Key Takeaways
- Revenue surged 48% YoY, margin in band: Revenue hit Rs.510 crore, driven by advanced-stage work at UP sites, while EBITDA margin of 12.7% stayed within the guided 11%-13% corridor.
- Debt doubled to fund execution: Debt jumped to ~Rs.282 crore as inventory investment in MEP for UP projects ramped up, since revenue recognition only occurs upon installation at site.
- Precast is scaling fast: Full-fledged operations began last year, with a FY24 target of ~Rs.250 crore and a pathway to Rs.1,000 crore in 3-4 years if capacity expands.
- Order inflow ambition is aggressive: Management targets more than Rs.3,000 crore in new orders for FY24, with a bid pipeline of ~Rs.6,000 crore and large station redevelopment bids imminent.
- What to watch next quarter: Whether the Rs.450 crore UP project completion stays on track for March 2024, the outcome of the Ahmedabad and Delhi railway station bids, and the pace of debt reduction toward the Rs.180-200 crore year-end target.
UP Projects & Execution Ramp-Up
- UP sites dominate revenue: Rs.196 crore booked from UP projects in Q1, taking the cumulative to Rs.915 crore; all projects are at MEP and interior work stage and running on schedule.
- Completion timeline: Out of the Rs.576 crore outstanding UP order book, ~Rs.450 crore is expected to be completed by March 2024, with two hospitals continuing through that date.
- SMC administrative building: On fast track; excavation completed and rafts ongoing; Rs.90 crore revenue booked through June 30, 2023.
- Spillover acknowledged but unquantified: Management confirmed spillover from Q4FY23 UP projects is being realized in Q1 and Q2 of FY24, but declined to quantify the amount when asked.
Debt, Limits & Balance Sheet
- Debt doubled on working-capital needs: Debt rose from ~Rs.145 crore in March 2023 to ~Rs.282 crore in June 2023 because inventories were utilized at UP project sites, with additional investment in MEP; revenue recognition follows installation, so the cash cycle lagged.
- Year-end debt target: Management expects debt to reduce to Rs.180-200 crore by end of FY24, and further to Rs.100-150 crore by year-end.
- Bank guarantee limits expanding: A resolution passed to increase limits to a maximum of Rs.3,000 crore, but the actual planned increase is to ~Rs.1,500 crore (fund-based Rs.145 crore), with room to go higher if needed.
- Interest cost trajectory: Interest cost will reduce as debt is repaid within a year, though bank guarantee charges may increase if large projects are secured.
Precast: The Hidden Growth Lever
- Scale and ambition: Full-fledged precast operations started last year, with projects executed up to Rs.80 crore in size; the FY24 target is ~Rs.250 crore, and an individual plant can reach Rs.300 crore.
- Long-term pathway: If expanded from the current facility, precast can grow up to Rs.1,000 crore in the near future after 3-4 years.
- Revenue is embedded, not separate: Precast is backward integration used in composite orders, so revenue is booked in the main revenue stream and not segregated; management declined to break out precast revenue when asked.
- L&T order progressing: The Rs.195 crore L&T precast order received in January is now underway; molds sourced from outside the country and Jaipur are in place, and small supply was initiated last month; completion expected in FY24 with possible spillover to Q1 FY25.
- Capacity expansion is inquiry-dependent: A Rs.20 crore CAPEX for small expansions was approved based on inquiry levels; shed infrastructure is 100% done on the structure side and 50% on roofing; a spare line for beams, columns and slabs can be added with machinery only, but management has no fixed spending plan, saying it depends on inquiry flow.
P. S. Patel: "Mostly 40% time of the person is saved by doing Precast. So probably once someone gets that technology installed at his own campus or at his own facility, he will be tempted to go for future and repeat orders..."
Order Pipeline & Bidding Landscape
- Bid pipeline steady at ~Rs.6,000 crore: Management may also bid for Delhi Airport and Delhi Railway Station, alongside the confirmed station redevelopment bids.
- Ahmedabad (Kalupur) Railway Station: Bidding in September, around the 9th.
- Delhi Railway Station: Bidding by October 9th or 10th; project size ~Rs.5,000 crore; PSP will bid through a JV because bridges constitute 40% of the project and require experience PSP does not have; management declined to name the JV partner.
