Key Takeaways
- Execution engine restarted, guidance raised: After a year of challenges, project execution has turned around with government support, enabling POWERGRID to raise its FY26 CapEx guidance to ₹32,000 crores and capitalization to ₹22,000 crores.
- A ₹1.95 lakh crore project pipeline is now visible: Works in hand of ₹1,45,513 crores plus ₹50,000 crores of WIP set the stage for a multi-year buildout, with annual CapEx stepping up to ₹45,000 crores by FY28.
- The balance sheet crossed a milestone but returns dipped: Gross fixed assets surpassed ₹3 trillion, yet standalone RoNW fell from 12.42% to 11.51% as net worth grew faster than profit.
- Supply chain is the critical bottleneck to watch: Domestic transformer capacity of 2,28,000 MVA falls short of the 4,21,000 MVA demand projected for FY26-27, and management flagged that government relaxation for Chinese firms in India would be a boost.
- What to watch next quarter: Whether the Q4 commissioning surge closes the gap to the 5,500 ckm and 60,000 MVA annual targets, and any policy movement on Chinese supplier relaxation or the CERC draft on BESS in the cost-plus model.
Execution Turnaround & Project Delivery
- Challenges resolved: Execution bottlenecks from the prior year have been addressed with support from the Government of India and stakeholders, and performance is now improving across all areas.
- RoW breakthrough: Right-of-way issues improved significantly after Government of India guidelines issued in June 2024, March 2025, and December 2025. States adopted these at different times, and District Collectors issued MRC rate orders by September-October, after which work accelerated into Q3 and is expected to be even better in Q4.
- Structural RoW change: Compensation rates were raised from 30% of land value to 45% in semi-urban areas and 60% in urban areas like Delhi, making the improvement durable rather than a one-time fix.
- Dedicated execution infrastructure: A corporate-level ROW cell now monitors issues day-to-day, with regional cells escalating to Chief Secretaries or the Power Secretary. A land acquisition cell identifies 3-4 options per project before bidding, and bulk transformer procurement (30 units per package, 10-12 packages per year) secures supply in advance.
- Mechanization and monitoring: Cranes are now used for tower erection, and Portadeck mats allow work during rains and muddy conditions. Control rooms in each region have camera connectivity at all sites, letting the Chairman view progress and call project managers on screen.
- Q4 surge expected: Management expects to add 18,000-20,000 MVA of transformer capacity and reach 1,500-2,000 ckm in the remaining two months, coming close to the CEA targets of 60,000 MVA and 5,500 ckm. Key lines likely commissioned in Q4 include Bhadla-III to Sikar-II, Bhadla-III to Ramgarh, Navsari to Padghe, and Maheshwaram to Kurnool.
Dr. R.K. Tyagi: "With the support of Government of India, with the support of our stakeholders, we have been able to resolve many of the issues. And now, our execution of projects, our performance is improving in all areas, unlike last year wherein we had number of challenges in commissioning our projects."
The Multi-Year Capex Cycle
- Guidance raised mid-year: FY26 CapEx commitment increased from ₹28,000 crores to ₹32,000 crores, with 9-month actuals already at ₹29,200 crores. Capitalization guidance raised from ₹20,000 crores to ₹22,000 crores, with ₹18,700 crores already commissioned as of 31st January 2026.
- Stepping up annually: FY27 CapEx is guided at ₹37,000 crores with capitalization of ₹30,000 crores, and FY28 CapEx at ₹45,000 crores with capitalization of ₹35,000 crores.
- Project pipeline of ₹1,95,000 crores: This comprises ₹1,45,513 crores of works in hand plus ₹50,000 crores of WIP, to be commissioned over the next 3-4 years.
- Demand drivers are structural: India's move toward a $10 trillion economy brings rapid industrialization, urbanization, EVs, green hydrogen, and data centers. By 2032, the plan calls for 600 GW of non-fossil fuel capacity, 71 GW of additional demand for green hydrogen, 47 GW of BESS, and 27 GW of pumped hydro.
- Capitalization urgency tied to renewables: The raised capitalization target is driven by the need to commission RE evacuation projects so that green power is not curtailed; management wants to ensure no RE power is curtailed in India.
- Capitalization mix shifting: Over the next 2-3 years, 80-90% of capitalization will come from TBCB projects and only 10-20% from RTM, reflecting the competitive bidding pipeline.
Dr. R.K. Tyagi: "RE projects are very critical projects which are commissioned and we don't want that any power RE power, Green power, which is almost free given by nature. So, it should not be curtailed at any cost. So, we want to focus on these projects so that no power is curtailed in India."
HVDC & Major Project Pipeline
- Barmer II to South Kala Amb HVDC: A ~₹35,000 crore project, sure to be awarded with OBD on 1st April 2026.
