Key Takeaways
- Capex inflection confirmed, guidance raised: FY24 CapEx now expected to exceed ₹10,000 crore, up from the original ₹8,800 crore target, with a steep ramp to ₹15,000 crore in FY25 and ₹20,000 crore in FY26.
- TBCB wins surge, market share jumps: Won 6 ISTS projects worth ~₹20,000 crore in Q3 alone, pushing the 9-month win tally to ₹26,000 crore and market share to 60-65%+, well above the ~40% long-term average.
- Balance sheet strengthens alongside growth: Debt reduced by ₹9,000 crore to ₹1,19,000 crore, improving the debt-equity ratio to 58:42 from 61:39, even as the capex cycle accelerates.
- Transmission pipeline is enormous and visible: The NEP pegs ISTS investment at ₹3,10,000 crore, and management sees a cumulative ₹2,00,000+ crore capex opportunity across inter-state, intra-state and cross-border segments through 2032.
- What to watch next quarter: Whether the ₹55,000 crore work-in-hand translates into a material FY25-26 capex guidance upgrade, progress on the Leh Ladakh FEED study, and any CERC draft regulation clarity on ROE for new assets.
Capex Trajectory & Execution
- FY24 beat in motion: Q3 CapEx of ₹3,444 crore took the 9-month total to ₹7,690 crore, and capitalization of ₹1,784 crore in Q3 brought the 9-month figure to ₹5,780 crore, putting the company on track to exceed its original ₹8,800 crore target and reach ₹10,000 crore plus.
- Steep ramp ahead: FY25 CapEx is guided at ₹15,000 crore and FY26 at ₹20,000 crore, but management acknowledged that with ₹55,000 crore of works in hand to be executed in 24-30 months, these estimates may be trued up after six months once project visibility improves.
- Capitalization to follow with a lag: Capitalization is expected at ~₹8,500 crore for FY24, then nearly doubling to ₹16,000-17,000 crore in FY25 as projects move from CWIP to completed assets, though the FY26 figure was not provided.
- Long-term visibility is exceptional: Management sees cumulative capex of ₹2,00,000+ crore through 2032 across inter-state, intra-state and cross-border transmission, averaging ₹20,000-25,000 crore annually, with some years at ₹15,000 crore and others at ₹30,000 crore depending on project timelines.
- HVDC projects anchor the out-years: The Fatehpur-Badla and Khavda-Nagpur HVDC projects carry a 48-54 month timeline, with real capex starting only in the last quarter of FY25, meaning the bulk of spending lands in FY26 and beyond.
R. K. Tyagi: "If we look at this outlook upto 2032, we have interstate intrastate cross border. If we add all the sectors and possible capex, so we are touching somewhere 200,000+ capex in the next 7-8 years."
TBCB Wins & Competitive Positioning
- Market share surged on deliberate aggression: Power Grid's TBCB market share rose to 60-65%+ recently, up from a long-term average of ~40%, as the company shifted to a more competitive bidding stance to sustain growth and protect investor returns.
- Q3 was a standout quarter: Six ISTS TBCB projects were won in Q3 alone, carrying a notional NCT cost of ~₹20,000 crore and an annual tariff of ₹1,636 crore, bringing the 9-month FY24 tally to ₹26,000 crore in project cost and ₹2,340 crore in annual tariff.
- Winnability is holding at high levels: The tariff-based win rate stands at almost 67%, and management expressed confidence that the winning momentum will continue given the large pipeline still to be bid.
- The pipeline supports further wins: Of the ₹2,44,000 crore ISTS network identified by the CEA, ₹96,000 crore has been awarded, ₹84,000 crore is in the bidding pipeline, and ₹64,000 crore is yet to be bid out, leaving ample room for further market share gains.
- IRR discipline is maintained: Management targets ~14% IRR on projects and ensures it stays at 11-12% even in competitive bids, balancing market share ambition with return thresholds.
Ravindra Kumar Tyagi: "Now we are more aggressive because we had to compete. If we have to survive, if we have to take care of the interest of our investors, so definitely we had to….growth has to be maintained."
Balance Sheet & Capital Management
- Debt reduction despite capex ramp: Gross debt fell from ₹1,28,000 crore to ₹1,19,000 crore, and the debt-equity ratio improved to 58:42 from 61:39, reflecting strong internal cash generation and securitization proceeds.
