Key Takeaways
- Record order intake, HVDC-led: Orders hit ₹11,594.3 crores, up 838% YoY, driven by the Khavda-Nagpur HVDC link, while base orders also grew double digits.
- Profit surged on low base and forex: Profit after tax rose nearly 5x YoY to ₹138.2 crores, aided by notional forex gains on export deliveries.
- Backlog at an all-time high: Order backlog reached ₹18,994.4 crores, providing revenue visibility for several quarters, though HVDC revenue will be back-end loaded.
- Balance sheet transformed: Strong collections and the HVDC advance made the company debt-free as of December 31, 2024.
- What to watch next quarter: Whether the renewable segment recovers from its 68% YoY decline, the pace of base-order growth excluding the lumpy HVDC, and any specifics on the ₹4,200 crores fund-raise deployment.
The HVDC Quarter
- Khavda-Nagpur link details: The 800kV, 6,000 MW bi-pole bi-directional HVDC order from PGCIL was awarded to a consortium of Hitachi Energy India and BHEL, covering converter transformers, AC/DC control and protection, gas-insulated high-voltage switchgear, thyristor valves, and 765kV/400kV substation work.
- Revenue phasing is back-end loaded: Revenue from the HVDC project will be low in the first 12 months, with the bulk flowing in the second and third year; contractual timelines are 48 months for Bipole-I and 54 months for Bipole-II.
- HVDC pipeline is structural, not cyclical: Management noted that India's HVDC need has shifted from one project every four to five years to two projects per year, with upcoming projects at Bhadla, Khavda-Olpad, and Pang-Kaithal, though participation in these was not confirmed.
- Order size kept confidential: Management declined to disclose the exact value of the HVDC order, citing ongoing similar projects.
N Venu: "India used to have one HVDC project for every four or five years. But today the need of the hour is one project per year. And now the need of the hour is not one, but two projects per year."
Order Book & Segment Mix
- Base orders grew double digits ex-HVDC: Even stripping out the lumpy HVDC win, order growth was double-digit in the quarter, fueled by exports and domestic segments including data centers and industries.
- Exports crossed 40% of orders ex-HVDC: Key export orders came from Croatia, Indonesia, Azerbaijan, and Canada, reflecting a broadening geographic footprint.
- Industries up ~60% YoY: The industries segment showed strong momentum, while data center orders grew six-fold on a low base, driven by data usage and privacy laws.
- Renewables declined 68% YoY, seen as seasonal: Management expects significant demand from the renewable segment in the coming quarter, attributing the drop to timing rather than structural weakness.
- Services contributed 11% of orders ex-HVDC: Repeat orders came from major steel producers, lifecycle services for thermal plant substations, SCADA upgrades, and renewable study orders.
| Segment | Order Trend | Commentary |
|---|---|---|
| Transmission | ▲ Strong | Grew with and without the large HVDC order |
| Industries | ▲ Up ~60% YoY | Broad-based industrial demand |
| Data Centers | ▲ 6x growth | Low base; AI-ready data centers expected to add further demand |
| Renewables | ▼ Down 68% YoY | Believed to be seasonal; recovery expected next quarter |
| Exports (ex-HVDC) | ▲ Over 40% of orders | Key wins from Croatia, Indonesia, Azerbaijan, Canada |
| Services (ex-HVDC) | ▬ 11% of orders | Repeat orders from steel, thermal, SCADA, renewables studies |
Strategic Moves: Services Unit, Investments & Fund-Raise
- New service business unit from April 1, 2025: A fifth business unit will be created to tap the existing installed base of approximately ₹80,000+ crores, with all existing business units working closely with it to shape end-to-end service opportunities.
- ₹2,000 crores investment plan over four to five years: The plan covers expansions, capacity building, and talent attraction, signaling a multi-year capex cycle.
- Board approved fund-raise up to ₹4,200 crores: Described as an enabling resolution to provide flexibility for managing the capital structure and reacting to potential initiatives; management declined to comment on timing, specifics, or whether it includes an OFS component.
