Key Takeaways
- Record H1, but guidance held flat: Sales hit INR18,143 crores in H1, up 157% YoY and already above full-year FY25, yet management explicitly declined to raise its presales guidance.
- One-off NCR boost explains the beat: INR8,300 crores of H1 sales came from NCR, largely the Indirapuram project, a lumpy contribution the existing land bank cannot repeat next year.
- Margins are structurally improving: Residential EBITDA margins are now sustaining at 28–30% as revenues from FY22 launches finally flow through the P&L, and consolidated PAT nearly doubled YoY.
- Price discipline is now explicit policy: The CMD stated prices have peaked and further increases would be counterproductive, prioritizing affordability and demand protection over pushing realizations higher.
- What to watch next quarter: Whether the Q3 launch pipeline converts on schedule, any land acquisition closure in Thane or NCR, and the pace of leasing decisions at BKC and Mahalakshmi as those assets near completion.
Sales Performance & Geography
- H1 sales broke the full-year record: INR18,143 crores in six months surpassed all of FY25, driven by sustained demand and a healthy launch pipeline across key markets.
- Three cities drove the quarter: Bangalore, NCR and Mumbai together accounted for over 80% of Q2 sales, with NCR alone contributing 45% of the half-year total.
- NCR surge is not repeatable: The INR8,300 crores from NCR came largely from the Indirapuram project, a one-off boost; management gave no direct answer on how next year's land bank replaces it.
- Realizations rose across formats: Apartment prices up 8% YoY to nearly INR15,000/sq ft, while plot realizations jumped 43% to INR9,500/sq ft.
- Collections kept pace: Q2 collections of INR4,213 crores grew 54% YoY, with H1 collections at INR8,735 crores, up 55% YoY.
- Old inventory is gone: All sales now come from new launches only, with very low legacy stock remaining.
Zayd Noaman: "We achieved a record-breaking sales of INR18,143 crores in the first half of this financial year. That's a 157% year-on-year growth, surpassing our entire FY25 full-year sales in just 6 months."
Launch Pipeline & Business Development
- Five projects added in Q2: New residential additions carried a GDV of about INR12,600 crores, taking H1 business development to roughly INR33,000 crores across Bangalore, Hyderabad, Mumbai and Chennai.
- Q3 launch slate is specific: Four projects are expected this quarter: Marigold Phase 2 (plotted), Prestige City Fernvale, Eaton Park (both at Sarjapur), and Evergreen at Prestige Raintree Park, all subject to approvals and RERA.
- Q4 pipeline anchored by Hyderabad: Golden Grove in Tellapur (about 0.9 crore sq ft) and Prestige Rock Cliff in Banjara Hills are targeted for Q4, with Rock Cliff approval expected imminently.
- Goa and Bandra projects in the wings: Prestige Sea Scapes in Goa may launch this quarter or next; the Business Day Bandra LIG redevelopment, with offices for sale near the new High Court, is expected in the last quarter.
- Land bank conversion to accelerate: Management expects significant changes in the land bank within 12 to 18 months, with upcoming launches shrinking and new projects flowing from both existing land and fresh acquisitions.
- Monetization target is 12 months: The stated goal is to monetize acquisitions within a year of closing, with clean, litigation-free land enabling near-immediate churn subject only to design and approvals.
Management: "If I'm sitting on land, there will be some trouble in that land or there will be some litigation on that land, which I need to sort out. But if it's clean and clear, the churn becomes almost immediately."
Commercial & Annuity Portfolio
- Office leasing stayed healthy: Gross leasing of 0.23 crore sq ft in Q2, with portfolio occupancy at 93%; Prestige Sky Tech in the financial district is almost fully leased despite market oversupply concerns.
- Retail malls performed: Gross property occupancy rose 10% to INR623 crores, footfalls reached 0.48 crore, and mall occupancy held at 99%.
- BKC and Mahalakshmi timelines are set: BKC should be ready in calendar year 2026 with occupier fit-outs starting in calendar 2027; Mahalakshmi, a high-rise, is expected up and running in calendar 2028 or early 2029.
- Leasing strategy is deliberately slow: Management is holding back on committing more leases at both BKC and Mahalakshmi, preferring to let the assets get ready first before locking in terms.
- No pre-leasing number disclosed: When asked how much of the 2.4 crore sq ft ongoing commercial portfolio is pre-leased, management gave no figure, calling it work in progress and stating product will be leased once ready.
- Data center entry via partnership: The company has land and expertise to build data centers but will partner with an operator to run them, using a capex model with an eventual REIT exit; an announcement was made with the Maharashtra government.
Margins & Financials
- Consolidated profitability jumped: Q2 revenue rose 11% YoY, EBITDA grew 57% with margins expanding to 43.6%, and PAT nearly doubled, up 95% YoY to INR458 crores at roughly 17% margin.
- Residential margins now structural: Earlier subdued margins reflected corporate overhead sitting in the P&L while revenues lagged under the completed contract method; with FY22-launched projects now delivering revenue, residential margins are sustaining at 28–30%.
- Revenue recognition lags sales by years: Revenue booked today reflects what was sold roughly four years back, with plotted development as the only exception to this timing.
