PSP Projects Ltd Q1 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/q4su9vra9pqtxk4gen5whfme.pdf

Key Takeaways


Labour: The Quarter's Binding Constraint

Patel: "We are purely understanding the labor situation is not going to help the organization, and this will continue throughout the year. And day by day, the country's economy is growing fast. So we are very much serious to work on that part also."

The Adani Order Book: Scale and Terms

Patel: "If we can prove on ground and we are able to handle them, most of the projects, we will be given the first priority always."

Project-Level Execution: What Moved and What Stalled


Margins: The Bridge from Here to 8-9%

Patel: "Since the closure of the project has not happened, they are taking undue advantage of the contactor, and that's how it has happened."

Order Book Composition and Non-Adani Opportunities


Guidance & Commitments

CommitmentSpecificsTimeline
Labour shortfall reductionShortfall to reduce further; minor impact remains in Q2Starting August 2025
Order inflow from Adani Group₹7,500-8,000 crore from projects under discussionFY26
EBITDA margin recovery8-9% rangeQ2 or Q3 FY26, probably Q2
Revenue guidanceWill provide after seeing first two quartersAfter Q2 FY26
Working capital / debt improvementFund-based WC from banks to reduce drastically via Adani mobilisation advances (min. ₹750 crore)By end-Q3 FY26
SMC project completionOn track; cannot go beyond FY27FY27
UP project additional costNot more than ₹5 crore total, some possible in Q2Q1-Q2 FY26
Capex as % of revenue3-4% range, ±0.5% for large Adani projectsFY26 and FY27
Precast revenue scale-upUp to ₹500 croreWithin 1-1.5 years
Dharavi project36-month timeline; detailed update possible once basement excavation underwayOctober-November 2025

Key Metrics

MetricQ1 FY26
Revenue from operations₹513 cr, decreased 16% YoY from ₹612 cr
EBITDA₹24 cr, decreased 67% YoY from ₹73 cr
EBITDA margin4.77%, vs 12% in Q1 FY25
Net profit₹13 lacs, reduced 100% YoY from ₹34 cr
Employee cost as % of revenue6.8%, vs typical range of 4% to 5%
Additional expense on UP projects₹4.5 cr, booked in Q1 FY26; up to ₹5 cr possible in Q2
ECL provision₹8.68 cr, vs ₹4 cr in Q1 FY25; includes ₹4 cr for Pandharpur project
Order book (work on hand)₹6,514 cr as on June 30, 2025, 11% YoY growth; Adani projects 27%
Order inflow₹107 cr excluding GST in Q1 FY26
FY26 order inflow guidance (Adani)₹7,000 cr to ₹8,000 cr, projects under discussion
FY26 EBITDA margin guidance8% to 9%, maintained; expected from Q2 or Q3
Labor shortfall37% during April-May 2025, reduced to 19% at present
Net unbilled revenue₹556 cr as on June 30, 2025
Receivables₹525 cr as on June 30, 2025
Short-term borrowings₹338 cr excluding short-term maturities of ₹25 cr
Mobilisation advance₹326 cr as on June 30, 2025
Capex incurred₹32 cr in Q1 FY26, mainly plant and machinery, formwork, cranes
FY26 capex guidance3% to 4% of revenue, plus or minus 0.5% for Adani projects
Non-Adani margin guidance9% to 10%
FY26 revenue guidance (per an analyst's math)₹4,500 cr for FY27, based on order book of ₹6,514 cr and expected inflows
Precast facility revenue target₹400 cr to ₹500 cr, currently at 50%+ utilization; target within 1-1.5 years
Cost of material consumed as % of total expense38.51%, up from 30.03% in Q1 FY25, rise of over 800 bps YoY