Key Takeaways
- Orders surged 84% for the full year, reaching ₹6,817 crores, driven by utilities, transportation and industries, while exports hit a record high.
- Profitability rebounded sharply QoQ, with PBT quadrupling to ₹65 crores and PAT up more than tenfold to ₹50.8 crores, though chip shortages and commodity prices remain a drag.
- Supply chain pain is easing but not gone: the semiconductor shortage impact halved to ~₹50 crores this quarter, yet stabilization is still 1–2 quarters away.
- A credible path to 10% EBITDA by end-2025 was laid out, anchored on services growth, exports, operational excellence and supply chain normalization, assuming geopolitical headwinds become contained.
- What to watch next quarter: whether the chip shortage impact shrinks further, the pace of margin recovery toward that 10% midterm target, and conversion of the large HVDC and rail tender pipeline into booked orders.
Order Book & Demand Drivers
- Utilities-led order surge: orders grew 84% YoY to ₹6,817 crores, with utilities, transportation and industries as the primary drivers, while the company says the market itself is not growing at that level.
- Exports hit a milestone: exports contributed 19% of orders, the highest ever, sourced from Middle East, Africa and Japan, with a stated ambition to bring exports to 25%.
- Service orders on a positive trajectory: key wins included life cycle service support from a national utility and remote operations for HVDC stations, supporting the plan to grow services to ₹2,000 crores by leveraging a 60+ year installed base.
- Renewable integration orders: cumulative orders secured for integration of over 1 GW of solar power, feeding demand for grid integration technologies under India's 500 GW by 2030 target.
- Rail electrification momentum: Indian Railways' Net Zero by 2030 commitment and electrification of high-density corridors drove growth, with Scott and reconnected transformers supporting the 100% electrification vision over the next 2–3 years.
- Data centre orders dipped this quarter: management attributed the decline to decision delays and does not view it as a persistent trend, expecting a pickup in coming quarters.
- Large order pipeline described as very robust: some decisions may be postponed but the overall pipeline remains strong.
Venu: "We may be having a requirement of 1 HVDC project coming into the market for every year. So that's what exactly I told."
Margin Recovery & Headwinds
- Profitability snapped back from a weak base: PBT quadrupled to ₹65 crores and PAT rose more than tenfold to ₹50.8 crores QoQ, though the prior quarter was exceptionally soft.
- Chip shortage impact halved but persists: the semiconductor shortage caused a ~₹50 crores revenue impact this quarter, down from ~₹100 crores last quarter, with supply chains not yet stabilized and normalization expected to take a minimum of 1–2 quarters.
- Commodity prices and product mix weighed on costs: structured material cost at 65% was slightly higher QoQ due to product mix, while commodity price increases and other expenses continued to pressure PBT YoY.
- Price variation clauses protect the backlog: more than 65% of the order backlog carries price variation clauses, providing a pass-through mechanism for commodity price impacts.
- Personnel expenses improved: on a percentage basis, personnel costs came down from the last quarter.
- Royalty payments defended as access to global innovation: royalty gives same-day access to product releases worldwide, which management argues is essential given the constant portfolio changes required by the energy transition, digitalization and grid resilience.
Venu: "All these things will take us in a sustainable manner to a 10% operational EBITDA level by end of 2025."
Project Pipeline: HVDC, Rail & High-Speed
- One HVDC project booked last year: the company expects roughly one HVDC project to come to market each year, and is targeting Bhadla or Khavda whichever materializes this year.
- Leh-Ladakh HVDC study underway: PGCIL has issued a consulting study for this challenging project, though no order has been booked.
- Vande Bharat and locomotive tenders in play: five large railway tenders covering 9,000 HP, 12,000 HP and train sets are in motion, with some finalized to OEMs; discussions are ongoing for supplying traction transformers, and some may materialize in the last part of FY24.
- High-speed rail tender expected in the next two quarters: the electrical portion of the high-speed rail project is a large tender comprising several stations; the company is working with EPC and OEM partners, but management declined to quantify the opportunity size, calling it a work in progress.
