MP are doing bidding, but again, the pace is not commensurate with the requirement, in my view."

Monetisation, Capital Raising & Dividend

K. Sreekant: "I think instead of monetisation through InvIT, we are looking at securitisation of the cashflows and raising funds. So, that is something which we are doing, and hopefully about 3,000 crores we would raise before the end of this fiscal through this route."

New Ventures: Smart Metering, Solar & Data Centre


Guidance & Commitments

CommitmentSpecificsTimeline
FY23 capexAchieve ₹8,800 cr targetBy 31 March 2023
Securitisation raise~₹3,000 cr via cashflow securitisationBefore end of FY23
FY23 capitalisation₹10,000–12,000 cr on consolidated basisFY23
FY24 capitalisation~₹10,000 cr, much from TBCB projectsFY24
FY24 capex~₹8,000–8,800 cr; upside if more TBCB winsFY24
Smart metering1 cr meters completed, ~₹700 cr annual revenue~2 years
Ladakh transmission capexCapex to start; ~5 years to execute post-biddingStarting FY24
Dividend pay-outContinue at ~60% pay-out levelOngoing
TBCB award pipeline₹40,000–50,000 cr in awards expectedNext 12 months

Key Metrics

MetricQ3 FY23
Consolidated income₹11,530 cr, +8% YoY
Consolidated PAT₹3,645 cr, +11% YoY
9M consolidated revenues₹34,048 cr, +8% YoY
9M consolidated PAT₹11,097 cr, +11% YoY
EBITDA gross margin growth~6% YoY, adjusted for regulatory deferral balances
Incentive income₹130 cr for Q3; ₹408 cr for 9M
Surcharge income₹146 cr for 9M
Debt-equity ratio61:39, steady; improvement expected from deleveraging
FY23 capex target₹8,800 cr; ₹5,429 cr achieved by end of Q3
Consolidated capitalization (9M)~₹5,190 cr by end of Q3
FY23 capitalization target₹10,000–12,000 cr
FY24 capitalization target~₹10,000 cr, consolidated including TBCB
FY24 capex guidance₹8,000–8,800 cr, could increase with more TBCB wins
Works in hand~₹47,000 cr, including Leh scheme at ~₹22,000 cr
Operational availability99.81%, above 99.75% incentive cut-off
Trippings per line0.21, improved from 0.28 in prior-year period
Telecom revenues₹187 cr for Q3; orders received ₹68 cr
Consultancy income₹142 cr for Q3; realisation 86% against billing of ₹34,000 cr
Smart metering capex₹5,500–6,000+ cr per 1 crore meters
Smart metering annual revenue~₹700 cr when 1 crore meters fully on
TBCB projects won in FY232 out of 5 projects bid
TBCB awards expected next 12 months₹40,000–50,000 cr (₹22,000 cr under bidding + ₹33,000 cr approved)
CEA transmission plan investment₹2,44,200 cr for nearly 51,000 ckm of lines
Ladakh transmission project cost₹20,772 cr excluding IDC; ~₹22,500 cr including IDC
Central grant for Ladakh project₹8,000 cr
LPS rules fair value charge₹94 cr in Q3, vs ₹127 cr in Q2
Receivables converted under LPS₹2,400 cr total; ₹600 cr received so far
Expected fundraise via securitisation~₹3,000 cr before end of FY23
Dividend pay-out (last year)~60%; ₹10 of ₹15 standalone EPS already paid in FY23