Key Takeaways
- Flat revenue, temporary disruption: Revenue was flat QoQ as unprecedented rains left customer sites unable to accept deliveries and a GST rate reduction added a mechanical drag; production volumes increased, pushing up finished goods inventory that management expects to clear this quarter.
- Cell capacity target pulled forward 18 months: The 4.8 GW TOPCon cell project has been scaled to a 7 GW single-location line, advancing the 10 GW total cell capacity target from FY28 to September 2026, funded entirely through internal accruals.
- Order book swells to INR 6,511 crores in new wins this quarter from top-tier IPPs, while cell order book visibility extends 12 to 18 months as module manufacturers without cell capacity lock in supply contracts.
- Diversification bets are now live: Acquisitions of KSolare (inverters) and Transcon (transformers) closed, a 5 GW ingot wafer project was announced, and BESS first-phase completion is set for June; together these new businesses are targeted to contribute ~30% of revenue over time.
- What to watch next quarter: Whether the elevated finished goods inventory clears as promised, the pace of ramp-up on the new 1.2 GW TOPCon line to full utilization by December, and any final ALMM-3 policy announcement that could unlock the ingot wafer investment thesis.
The Flat Quarter: What Happened and Why It Reverses
- Rain and GST, not demand: Unprecedented rains meant customer sites were physically not ready to receive deliveries, while a reduction in GST rates created a mechanical revenue headwind; neither reflects underlying demand weakness.
- Production kept running: The company continued producing to plan, so finished goods inventory rose; management stated this inventory will clear out in the current quarter.
- Order book remains firm: Contracts in the disclosed order book are firm, with no framework orders or those carrying cancellation clauses included; execution spans 12 to 18 months.
Chiranjeev Saluja: "The contracts on the order book, which we generally share with the shareholders in the market, is firm order books. We never account for any framework or orders which have a possibility of order cancellation clauses."
Cell Capacity: The 7 GW Acceleration
- 4.8 GW became 7 GW at nominal cost: The Naidupeta, Andhra Pradesh TOPCon cell project was scaled up to 7 GW, creating what management called India's single largest, single-location cell line in one building; the upgrade was done at nominal cost and funded entirely through internal accruals.
- Target pulled forward: The original plan to reach 10 GW total cell capacity by FY28 has been advanced by 18 months; the 4.8 GW line arrives in June (implied Q4 FY26 or early FY27), and the 7 GW line by September 2026.
- Why now: Management assessed that most newly announced cell capacity will take two to three years to come online and ramp up, creating an attractive window to capture strong demand with high-quality, high-efficiency cell supply.
- New 1.2 GW TOPCon line: Trial runs began in August; stabilization is nearly complete, with full utilization expected by December.
- Cell efficiency target: Above 25.2%, with a range of 25.2 to 25.4 cited.
- Market tightness thesis: Management expects the cell market to remain tight, protecting both volumes and margins; India's total cell capacity is expected to reach about 80 GW by end of 2027.
Chiranjeev Saluja: "We feel that many companies have announced cell manufacturing plans. Most of this new capacity will take two to three years to come online and ramping up. So, with the demand being so strong and an attractive market opportunity to be captured in this period, we had actually gone back to the drawing board."
Chiranjeev Saluja: "Puneet, it's going to be India's single largest, single location, 7 gigawatt cell line, TOPCon line in one building."
Order Book and the Cell-vs-Module Dynamic
- INR 6,511 crores in new orders won this quarter from top-tier independent power producers.
- Cell order book visibility: Several module manufacturers who are not integrating backward into cells want to block capacity with high-quality supply contracts, giving 12-to-18-month visibility on the cell order book.
- Cell vs module sales is a dynamic optimization: When large non-DCR orders from long-term IPP clients absorb module capacity, the company sells cells directly rather than converting them into DCR modules; the mix is evaluated dynamically to maximize overall profitability.
- Cell realizations marginally increased QoQ, not decreased; management dismissed DCR portal data suggesting a 10-15% drop as misleading because the portal is designed for traceability, not financial analysis, and includes inter-company sales going into module production.
- DCR module margins steady or up; non-DCR module margins slightly down as cell price increases flowed through, though most of those increases have been passed on to clients.