- Securitization fills the monetization gap: Under new NMP guidelines, only rights transfer is permitted, not ownership transfer, so Power Grid used securitization instead, raising ₹5,700 crore this year versus ₹3,400 crore last year.
- Debt structure is efficient: All debt sits on Power Grid's standalone books and is on-lent to SPVs, allowing the parent to borrow at better rates, which explains why consolidated CWIP exceeds standalone CWIP but debt appears only at the parent level.
- Receivables remain concentrated: Over-45-day receivables stood at ₹4,181 crore, with TNEB/TANGEDCO accounting for ~₹2,200 crore, though the BHAVINI issue was resolved with a commitment to pay all arrears in installments.
Regulatory & Policy Environment
- CERC draft regulations pose limited risk: The proposed changes to O&M charges, including a shift in the sub-station to transmission line ratio and addition of reactor charges, have a net impact of almost zero, per management.
- ROE grandfathering is the key watchpoint: Existing assets earn 15.5% ROE and new assets earn 15%, and management is in discussions with CERC, expressing hope that existing norms will continue for new projects as well, with no impact on revenue or profitability.
- ISTS roadmap expanded on storage delays: The NEP figure of ₹3,10,000 crore, up from the earlier ₹2,44,000 crore CEA plan, reflects additional transmission needed because battery storage has not materialized as expected, requiring more lines instead of storage-based deferral.
- The ₹3.1 lakh crore target faces timeline risk: With three years of the FY22-27 period already elapsed, an analyst flagged that the remaining target appears very aggressive, and management acknowledged "there can be some challenges" without offering a specific acceleration plan.
Ravindra Kumar Tyagi: "Discussions are going on and we are hopeful that whatever regulations and norms were there, they will continue. So there will not be any impact on Power Grid, revenue or profitability."
New Initiatives & Diversification
- PowerTel hived off and operational: The telecom business was separated into subsidiary PowerTel from 1 October 2023, earning ₹201 crore in its first quarter, adding 17 new customers, and securing a ₹362 crore multi-year order.
- Nagda Solar Plant under construction: The 85 MW captive solar plant is expected to be commissioned in Q3 of the calendar year, around August or September, contributing to the ESG target of 50% electricity from renewable sources by 2025.
- Leh Ladakh project advancing through FEED: Front-end engineering and design studies are nearly complete by March 2024, with FEED2 taking another 7-8 months, NIT expected in January 2025, order placement by March 2025, and project reality by FY30 given the 5-year construction timeline.
- Digitization and ESG milestones: A 132 kV bus reactor was successfully converted from synthetic oil to natural oil, a first in India; UNMS now covers almost 1 lakh km of fiber network; and the PARTeC Lab at Manesar received international IEC 61850 accreditation.
- Consultancy revenue steady: The consultancy segment earned ₹116 crore in income, with one new international assignment in Uganda, 17 ongoing international assignments, and 78 ongoing domestic assignments.
Operational Performance
- Reliability metrics improved: Transmission system availability rose to 99.86% in the 9-month period versus 99.81% last year, while line tripping fell to 0.22 per line from 0.27, reflecting better asset management.
- Key transmission links commissioned: The Lower Subansiri to Biswanath Chariali link, an important northeastern region connection, was added during the quarter.