- Management declined to disclose HVDC execution capacity: when asked how many HVDC orders can be serviced simultaneously, the response was that this is internal information.
Competitive Position & Strategy
- 80% of the portfolio is locally manufactured: the company is enhancing production capacity with global feeder factories, and inaugurated an HVDC and power quality factory in Chennai housing the world's second testing lab for power quality control solutions.
- Competition described as intensive: management pushed back on the idea that the business enjoys a restricted competitive set, stating there is a lot of competition across the portfolio.
- Growth strategy targets high-growth segments: the company grew orders 84% while the market did not, attributing this to upfront actions and investments focused on high-growth segments aligned with core competencies.
- Services and exports are the margin levers: improving service potential is positioned as a lever for sustainable profitable growth, alongside operational excellence initiatives and the export push to 25%.
- Management declined to endorse a 12–15% EBITDA ambition: when an analyst asked about longer-term potential for 12–15% EBITDA margins given the technology moat, management stuck to the midterm 10% operational EBITDA target and would not comment further.
Venu: "It needs the strengthening of the grid resilience, or the grid infrastructure needs, our portfolio needs to be robust, our technology needs to be updated and that needs a huge amount of investment and that's exactly our royalty we are paying there to get our product, the moment any product is released anywhere on the same day, same time, we are offering to our customers here."
Sustainability & Operational Milestones
- Safety and sustainability investments accelerated: a safety park was inaugurated at the Mumbai HVDC site, an electrical safety awareness program was rolled out across locations, and a 950 kW solar power installation was initiated at Maneja.
- Fuel transition underway: the company is transitioning from diesel to piped natural gas for heating in small power, traction and instrument transformer factories, aligned with the pledge to adopt 100% fossil-free electricity in operations.
- Digital solutions expanded in steel: the installed base of digital solutions in the steel industry grew during the quarter.
- Board changes: Nishi Vasudeva resigned as Non-Executive Independent Director effective May 24, 2023; Meena Ganesh was appointed as an additional director in a Non-Executive capacity for a 5-year term, subject to shareholder approval.
Venu: "The best way to predict the future is to create it. And that's precisely what we are doing here, shaping a sustainable energy future, not only for today's generation, but those to come."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Operational EBITDA target | Reach 10% operational EBITDA | End of 2025, assuming geopolitical and supply chain headwinds become contained |
| Supply chain normalization | Chip and electronic shortage stabilization | Minimum 1–2 quarters |
| Export share | Bring exports to 25% of orders | No date given |
| Services revenue | Grow services to ₹2,000 crores | No date given |
| Data centre order recovery | Expect data centre market to pick up | Coming quarters |
| Rail traction transformer orders | Some tenders may materialize | Last part of FY24 |
| High-speed rail tender | Electrical portion tender expected | Next 2 quarters |
| HVDC project win | Targeting Bhadla or Khavda project | This year |
| Margin trajectory | Yearly basis, definitely better margins | FY24 |
Key Metrics
| Metric | Q4 FY23 |
|---|---|
| Revenue | ₹1,336 cr, +28% QoQ |
| Full-year revenue | ₹4,483 cr, +14% YoY |
| Orders received | ₹1,262 cr, +3.3% QoQ, +20-21% YoY |
| Full-year orders | ₹6,817 cr, +84% YoY |
| Order backlog | ₹7,071 cr, providing 20 months of revenue visibility |
| Operational EBITDA | ₹76.5 cr |
| Profit before tax | ₹65.1 cr, quadrupled over previous quarter |
| Profit after tax | ₹50.8 cr, up more than tenfold over previous quarter |
| Material cost | 65% of revenue, slightly higher QoQ |
| Export contribution to orders | 19% of quarterly orders |
| Export share in order backlog | 20-23% |
| Services revenue | ~₹78-80 cr, approximately 6% of total |
| Semiconductor shortage revenue impact | ~₹50 cr, down from ~₹100 cr in Q3 |
| Order backlog with price variation clauses | More than 65% |
| Operational EBITDA target | 10% by end of 2025 |