- External vs captive cell split: After initially declining to give a number, management estimated roughly 50-50 for next year under analyst pushback.
Chiranjeev Saluja: "The DCR portal was launched by the Government of India more for traceability rather than doing a financial analysis on sales and production."
New Businesses: Inverters, Transformers, BESS, Ingot Wafer
- KSolare acquisition closed: The inverter manufacturer focuses on the residential market; at 0.1 crore inverters (~3 GW), revenue potential is about INR 1,500 crores, with a target to treble the top line over the next 2 to 3 years. The strategy is to enter residential first, bundle inverters with modules, build a retail distribution network, then expand into utility-scale and increase in-house component manufacturing.
- Transcon acquisition closed: A 23-year-old transformer manufacturer with strong execution capability; last year delivered EBITDA of about INR 30 crores, with significant growth expected this year. Production capacity is expanding from 2.5 GVA to 16.75 GVA by April 2026, moving into MV, HV, and EHV segments. Premier holds 51% at the Transcon level, with an effective ~37% share of the bottom line.
- BESS first phase: A 6 GWh line completes by June next year, capable of producing about 4 GWh of end products; FY27 production is expected at roughly 2 to 3 GWh, equivalent to about INR 1,000 crores plus in revenue. Management noted the assembly-line nature of the business drives very high fixed asset turnover (7x to 10x), delivering attractive returns on capital in line with the current business.
- Ingot wafer project expanded: Original plan of 2 GW by June 2026 has been expanded to 5 GW ingot wafer, to be commissioned by December 2027, with stabilization expected in the first half of calendar year 2028. A second 5 GW phase will follow; bulk of capex comes after the next 12 months.
- ALMM-3 catalyst: The government has released a well-thought-out draft ALMM-3 policy for ingot wafer; final policy is expected imminently and would underpin the backward-integration thesis.
- Combined contribution target: Together with BESS, these new businesses are expected to contribute approximately 30% of revenue over time.
Vinay Rustagi: "You know, given that it is an assembly line business, the fixed asset turnover will be actually very, very high, something like between 7x to 10x. And the result of that will be that the overall return from capital will still be very attractive in line with the current business."
Margins, Costs, and the Silver Question
- Gross margin improved marginally: The increase came from a greater proportion of cells sold in the quarter, increasing volumes driving efficiencies on the sales side, and fixed cost operating leverage.
- Silver price rise absorbed: Silver prices have gone up substantially, causing a marginal increase in BOM cost, but operational efficiency gains fully offset the impact; the company hedges silver at various intervals and expects to continue absorbing price moves with efficiency.
- China price outlook stable: Management's view is that cell and module prices from China have nearly stabilized and do not have much more room to rise from current levels.
- Depreciation variance: Slight variance occurred because accelerated depreciation on certain equipment has been completed; this keeps changing based on evaluation of specific equipment.
- Other income from forex: Largely driven by forex gains as the INR depreciated from ~85.7 to ~88 during the quarter; management noted this is a reinstatement gain, not realized cash, and declined to quantify the amount.
- No margin guidance: Management repeatedly declined to give forward margin guidance, citing board policy, though stated that cell and DCR module margins are stable at current levels.
Vinay Rustagi: "So, I think our view is kind of very hard to say and we will have to see how things develop. But our view is generally that the prices have nearly stabilized and don't have much more room to go up from current levels."
US Expansion and the Policy Backdrop
- US plans reactivated: Old expansion plans were put on hold during US policy uncertainty; with greater clarity emerging, management now sees manufacturing in the US as very attractive, particularly because IRA incentives for manufacturers will stay until almost 2030-32. The US remains terribly undersupplied on the cell side.
- Make in India expectations: Management expects more policy initiatives for inverters, BESS, and the module supply chain in the near future.
- ALMM-2 cost impact contained: Management estimated the increase in cost of power from DCR module requirements at about INR 0.10, calling it a very small increase the market can easily absorb; this addressed a question about a larger INR 0.30-0.40 estimate but did not directly reconcile the gap.
- IPP market outlook constructive: IPPs with three or more years in the business are seen as having strong pipelines and significant execution over the next two to three years.