- H2 residential revenue to improve: Full-year residential revenue is expected around INR11,000 to INR12,000 crores, with the second half better than the first.
- No move to percentage completion yet: Management will wait and watch on reverting from the completed contract method; auditors suggested running two sets of accounts if Maharashtra numbers grow large, but management called that too confusing.
- Debt to stay within guardrails: Net debt will remain within 0.5x levels; the hospitality IPO will retire debt, and financial closures are done across the board for capex projects.
- Construction spend guided: FY26 residential construction spend is estimated close to INR7,500–8,000 crores.
Pricing Philosophy & Demand
- Price growth is being capped by choice: Management believes prices have reached certain peaks and further increases would be counterproductive, hurting demand and affordability.
- Bottom-line protection, not price maximization: The stated priority is protecting the company's bottom line rather than pushing realizations higher, with the view that demand would drop if prices keep rising.
- Demand is broad-based but luxury has limits: Demand is good across all segments, but the high-priced luxury bracket above INR50–75 crores has a limited addressable market.
- No holding back launches: Management rejected the idea of deferring launches past INR25,000–26,000 crores of presales to roll into next year, stating they will not hold back when the market is good.
Irfan Razack: "Price can't go on infinitely higher. We've reached certain peaks. And I believe while my whole endeavour will be to make sure that the price doesn't go up more than this because then it's counterproductive."
Land Acquisitions & New Markets
- BIAL leasehold for convention center: A leasehold agreement with Bangalore International Airport covers 14.2 acres of prime land for a world-class convention center with a luxury hotel, retail and office space near the airport.
- Hyderabad auction land secured: Purchased land with development potential of over 0.3 crore sq ft, split roughly one-third residential and the balance office with support retail.
- Jijamata land now clean: The land is fully cleared; focus is on building 4,041 EWS homes first, with SOM engaged as architects; planning should close within a month and the project should go to market in about 3–4 quarters.
- NCR and MMR expansion in progress: Management is very sure more NCR land will be tied up in the next two quarters for the next financial year; in MMR, something big in Thane is almost at the verge of closing, with Navi Mumbai and in-town opportunities also being evaluated.
- No BD target given: When asked for a quantum of business development targeted for FY26 or FY27, management gave no figure, stating only that good opportunities will always be explored.
Irfan Razack: "We are not looking -- not only looking at cash flows or top line, we are looking at the bottom line, too."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Presales guidance | Existing guidance maintained; no increase or decrease despite 70% achieved in H1 | FY26 |
| Q3 launches | Marigold Phase 2, Prestige City Fernvale, Eaton Park, Evergreen (subject to approvals and RERA) | Q3 FY26 |
| Q4 launches | Golden Grove (Tellapur), Prestige Rock Cliff (Banjara Hills), subject to approvals | Q4 FY26 |
| BKC project ready | Asset complete for occupier fit-outs to begin | Calendar year 2026/2027 |
| Mahalakshmi project ready | High-rise asset up and running | Calendar year 2028/early 2029 |
| Jijamata market launch | Planning closed within a month; project to market | 3–4 quarters |
| Residential construction spend | Close to INR7,500–8,000 crores | FY26 |
| Full-year residential revenue | Around INR11,000 to INR12,000 crores | FY26 |
| Net debt ceiling | Remain within 0.5x levels; less than INR12,000 crores (~INR7,300 crores) | Ongoing |
| Land bank conversion | Significant changes visible as upcoming launches shrink and new projects enter | 12–18 months |
| Acquisition monetization | Monetize within 12 months of closing | Per acquisition |
| Business Day (Bandra) revenue | Offices for sale near new High Court | Last quarter FY26 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Sales (presales) | ₹6,017 cr, up 50% YoY |
| H1 FY26 sales | ₹18,143 cr, 157% YoY growth, surpassing entire FY25 full-year sales |
| Collections | ₹4,213 cr, up 54% YoY |
| Revenue | ₹2,698 cr, up 11% YoY |
| EBITDA | ₹1,176 cr, up 57% YoY; margin 43.6% |
| PAT | ₹458 cr, up 95% YoY; margin around 17% |
| Residential segment EBITDA margin | 28% to 30% sustainable going forward |
| Unrecognized residential revenue | ₹60,000 cr, to be recognized over 4 to 5 years at 28% to 30% EBITDA margin |
| FY26 presales guidance | ₹25,000 cr; 70% achieved in H1 (per an analyst's math) |
| FY26 residential revenue expectation | ₹11,000 to ₹12,000 cr for full year |
| FY26 residential construction spend estimate | ₹7,500 to ₹8,000 cr |
| Launches in Q2 | 0.39 cr sq ft, GDV nearly ₹4,000 cr |
| Business development added in Q2 | 5 new residential projects, GDV about ₹12,600 cr |
| Office portfolio occupancy | 93% |
| FY26 office exit rent projection | ₹820 cr |
| Retail malls occupancy | 99% |
| FY26 retail exit rentals projection | around ₹275 cr |
| Net debt-to-equity | 0.45x, expected to remain within 0.5x |