- Bikaner V to Begunia HVDC: Expected to be shortly approved and awarded in FY27.
- Paradeep to Andaman HVDC: A 320 kV, 500 MW link likely commissioned by 2031-2032, with an estimated cost of ~₹31,000 crores.
- Brahmaputra basin HVDC projects: Multiple projects (Niglok, Namsai, Roing, Silapathar, Gogamukh, Rauta) are in the pipeline, but their timeline depends on hydropower generation progress in the Northeast, where hydro projects take 8-10 years versus ~4 years for HVDC.
- Kurnool to Vishakhapatnam HVDC: Already discussed in the National Committee on Transmission.
- Other HVDC projects: Bhadravati and one RTM HVDC project will take about another 3 years; general TBCB projects have 2-3 years of CapEx, while remaining RTM projects have about 18-24 months.
- Major TBCB wins in FY26: Sonbhadra pumped storage evacuation (₹3,626 cr), SR-ER inter-regional strengthening (₹2,723 cr), NR-WR Vindhyachal-Varanasi (₹2,368 cr), Maharashtra intrastate Pune project (~₹3,500 cr), Davangere-Bellary (₹1,111 cr), Parli-Bidar (₹1,007 cr), and others.
Supply Chain: The Critical Constraint
- Transformer capacity gap: Current OEM capacity (T&R, Hitachi, Toshiba, CG) is 2,28,000 MVA, which can be augmented to 3,98,000 MVA in 2-3 years. However, demand in FY26-27 is projected at 4,21,000 MVA, leaving a significant shortfall.
- Chinese supplier relaxation under consideration: The government is considering relaxation for Chinese companies already available in India to boost the transmission sector. Management views this as a positive move for the industry, though no specific policy change or timeline was confirmed.
- Import policy unchanged for finished goods: The Government of India is not considering importing transformers as a complete item; only assemblies and components like copper, paper, and core will continue to be imported and assembled in India.
- Bulk procurement as a mitigant: POWERGRID now procures transformers in bulk (30 per package, 10-12 packages per year) to avoid uncertainty when projects are won, securing supply ahead of need.
- Commodity price insulation: Transmission line contracts are awarded on a firm-price basis, so metal price increases in copper and aluminum will not impact returns. For substations, a price variation clause is factored into bidding, so minimal impact is expected.
Dr. R.K. Tyagi: "unless until the Chinese companies available in India, if relaxation by Government of India is given, then it is going to boost the transmission sector. So, it should be a good move for everybody."
New Business & Diversification
- First BESS project: POWERGRID ventured into its first Battery Energy Storage project on a Build-Own-Operate basis in Kalikiri, Andhra Pradesh: 150 MW, 350 MWh, TBCB project with VGF support, estimated cost ~₹250 crores, annual tariff ₹29.52 crores.
- BESS ambition: Management expects 10-15% of total generation capacity to require BESS and stated POWERGRID will aggressively participate as more projects are bid out.
- CERC draft on storage in cost-plus: A draft paper proposes including battery energy storage as a transmission element for grid reliability. If approved, BESS projects would also become available in the RTM model, expanding the opportunity set.
- Africa50 partnership in Kenya: Entered into a partnership for two transmission projects under a PPP model: a 165 km Loosuk-Lessos line with a 400kV LILO at Loosuk, and a 220kV Kibos-Kakamega-Musaga line with a 132kV LILO at Musaga. This is the first independent transmission project in Africa, with risk shared with Africa50, at an estimated cost of ~$311 million. POWERGRID is also working with Africa50 in other countries for similar IPP-model projects.
- Intra-state transmission opening up: States like Maharashtra and Karnataka are beginning to open intra-state projects. Rajasthan has ~₹60,000 crores and Karnataka ~₹60,000-₹70,000 crores yet to be awarded. POWERGRID is evaluating risks and will bid aggressively or not depending on its book position and the specific project's difficulty.
- Market share maintained: POWERGRID is holding a 50-60% share in interstate TBCB projects, and intra-state is gaining traction.
Financial & Operational Performance
- Standalone financials: Q3 total income grew 7% YoY, with 9-month growth at 4% YoY. Q3 PAT grew 7% YoY, while 9-month PAT grew 3% YoY. Consolidated Q3 PAT grew 8% YoY, but 9-month PAT was nearly flat (+0.03%) due to one-time income in the prior year.
- Return on Net Worth declined: RoNW fell from 12.42% to 11.51% because Net Worth increased while profit remained almost the same.
- Commercial performance strong: Realization at 103% of billing (₹29,024 crores vs ₹28,161 crores), and trade receivable days reduced to 24.65 days, the lowest ever.
