Key Takeaways
- Margin recovery on track: Operational EBITDA improved sequentially for the third straight quarter to 6.3%, and management reiterated a clear strategy to reach double digits by fiscal year-end.
- Orders flat but mix improving: Order inflow was flat YoY at INR 1,235 crore, yet renewables orders grew 54% and datacenter orders surged 92%, shifting the backlog toward higher-growth segments.
- Exports and services are the margin levers: Export orders jumped 61% YoY and service orders 71% YoY, both accretive to margins as the company targets a 20-25% export share.
- Mumbai HVDC is now in production: The landmark project has commenced manufacturing and will drive material revenue in coming quarters, with completion on track for mid-2025.
- What to watch next quarter: Whether the sequential margin climb continues toward the 10% target, the pace of revenue conversion from the HVDC project, and any award on the bullet train electrical package.
Margin Recovery & Profitability
- Sequential climb: Operational EBITDA rose from 3.0% in Q1 to 5.8% in Q2 to 6.3% in Q3, driven by revenue accretion from a strong backlog, higher export and service contributions, and new green factories filling up.
- Profit surge off a low base: PBT up 152% YoY and PAT up 400% YoY, helped by normalizing supply chains and consistent expense control quarter-on-quarter.
- Gross margins stable: Management declined to provide a gross margin target but noted overall margin improvement is coming from better order gross margins, cost measures, and a richer service and export mix.
- IT cost tailwind: The company is still under a transition services agreement with ABB India for IT support; it expects to exit that support mostly by mid-next year, which should reduce own infrastructure costs.
- Pricing discipline: India remains a competitive market with commodity prices rising alongside price increases; the company has initiated a pricing excellence strategy to focus on quality orders and value-add pricing without compromising margin.
- FX loss: A INR 9.8 crore foreign exchange loss in the quarter was an accounting restatement entry, not an operating item.
N Venu: "In the last three quarters, so operational EBITDA, you take from a 3% in quarter one and 5.8% and now we came to 6.3%. So sequentially, we are improving it, and we also have a clear strategy to bring the double-digit operational EBITDA by end of the financial year is what we said."
Order Book & Segment Mix
- Flat headline, shifting composition: Total orders were flat YoY at INR 1,235 crore and declined QoQ because the prior quarter carried an exceptional order; base orders excluding the HVDC project and exports still grew 16% YoY.
- Renewables momentum: Orders from renewables grew 54% YoY, driven by utility demand for solar and wind energy, with key wins including 220kV and 400kV AIS substations for renewables projects.
- Datacenter surge: Datacenter orders grew 92% YoY, fueled by the 5G rollout, data localization regulation, and supportive data center policies; a 230kV GIS substation for a Chennai datacenter was commissioned during the quarter.
- Transmission stable, rail soft: Transmission orders held steady while the rail segment saw a slight decline versus the same quarter last year.
- Projects and services lead: The order mix tilted toward projects and services, with utilities rising and EPC as the primary channel; management insisted that a higher EPC share does not mean compromising order quality.
- Export breakout: Export orders rose 61% YoY, driven by transformers and high-voltage products from feeder factories, with demand from Europe, Africa, South and Central America, and the US.
- Service acceleration: Service orders grew 71% YoY, led by utilities and industries, adding a higher-margin recurring layer to the backlog.
N Venu: "just because our EPCs have gone up, not that we compromise our quality of the order. We have a clear strategy on those things, and then we are maintaining it"
Mumbai HVDC & Large Project Execution
- Production underway: Manufacturing for the Mumbai HVDC link has commenced at the HVDC and Power Quality factory in Chennai, marking the project's transition from planning to execution.
- Revenue recognition begun: Initial revenue recognition has started based on milestones, though at a slow pace; material revenue from major items is expected in the coming quarters as manufacturing scales.
- Completion timeline: The contract is on track for completion between March 2025 and June 2025, with execution and manufacturing progressing as planned.
- Competitive moat: Management highlighted that Hitachi Energy pioneered HVDC technology and is approaching 70 years of leadership globally, with roughly 50% of installed HVDC links worldwide running on its technology.