- First-of-its-kind capacity reservation agreement: The consulting team signed a nearly year-long agreement with an Indian customer in the decarbonization space, shifting from project-based to program-based work where one-time engineering is replicated across multiple projects for efficiency and cost benefits.
N Venu: "As you know this is an enabling resolution, so basically it enables the management to be ready and whenever it is needed."
Financial Health
- Revenue up 31% YoY at ₹1,672 crores: Growth was supported by a favorable execution mix and improving operational efficiencies.
- Profit before tax up 4x YoY to ₹184 crores: Notional forex exchange gains on export order delivery were a material contributor, alongside the low base effect.
- Debt-free as of December 31, 2024: A concerted focus on collections, plus the advance from the HVDC project, drove the company to a net-debt-free position.
- Double-digit margin guidance maintained for FY25: Management confirmed the company has already touched the guided level, but declined to give forward-looking indications on margin direction as revenue ramps up, committing only to improving all KPIs subject to market conditions.
Energy Transition & Demand Drivers
- Energy transition momentum expected to persist: Despite nascent signs of subduing economic momentum, management believes the zest to accelerate energy transition will continue, adding vigor to the energy segment with a positive trickle-down effect in coming quarters.
- AI-ready data centers as a demand multiplier: Management noted that ChatGPT queries require 8-10x more energy than a Google search, positioning AI-ready data centers as a structural growth driver for power equipment demand.
- Domestic transmission pipeline robust: Management does not see a major delay in awarding transmission projects, with customers actively finalizing orders.
- Energy storage being assessed: The company is looking at the market, assessing technologies and localization, but has nothing to announce at this point.
N Venu: "The trend around the world what we have seen is that you do one-time, and replicate, two, three-time projects. You design for one project and execute for two, three projects."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Service business unit launch | Fifth business unit to tap ₹80,000+ crores installed base | April 1, 2025 |
| Investment plan | ₹2,000 crores for expansions, capacity, talent | Next four to five years |
| HVDC Khavda-Nagpur execution | Bipole-I: 48 months; Bipole-II: 54 months | Contractual timeline |
| HVDC revenue phasing | Low in first 12 months; bulk in years two and three | From Q3 FY25 start |
| Margin guidance | Double-digit margin for FY25; already touched the level | FY25 |
| Renewable segment recovery | Significant demand expected after 68% YoY decline | Coming quarter |
| Leh-Ladakh HVDC project | Customers working on it; end of coming financial year per management's standpoint | FY26 end (vague) |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Order intake | ₹11,594.3 cr, highest ever quarterly, +838% YoY |
| Revenue | ₹1,672 cr, +31% YoY on favorable execution mix |
| Profit before tax | ₹184 cr, up 4x YoY; includes notional FOREX gains on export deliveries |
| Profit after tax | ₹138.2 cr, up nearly 5x YoY from a low base |
| Order backlog | ₹18,994.4 cr, highest ever, providing revenue visibility for several quarters |
| Cash position | Company became debt-free as of December 31, 2024, aided by HVDC advances and collections |
| Ex-HVDC order growth | Double-digit YoY, driven by exports, data centers, and industries |
| Industries orders growth | ~60% YoY |
| Data center orders growth | 6x on a low base |
| Renewables orders growth | -68% YoY, described as seasonal decline |
| Services share of orders (ex-HVDC) | 11% of total orders |
| Exports share of orders (ex-HVDC) | Over 40% of total orders |
| HVDC Khavda-Nagpur timeline | 48 months (Bipole-I), 54 months (Bipole-II) contractually; revenue low in first 12 months, bulk in years 2 and 3 |
| HVDC local content | 80% to 90% |
| India HVDC market share | 50% (per management); 8 of 16 India HVDC links run on Hitachi technology |
| Planned capex investment | ₹2,000 cr over next 4–5 years for expansions, capacity, talent |
| QIP fund raise approval | ₹4,200 cr enabling resolution approved by Board on January 18, 2025 |