- Supply chain constraints are being addressed: Management is developing more vendors for transformers at the 220 kV and 400 kV levels to mitigate supply chain challenges that could otherwise slow project execution.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY24 CapEx | ₹10,000 crore plus (raised from ₹8,800 crore) | FY24 |
| FY25 CapEx | ₹15,000 crore plus | FY25 |
| FY26 CapEx | ₹20,000 crore plus | FY26 |
| FY24 Capitalization | ~₹8,500 crore | FY24 |
| FY25 Capitalization | ~₹16,000-17,000 crore | FY25 |
| Nagda Solar Plant | 85 MW commissioned | Q3 CY24 (Aug-Sep) |
| Leh Ladakh FEED completion | FEED studies complete | March 2024 |
| Leh Ladakh FEED2 outcome | Outcome of FEED2 | December 2024 |
| Leh Ladakh NIT | Notice inviting tender | January 2025 |
| Leh Ladakh order placement | Order placed | March 2025 |
| Leh Ladakh project completion | Project reality | FY30 |
| Fatehpur-Badla HVDC award | Awarded | Within FY24 |
| Fatehpur-Badla HVDC capex start | Real capex begins | Last quarter FY25 |
| Fatehpur-Badla HVDC completion | Bipole 1: 48 months, Bipole 2: 54 months | ~4.5 years from start |
| FY25-26 capex true-up | Possible guidance revision after 6 months | Mid-CY24 |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Consolidated revenue | ₹11,820 cr, vs ₹11,281 cr in Q3 FY23 |
| Standalone revenue | ₹11,468 cr, vs ₹11,281 cr in Q3 FY23 |
| Consolidated PAT | ₹4,028 cr, vs ₹3,702 cr in Q3 FY23 |
| Standalone PAT | ₹3,970 cr, vs ₹3,702 cr in Q3 FY23 |
| Consolidated EBITDA margin | 80% plus, for 9M FY24 |
| 9M FY24 consolidated revenue | ₹34,608 cr |
| 9M FY24 consolidated PAT | ₹11,407 cr |
| 9M FY24 EPS | ₹12.26, vs ₹11.93 as on 31-12-22 |
| Q3 CapEx (consolidated) | ₹3,444 cr; 9M FY24: ₹7,690 cr |
| Q3 capitalization | ₹1,784 cr; 9M FY24: ₹5,780 cr |
| FY24 CapEx guidance | ₹10,000 cr plus, hopeful; by Jan'24 already achieved ~₹8,700 cr |
| FY25 CapEx guidance | ₹15,000 cr plus, close to $2 billion |
| FY26 CapEx guidance | ₹20,000 cr plus, close to $3 billion |
| FY24 capitalization guidance | ₹8,000-8,500 cr |
| FY25 capitalization guidance | ₹16,000-17,000 cr |
| Work in hand | ₹77,770 cr: ongoing RTM ₹11,450 cr, new RTM ₹24,800 cr (incl. Leh-Kaithal HVDC ₹20,000 cr+), TBCB ₹41,450 cr |
| TBCB projects won in Q3 FY24 | 6 projects, NCT cost ~₹20,000 cr, annual tariff ₹1,636 cr |
| TBCB projects won in 9M FY24 | ₹26,000 cr worth, annual tariff ₹2,340 cr; winnability ~67% tariff-wise |
| Transmission system availability | 99.86% in FY24 so far, vs 99.81% in 9M FY23 |
| Tripping rate | 0.22 per line in FY24 so far, vs 0.27 per line last year |
| Gross fixed assets | ₹2,74,000 cr; CWIP ~₹16,600 cr |
| Loan/Debt | ₹1,19,000 cr, reduced from ₹1,28,000 cr |
| Net worth | ₹87,194 cr, vs ₹82,226 cr last year |
| Debt-equity ratio | 58:42, improved from 61:39 last year |
| Return on net worth | 13.08%, vs 13.50% last year |
| Receivables >45 days | ₹4,181 cr; TNEB/TANGEDCO ~₹2,200 cr, plus J&K, M.P., U.P. |
| Consultancy income | ₹116 cr in 9M FY24 |
| PowerTel first-quarter income (from Oct'23) | ₹201 cr; 17 new customers, ₹362 cr multi-year orders |
| Securitization in FY24 | ₹5,700 cr loan taken, vs ₹3,400 cr last year |
| Q3 transmission capacity added | 3,100 MVA transformation capacity, 834 circuit km of lines |
| Nagda Solar Plant capacity | 85 MW, expected Q3 FY25 (Aug/Sep 2024) |
| Ladakh RDSS project cost | ₹862 cr, agreement signed in Q3 |
| ISTS pipeline (CEA plan) | ₹2,44,000 cr total; ₹96,000 cr awarded, ₹84,000 cr under bidding, ₹64,000 cr yet to be bid |
| NEP ISTS target (FY22-27) | ₹3,10,000 cr |
| Capex visibility up to 2032 | ₹200,000 cr plus |
| ROE on new assets (draft CERC) | 15% indicated for projects commissioned after Apr 1, 2024; old assets grandfathered at 15.5% |