Hitachi Energy India Ltd Q3 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/4trrrjtdzxrwfdyrg1cet394.pdf

Key Takeaways


The Quarter: Orders vs. Execution


The Chip Shortage: Impact and Response

Venu: "While a lot of our manufacturing has completed in these panels, but because of some relays not there, so, we are unable to dispatch those things and able to gain revenue. While the cost has come in already, we were not able to gain."

Margin Walk and Cost Structure

A Singh: "If you would have not had this, probably there would be roughly in the range of 2% to 3% margin would be on the upside compared to what we are having."

Energy Transition: The Pipeline Is Real

Venu: "Previously, India is to have one HVDC project for every five or six years, and we said that, we envisage one per year, which is in line with our envision, in line with our thought process is coming out."

Growth Strategy and Capacity Build-Out


Guidance & Commitments

CommitmentSpecificsTimeline
Chip shortage normalizationLead times improving; actions include alternative suppliers, design changes, advance ordersProgressively over the next couple of quarters
Kudus Mumbai revenue startRevenue recognition to begin after design, studies, approvals and engineering phaseMiddle of next financial year
IT independence from ABBTransactional services agreement with ABB for IT services to end2023
Railway OEM bids finalizationFive projects with ₹4,000–₹4,500 cr accessible market; OEMs biddingNext one year or so
Analyst meet at Vadodara facilityPhysical meet to showcase power systems evolution and energy transition readiness; global CTO attendingMarch 3, 2023

Key Metrics

MetricQ3 FY23
Revenue₹1,041 cr
Revenue growth (9M YoY)13%
Orders received₹1,222.1 cr, up 31.3% YoY
Order backlog₹7,231.3 cr, providing ~20 months revenue visibility
Operational EBITA₹29.9 cr
Profit before tax₹13.4 cr
Profit after tax₹4.6 cr
Material cost62–63% of revenue, QoQ
Revenue loss from chip shortage~₹100 cr in the quarter
Bottom-line impact from chip shortage~₹31 cr
Margin upside absent chip shortage2–3% higher at PBT level
Debt level₹275 cr gross, net debt ~₹150 cr
Export order share20–25% of quarterly orders
Service revenue sharehigh single digit percentage, plan to reach double digit
Datacenter orders growth>300% YoY
Royalty expenses3.5% of revenue, range 3.5–4%