- Localization depth: Approximately 85% of what the company produces globally for HVDC is already manufactured locally in India.
- Pipeline visibility: Two additional HVDC projects are expected to be awarded in the next 12 months, with the Bhadla HVDC tender due by February 1st per the REC website schedule.
N Venu: "we are pioneering this technology, and we will be completing 70 years of this technology globally as an inventor of the pioneering technology by Hitachi Energy and our predecessors... almost 50% of our existing installation HVDC links run through Hitachi Energy technology"
Strategic Initiatives & New Opportunities
- Bullet train bid submitted: The company has submitted bids to EPCs including the winning bidder for the bullet train electrical package; management expects the award timeline in one to two quarters but declined to disclose the opportunity size.
- Leh-Ladakh feasibility study: The technical feasibility study for Power Grid's Leh-Ladakh project is on track for completion by March 31, 2024, with reports being submitted progressively; management believes technical solutions are available but deferred cost-feasibility questions to the customer.
- STATCOM order underway: A STATCOM order with a 24-month completion timeline has started, with the first two quarters focused on engineering and design.
- RDSS pipeline: The pipeline under the Revamped Distribution Sector Scheme is described as "very robust," with the company focusing on SCADA, automation, DMS, and EMS, though management declined to quantify it.
- Reiwa ERP implementation: The multi-year Reiwa ERP upgrade project enters its implementation phase in the coming quarter.
- Sustainability investments: The company is setting up EV charging points, a Battery Energy Storage System, and electrification of equipment such as fork-lifts in coming quarters.
- Training center recognition: The Hitachi Energy TEC Training and Experience Center in Maneja was recognized by the Central Electricity Authority as a Category-I (Grade B) training facility for the transmission and distribution segment.
Related Party Transactions & Governance
- Shareholder approval sought: The board approved a postal ballot notice for material related party transactions with Hitachi Energy Sweden AB up to INR 700 crore in FY23-24, triggered because transactions crossed 10% of the prior year's revenue threshold, a regulatory requirement for prior minority shareholder approval.
- Two-way flow: The INR 700 crore covers both sales (the Indian entity selling to the Sweden factory) and purchases (components for HVDC), not a one-way cost; management corrected an analyst's assumption that this represented a cost that could be localized, noting 85% is already produced locally.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Operational EBITDA target | Double-digit (10%) operational EBITDA | By end of FY25 |
| Export revenue share | Reach 20-25% range, then stabilize at 25% | Not specified |
| Mumbai HVDC completion | Contract completion on track | March 2025 to June 2025 |
| Leh-Ladakh feasibility study | Technical feasibility study submitted to Power Grid | By March 31, 2024 |
| IT cost reduction | Exit ABB TSA support, own infrastructure costs decline | By mid-next year |
| Bullet train electrical award | Award timeline expected | One to two quarters |
| STATCOM project completion | 24-month timeline from start | Within 24 months |
| Bhadla HVDC tender | Tender due date per REC schedule | February 1, 2024 |
| Two HVDC project awards | Two projects expected to be awarded | Next 12 months |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Revenue | ₹1,276.4 cr, +23% YoY and +3.9% QoQ |
| Operational EBITDA | ₹81 cr, +62.2% YoY and +24.6% QoQ |
| Operational EBITDA margin | 6.3%, improved sequentially from 5.3% in Q2 and 3.0% in Q1 |
| Profit before tax | ₹33.8 cr, +152% YoY |
| Profit after tax | ₹23 cr, +400% YoY |
| PBT margin | 2.6% |
| Order inflow | ₹1,235 cr, flat YoY |
| Order backlog | ₹7,552.3 cr, providing revenue visibility for ~22 months |
| Base orders growth | +16% YoY, excluding HVDC project |
| Renewables orders growth | +54% YoY |
| Datacenter orders growth | +92% YoY |
| Export orders growth | +61% YoY |
| Service orders growth | +71% YoY |
| FX loss | ₹9.8 cr in the quarter |
| Utilization level | 75% to 85–90% across factories, lower in new factories |