- Dharoi Dam: Phase I already received and under execution after a government-side delay; Phase II bidding by end of this week; Phase III may be announced in October/November 2023.
- Other outstanding bids: Gem and Jewellery Park, where PSP is second lowest, with finalization expected when the order is given to the lowest bidder; Central Vista MP office project remains at the prequalification stage for 9 months with no announcement yet and a slowed-down timeline.
- Competitive intensity: In high-ticket-size projects, competition is limited to a maximum of 5 or 6 players.
P. S. Patel: "In high ticket size project, the competition will be maximum amongst 5 or 6 players."
Construction Demand Environment
- Gujarat government capex tailwind: Rs.5 lakh crore announced in the February 2023 budget for the next 5 years across ports, roads, railways, hydroelectric projects, DMIC, GIFT, Metro, Bullet Trains, railway redevelopments, urban transportation, tourism, slum rehabilitation, hospitals, education and multi-level parking.
- Broader opportunity set: Huge opportunities expected in the next 3 years: many airports, government-side redevelopment, medical colleges, educational institutions; India is thinking about the Commonwealth Games and Olympics, with Gujarat to bid; large corporate CAPEX from Adani, Reliance, Arcelor Mittal and Vedanta Foxconn.
- Geographic focus: Management answered generally about being open to other states but did not provide a specific market size figure for Gujarat when asked about total addressable market.
Margins & Guidance
- Margin guidance maintained: EBITDA margin guidance remains 11%-13%; Q4FY23 saw ~14%+ due to large project completions, and similar events can cause ±1% variation, but the band is unchanged.
- Revenue guidance intact: FY24 revenue guidance of Rs.2,600 crore maintained.
- Surat Municipal Project contribution: ~Rs.300 crore expected in FY24, with FY25 revenue much higher as finishing activity starts.
- Order inflow target: More than Rs.3,000 crore for FY24.
P. S. Patel: "As I have always mentioned, our margin profile will be in the range of 11%-13% depending upon the stages and execution of the projects."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue | Rs.2,600 crore | FY24 |
| EBITDA margin | 11%-13% range | FY24 |
| UP project completion | ~Rs.450 crore of outstanding Rs.576 crore order book | By March 2024 |
| Surat Municipal Project revenue | ~Rs.300 crore | FY24 |
| Debt reduction | To Rs.180-200 crore; further to Rs.100-150 crore | By end FY24; by year-end |
| Precast revenue target | ~Rs.250 crore | FY24 |
| L&T Precast order completion | Rs.195 crore order, possible spillover to Q1 FY25 | FY24 |
| Order inflow | More than Rs.3,000 crore | FY24 |
| Ahmedabad Railway Station bid | Bidding participation | ~September 9, 2023 |
| Delhi Railway Station bid | Bidding through JV | By October 9-10, 2023 |
| Dharoi Dam Phase II bid | Bidding participation | By end of this week (from call date) |
| Bank guarantee limit increase | To ~Rs.1,500 crore | Not specified |
Key Metrics
| Metric | Q1 FY24 |
|---|---|
| Revenue from operations | ₹510 cr, +48% YoY |
| EBITDA | ₹65 cr, +37% YoY |
| EBITDA margin | 12.69%, vs 13.64% in Q1 FY23 |
| Net profit | ₹37 cr, +29% YoY |
| PAT margin | 7.13%, vs 8.13% in Q1 FY23 |
| Order inflow | ₹758 cr (excl. GST), +38% YoY |
| Outstanding order book | ₹5,321 cr, +15% YoY; 46% private, 55% government |
| Order inflow target for FY24 | More than ₹3,000 cr |
| FY24 revenue guidance | Maintained (previously ₹2,600 cr) |
| Ongoing projects | 48, 81% in Gujarat, 19% in UP |
| UP projects revenue booked in Q1 | ₹196 cr; cumulative ₹915 cr |
| SMC administrative building revenue booked | ₹90 cr till June 30, 2023 |
| Net working capital cycle | 43 days (debtor days 81, creditor days 71, inventory days 33) |
| Total debt | ₹282 cr (long-term ₹97 cr, short-term ₹185 cr); expected ₹100–150 cr by year-end |
| Precast revenue target for FY24 | ₹250 cr (peak capacity ₹300 cr per plant) |