Vinay Rustagi: "We had put our old plans on hold while all these changes were going on. But now, I think as we begin to kind of get more clarity, it does seem like, making it in the US is going to be very attractive, particularly as the IRA incentives for manufacturers will stay until almost until 2030, '31, '32."
Capital Allocation: No New Debt, Internal Accruals Fund Growth
- Capex funded internally: Most capex spend is coming from internal accruals; management does not plan to take any new debt and is working toward making the company debt-free gradually over time.
- Capex figure withheld: Management declined to give a ballpark capex number for FY27 and FY28, saying it keeps changing based on plans.
- Capacity headroom: If demand is strong, the company may go beyond 10 GW in cell capacity; enough land and facilities are available.
- Retail business build-out: The company is focusing on building out the retail business as a new channel.
Vinay Rustagi: "Our aim remains that we want to kind of focus on scale, on vertical integration, and adopting the latest technology. And we feel that, our business is poised to grow very strongly, given our plans for capacity expansion, backward integration, and diversification into new areas."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| New 1.2 GW TOPCon cell line ramp-up | Reach full utilization | December 2025 |
| 4.8 GW cell line commissioning | Line comes online | June 2026 (implied Q4 FY26 / early FY27) |
| 7 GW cell line commissioning | India's largest single-location cell line | September 2026 |
| Total cell capacity target | 10.6 GW | September 2026 (advanced from FY28) |
| BESS first phase completion | 6 GWh line capable of ~4 GWh end products | June 2026 |
| BESS FY27 production | 2 to 3 GWh, ~INR 1,000 crores+ revenue | FY27 |
| Transformer capacity expansion | 2.5 GVA to 16.75 GVA | April 2026 |
| Ingot wafer Phase 1 commissioning | 5 GW | December 2027 |
| Ingot wafer Phase 1 stabilization | Four to six months post line build-out | First half calendar year 2028 |
| KSolare revenue scale-up | Treble current top line | Next 2 to 3 years |
| New businesses revenue contribution | ~30% of total revenue | Over time (no date) |
| Debt posture | No new debt; become debt-free gradually | Over time (no date) |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue | ₹440 cr (per analyst observation), up from ~₹420 cr QoQ |
| Order wins | ₹6,511 cr in the quarter |
| Order book duration | 12 to 18 months |
| Cell realization | Marginally increased QoQ, no reduction in selling prices |
| Gross margin | Marginally increased QoQ, driven by higher cell sales proportion and operating leverage |
| New TOPCon cell line target efficiency | Above 25.2%, targeting 25.2–25.4% |
| Cell capacity expansion (4.8 GW to 7 GW) incremental capex | ₹502 cr, with 23% saving per GW versus greenfield |
| Cell and module expansion capex (7 GW cell, 5.6 GW module) | ~₹4,000 cr over next 12 months |
| Inventory build-up | ~₹300 cr incremental, due to shipment delays from rains and GST rate reduction |
| KSolare revenue (FY25) | ₹143 cr |
| KSolare target revenue at 0.1 crore inverters | ~₹1,500 cr, translating to ~3 GW capacity |
| Transcon capacity expansion | 2.5 GVA to 16.75 GVA by April 2026 |
| Transcon EBITDA (last year) | ~₹30 cr |
| BESS first-phase capacity | 6 GWh line, capable of ~4 GWh end products, completion by June 2026 |
| BESS expected FY27 production | 2 to 3 GWh, with realizations of ₹60–65 lakh per unit |
| BESS expected FY27 revenue | ~₹1,000 cr plus |
| Silver paste cost | ~$1.4 to $1.45 per watt, up from ~$0.01 a year ago |
| Forex gain driver | INR depreciated from 85.7 to ~88 during the quarter |
| India cell capacity (current) | ~27 GW, production run rate 16–17 GW per annum |
| India cell capacity expectation by end-2027 | ~80 GW |
| Solar capacity auctioned and allocated (utility scale) | More than 100 GW |
| ALMM-2 cost impact on power | Increase of ~₹0.10 per unit |
| Solar plus BESS tariffs | Less than ₹3 per unit |
| Cell sales mix (external vs internal) | ~50:50 expected |