Hitachi Energy India Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/zl3i641be2adc2135sx3c4g9.pdf

Key Takeaways


Demand Environment

Venu Nuguri: "When we talk to data center developers, there is a lot of plans, but the key is there should be support from government for the same. These projects do not have a long gestation period so if we are talking about 15 GW by 2030, then the project pipeline will be sustainable going forward."

Order Wins & Backlog

Order backlog stands at ₹32,222.1 crs, providing good revenue visibility for the coming quarters.

WinDetails
First BESS project165 MW / 330 MWh in Andhra Pradesh; end-to-end project order excluding batteries but including battery management software integration.
Europe wind evacuation2 GW wind power evacuation project; part of a landmark grid expansion program with three key transmission links collectively delivering 6 GW of clean electricity.
Solar park GIS/GIBSupply of GIS/GIB solutions for a 100 GW solar park in western India; includes a Load Pooling Station and Main Pooling Station with 56 bays of 400 kV GIS and 12.8 km of 400 kV GIB.
Data center ordersMultiple orders from hyperscalers during the quarter, including a 40 × 2500 kVA data center project in Hyderabad awarded by a leading Indian multinational conglomerate.
TenneTCombination of 3 orders related to 2GW TenneT; characterized as "more of services and support from here"; approximate value ₹1,700 cr.

Financial Performance

MetricTrendCommentary
Revenue▲ 68.6% YoYDriven by robust execution of the order backlog.
Operational EBITDA▲ 135.0% YoYIncludes an unrealized forex loss of ₹36.37 cr.
PBT▲ 120.2% YoYDisciplined execution and operating leverage.
Material costs▬ StableMaintained within historical range as % of revenue despite evolving geopolitical environment.
Depreciation▲ QoQReflects ongoing capex toward capacity expansion.
Finance cost▬ StableBroadly stable.
Ajay Singh: "Despite this impact, we were able to maintain total expenses as a percentage of revenue broadly in line with the previous quarter, reflecting our disciplined cost management."

New Growth Engines: BESS, Data Centers, Exports

Venu Nuguri: "More competition is welcome to meet the demand and supply challenges or perceived demand and supply challenges, if any. As long as there is a level playing field, we do not see any issue in competing and ensuring that our margin ambition is met in that."

Capacity, Capex & Execution


Guidance & Commitments

CommitmentSpecificsTimeline
HVDC pipeline conversionOne full greenfield HVDC project under biddingAward expected within 6 months
Railway & metro recoveryProjects expected to pick up based on discussions with rail and metro authoritiesFrom H2 FY27
Karjan facility commissioning20th manufacturing facility, fully digital and smartDecember 2028
BESS scale-upValidate deployed technology first, then scale up slowlyNo date (technology validation dependent)
BESS marginsMargins to "gradually reach the desired levels" as technology matures and localization scalesNo date (localization dependent)
Safety targetRecordable injury frequency rate of 0.09Ongoing
Gender diversityFurther improvement of 3–4 percentage pointsBy 2030
Sustainability targets2030 sustainability targets, including water targetBy 2030

Key Metrics

MetricQ1 FY27
Revenue from operations₹2,493.7 crs, up 68.6% YoY
Operational EBITDA₹399.9 crs, up 135.0% YoY; includes unrealized forex loss of ₹36.37 crs
Profit before tax margin15.6%
Profit after tax margin11.8%
Profit before tax growth120.2% YoY
Other income~₹57 crs, primarily interest income on deposits
Order intake₹5,096.5 crs
Order intake growth excluding HVDC26.1% YoY and 39.7% QoQ
Order backlog₹32,222.1 crs, strong double-digit growth vs Q1 FY26
Export contribution to revenue~25% run rate
TenneT order value~₹1,700 crs, combination of 3 orders
BESS first project165 MW / 330 MWh in Andhra Pradesh, C&I customer
Data center project, Hyderabad40 × 2500 kVA, awarded by a leading Indian multinational conglomerate
Solar park project, western India56 bays of 400 kV GIS and 12.8 km of 400 kV GIB, supporting a 100 GW solar park
Karjan manufacturing facility20th facility, construction began June 2026, commissioning targeted December 2028
Commodity pass-through orders60%–65% of orders are pass-through on commodity prices