- Telecom and consultancy growth: Telecom income rose from ₹825 crores to ₹879 crores, with one multi-year order of ₹206 crores and 18 new customers added. Consultancy income surged from ₹427 crores to ₹1,173 crores, with 5 new orders and international presence in 25 countries.
- Operational excellence maintained: Transmission availability remains at international best levels, with annual tripping per line at 0.21, comparable to or better than international best utilities.
- O&M charges fixed: O&M charges are already fixed for the next five years, with the next revision due after 2029, providing cost-side visibility.
ESG & Technology Milestones
- Synthetic ester oil transformers: Commissioned the first 400kV/220kV 315 MVA transformers using synthetic ester oil (vegetable oil) as an ESG step. Earlier, a 400kV reactor was commissioned in 2019, and two transformers at Aizawl and Pusauli were retrofilled with ester oil. Two more ester oil transformers and reactors are on order.
- Asia's first 315 MVA ICT at Bhiwadi: Commissioned recently using biodegradable ester oil, improving environmental performance and fire safety.
- 50% renewable power consumption achieved: POWERGRID achieved its 50% renewable power consumption target by December 2025.
- Insulated cross arm in monopole: Installed recently, reducing RoW from 46m to 31m (a 35-40% reduction), optimizing land utilization and lowering environmental and social impact.
- Emergency restoration capability: Procured a mobile GIS substation (220kV) mounted on a trailer for emergency restoration; 132kV and 400kV versions are ordered and coming shortly.
- Skilled manpower pipeline: Four skill development centers opened at Malda, Banka, Raigad, and Bassi, running 50 batches of 3-month training, producing ~800 trained fitters per year.
Dr. R.K. Tyagi: "It is a vegetable oil. It can be easily decomposed unlike mineral oil. So, it is a step towards ESG."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 CapEx | ₹32,000 crores (raised from ₹28,000 cr) | By March 2026 |
| FY26 Capitalization | ₹22,000 crores (raised from ₹20,000 cr) | By March 2026 |
| FY27 CapEx | ₹37,000 crores | FY27 |
| FY28 CapEx | ₹45,000 crores | FY28 |
| FY27 Capitalization | ₹30,000 crores | FY27 |
| FY28 Capitalization | ₹35,000 crores | FY28 |
| Barmer II to South Kala Amb HVDC award | ~₹35,000 crore project, OBD | 1st April 2026 |
| Bikaner V to Begunia HVDC award | Expected to be awarded | FY27 |
| Paradeep to Andaman HVDC commissioning | 320 kV, 500 MW, ~₹31,000 cr | 2031-2032 |
| Annual transmission line target | Close to 5,500 ckm | By March 2026 |
| Annual transformer capacity target | Close to 60,000 MVA | By March 2026 |
| Project pipeline commissioning | ₹1,95,000 crores (works in hand + WIP) | Next 3-4 years |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Total Income (standalone) | ₹12,436 cr, +7% YoY |
| Total Income (consolidated) | ₹12,599 cr, +7% YoY |
| EBITDA (9M) | ₹29,846 cr |
| Profit After Tax (standalone) | ₹4,160 cr, +7% YoY |
| Profit After Tax (consolidated) | ₹4,185 cr, +8% YoY |
| Earnings Per Share | ₹12.24, vs ₹12.23 YoY |
| Gross Fixed Assets (consolidated) | ₹3,04,336 cr, crossed ₹3 lakh crore for the first time |
| Net Worth | ₹98,906 cr, vs ₹91,000 cr YoY |
| Debt/Equity Ratio | 59:41 |
| Return on Net Worth | 11.51%, vs 12.42% YoY |
| Trade Receivable Days | 24.65 days, lowest ever at end of Q3 |
| CapEx (9M) | ₹26,761 cr, vs ₹17,651 cr YoY |
| Capitalization (9M) | ₹12,915 cr, vs ₹7,423 cr YoY |
| Works in Hand | ₹1,45,513 cr, plus ₹50,000 cr work in progress |
| Transmission System Availability | 99.84% |
| Telecom Income | ₹879 cr, vs ₹825 cr YoY |
| Consultancy Income | ₹1,173 cr, vs ₹427 cr YoY |
| FY26 CapEx Guidance (revised) | ₹32,000 cr, raised from ₹28,000 cr |
| FY26 Capitalization Guidance (revised) | ₹22,000 cr, raised from ₹20,000 cr |
| FY27 CapEx Guidance | ₹37,000 cr |
| FY28 CapEx Guidance | ₹45,000 cr |
| FY27 Capitalization Guidance | ₹30,000 cr |
| FY28 Capitalization Guidance | ₹35,000 cr |
| TBCB Market Share Guidance | 50–60% of new interstate projects |
| Renewable Power Consumption | 50% of total power consumption met through renewable in Dec 2025 |