Key Takeaways
- FY26 revenue surged 67%: Execution on utilities and infrastructure projects, combined with expanded capacity reaching peak monthly utilisation, drove the strongest quarter in Q4.
- Margins doubled on scale: Operating margins expanded from ~5% to ~10% as the Ghiloth facility scaled, with medium-voltage cables promising a further lift toward 13% at the segment level.
- A new growth cycle is funded: A third facility focused on medium-voltage cables breaks ground with INR40 crores capex, targeting INR250 crores ready capacity by Q1 FY28, funded via internal accruals and debt.
- The model is shifting toward faster cash conversion: Management is deliberately tilting the mix toward private EPC customers, targeting a 5% order book increase from that segment to reduce working capital intensity.
- What to watch next quarter: The pace of the new MV facility ramp, whether receivable days normalise toward the 70-80 day target as guided, and any early signs of MV order inflow from the five newly enlisted states.
Growth Engine: Capacity, Approvals & Execution
- Ghiloth unit 2 hit its stride: The second facility, commissioned in H2 2024, ramped up gradually and reached peak utilisation on a monthly basis by March 2026, directly powering the 70% H2 revenue growth.
- Approvals unlocked the TAM: Over four years, the company secured SEB and PSU approvals across 18 states, transforming its addressable market. The larger Ghiloth plant enabled it to serve these newly approved clients at scale.
- Project-oriented model differentiates: The company operates a made-to-order, project-centric manufacturing model rather than competing with standardised, mass-production cable makers, aligning it with complex T&D and EPC demand.
- Order book kept deliberately short: Management targets a 4-6 month order book to protect margins, because longer-duration contracts can compress absolute profitability when raw material prices rise, even with pass-through clauses.
Naman Singla: "we want to maintain this order book of not more than 4 to 6 months, because that impact on the price increment in the coming years might affect our EBITDA margins in the longer order books."
Margin Trajectory & Mix Shift
- Scale drove the 5% to 10% margin doubling: When sales were ~INR80 crores, margins were compressed by the cost of pushing products across geographies. Current scale and execution capability absorbed those costs, and medium voltage is expected to add further lift.
- LV margins are stable at 10-11%: The base low-voltage cable business delivers consistent segment EBITDA margins in this range, providing a floor for the blended corporate margin.
- MV promises a 13% segment margin: Medium-voltage cables are expected to generate at least 13% EBITDA margin at the segment level, and a blended corporate rate of approximately 12% if MV and LV revenues reach parity.
- FY27 margin guided flat during ramp: Blended EBITDA margin is expected to stay at approximately 11% in FY27 because MV contribution will be modest in the initial ramp phase, with expansion materialising in FY28 as utilisation builds.
Nikunj Singla: "As utilisation of the MV facility improves and product mix gradually shifts towards higher-value products, we believe this should support margin expansion opportunities from FY '27 and FY '28 onwards."
The Medium-Voltage Bet
- Unit 3 is the next growth leg: The new Ghiloth facility is purely focused on medium-voltage cables (up to 33 kV), with groundbreaking completed and production expected to begin by early H2 FY27.
- INR250 crores capacity by Q1 FY28: Total capex of ~INR40 crores will deliver ready capacity of at least INR250 crores, with the company already enlisted in more than five states and confident of securing MV business this year.
- Ramp will be gradual: Management expects approximately 28% utilisation initially, as machinery takes 2-3 months to settle and production increases over 4-5 months, with maximum effort to reach peak utilisation as soon as possible thereafter.
- 33 kV is the ceiling for now: The company has no plans to move beyond 33 kV this year, but notes its current product mix already covers data centre requirements, a key demand vertical.
- The moat is built: Achieving approvals from single-voltage to 33 kV cables unlocks a PAN India market estimated at INR90,000 crores, and the qualification process for a competitor would require at least two to three years of intensive work.
Naman Singla: "we have done the tough part of adding all the product mix that is available till 33 kV, which gives us a market cap as of year 24 of INR90,000 crores PAN India. So, we have done the tough part of getting ourselves approved from a single-voltage cable to a 33,000-voltage cable."
Working Capital & Customer Mix
- Receivables spiked on seasonal Q4 billing: Year-end receivables were elevated because Q4 is the seasonally strongest execution quarter; 35% of outstanding receivables were already collected by May end, and receivable days are expected to normalise to 70-80 days averaged over the year.
- Government business ties up cash: Utility and SEB projects, while a significant revenue contributor, carry longer receivable cycles and milestone-based payment structures that elevate working capital intensity.
- The private-sector pivot is deliberate: Management is targeting a 5% increase in the EPC and private-sector share of the order book to improve cash conversion, reduce working capital intensity, and strengthen balance sheet quality.
- Raw material volatility is passed through: Aluminium price increases from INR280 to INR410 have not impacted inquiry or order inflows because the company forwards volatility to customers, and the sector benefits from government priority on power generation self-reliance.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | At least 40-45% YoY | FY27 |
| Revenue growth | 40-50% YoY minimum | FY28 |
| Blended EBITDA margin | Approximately 11% | FY27 |
| MV segment EBITDA margin | At least 13% | Steady-state (ramp phase) |
| New MV facility ready capacity | INR250 crores | Q1 FY28 |
| Total capex (Unit 3) | ~INR40 crores, exhausted | Q1 FY28 |
| Receivable days normalisation | 70-80 days averaged over the year | H1 FY27 |
| Private/EPC order book mix | Increase by 5% | Undated (future) |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue (FY26) | ₹234.9 cr, +67% YoY |
| Revenue (H2 FY26) | ₹144.2 cr, +70% YoY |
| EBITDA (FY26) | ₹23.5 cr, +61% YoY; margin at 10.0% |
| EBITDA (H2 FY26) | ₹13.7 cr, +50% YoY; margin at 9.5% |
| PAT (FY26) | ₹12.3 cr, +66% YoY |
| PAT (H2 FY26) | ₹6.7 cr, +38% YoY |
| One-time expenses (H2 FY26) | ~₹2 cr pre-tax, post-tax impact ~₹1.5 cr |
| FY27 revenue growth guidance | 40–45% YoY |
| FY27 EBITDA margin guidance | ~11% blended, medium-voltage contribution ramps gradually |
| Order book (as of May end) | ~₹191 cr, including largest-ever single order of ₹32 cr |
| Order book mix | 40–45% EPC, 50–55% government tenders; ~25% medium-voltage cables |
| Capacity utilisation (FY26) | ~55% across existing facilities; near-peak in March 2026 with ~₹30 cr monthly revenue |
| Total debt (as of Mar 31, 2026) | ₹51.5 cr; net debt ₹38.6 cr |
| Receivable days | 85 days; inventory 62 days; cash conversion cycle 81 days |
| Capex plan | ~₹40 cr total; ₹25 cr by H1 FY27, remainder by Q1 FY28; total revenue capacity to exceed ₹600 cr by Q1 FY28 |