Key Takeaways
- Revenue surges, margin lags: H1 FY27 revenue jumped ~60% YoY, putting the company on track to exceed its 30–35% growth guidance, but EBITDA margin sat at ~6.3% because most projects are stuck in the low-margin structural phase.
- The order book is a 3-year visibility engine: At ₹12,872 crores with a maximum 36-month project timeline, the entire backlog converts to revenue within 2.5 to 3 years, supporting a stated 25% top-line CAGR ambition.
- Adani is the anchor and the margin drag: Adani Group projects form ~72% of the order book on a cost-plus model that eliminates material risk but currently earn only 5.5–5.7% margin, pulling the blended number down.
- The margin story is back-end loaded: As projects shift from structural RCC work (30% of scope, slow, low overhead absorption) to finishing and MEP (70% of scope, fast), execution cycles compress to 6–7 months and margins are expected to improve by 1–1.5% in the near term.
- What to watch next quarter: Whether the promised H2 margin lift toward 7% actually materializes as projects transition to finishing stages, and whether order inflow stays on pace for the ₹5,000 crore plus full-year target.
Revenue & Execution Runway
- H1 delivery was the strongest ever: Highest-ever quarterly and half-yearly revenue, driven by healthy execution and improved labour availability, with H1 up ~61% YoY. Management sees potential upside to its 30–35% FY27 growth guidance and is internally targeting beyond 30%, with one analyst’s ~₹4,500 crore full-year assumption described as “fair” as an assumption, while management’s internal target is to cross beyond ₹4,000 crores.
- Second half is structurally stronger: H2 has historically outperformed H1, and the current run rate supports that pattern continuing. The precast facility, running at full capacity, accelerates structural completion to nearly half the usual time, pulling revenue recognition forward even if it does not immediately lift margins.
- Labour scales with ambition: Workforce doubled to 23,000–25,000 from ~11,000 last quarter, though some projects run 10–15% below requirement due to the faster pace. Overall market labour remains sufficient.
- Unbilled revenue is a timing issue, not a risk: The increase stems from government projects (Dharoi Dam, SMC) where last-month rates await certification and GST invoicing. Structurally, ~70% of the last month’s revenue will always sit in unbilled revenue due to the certification lag, and the current bulge is expected to normalize.
Prahaladbhai Patel: “Based on the run rate we are seeing this year, there could potentially be an upside to this guidance, and internally, we are targeting growth beyond 30%. However, at this stage, we would prefer to maintain our market guidance at 30% to 35%.”
Order Book & Pipeline
- The ₹12,872 crore order book converts fast: No project in the book has a timeline beyond 36 months, so the entire backlog executes within 2.5 to at most 3 years. This gives a clear visibility window for the 25% 3-year top-line CAGR target.
- Adani Group provides a captive pipeline: PSP holds a first right of refusal on Adani projects in Gujarat, Ahmedabad, and Mumbai. The company is currently executing two Dharavi projects, with a third possible next year, plus office work at Mumbai International Airport and potential future airport developments. Management confirmed data center build-out capability, describing it as “a simple building with a heavy loading criteria.”
- New order inflow guidance held at ₹5,000 crore plus for FY27: The minimum range remains ₹4,000–5,000 crores approximately, unchanged from prior guidance.
- Public sector and tourism infrastructure add diversification: Commonwealth Games tenders have begun (first tender announced, PSP will participate), and tourism projects at Dharoi, Ambaji, and the completed Kashi project offer a large future scope.
- Selective bidding is the stated H2 priority: Disciplined project execution, timely delivery, cost control, working capital management, and selective purchase of new orders headline the second-half agenda.
Prahaladbhai Patel: “So maximum project time line for any of the projects which is included in this order book is not going beyond 36 months. So we can consider that this is to be done in 2.5 at most is 3 years.”
Margins: The Structural-to-Finishing Bridge
- H1 FY27 EBITDA margin of ~6.3% sits below the ~7% full-year guide: The shortfall is mechanical, not operational. Most projects are in the RCC structural execution stage, which represents ~30% of total project scope and carries lower overhead absorption. The remaining 70% of scope (MEP, civil finishing, interiors) has a much faster execution cycle of 6–7 months versus 18–24 months total, and that faster churn improves overhead absorption and margins.
- Adani projects are the blend-down force: Adani projects currently operate at ~5.5–5.7% margin because they too are stuck in the structural phase. As these projects move into non-structural scope, management expects EBITDA to improve by 1–1.5% in the near term, with potential for more by project end.
- H2 margin expected in the same range as H1, with a possible 1% swing either way: Management sees H2 EBITDA margin potentially reaching 7.5%, and closer to 7% when adjusting for ECL provisions. FY28 EBITDA margin is expected at 7%.
- Medium-term ambition is 7.5–8%, but no commitment: Management sees potential for margins to move toward that range as projects progress but will not commit, citing execution complexities and challenges unique to each project.
- Cost inflation is largely someone else’s problem: On Adani projects (~75% of the book), the cost-plus-percentage model means all material cost differences are reimbursed by the group, so PSP takes no material risk. On non-Adani projects like Ambaji, cement and steel are covered through an RBI Index. Some impact was felt on SMC and RVNL projects from war-related material price increases, but the overall impact on PSP was not significant. Workforce costs have been adjusted ~10% upward since the Adani association to account for inflation.
Prahaladbhai Patel: “I do not see a significant risk of margins falling below 7%. In fact, there could be potential for margins to move towards 7.5% to 8% as the projects progress. However, I would not like to commit to that level at this stage, given that every project has its own execution complexities and challenges.”
Costs, Capex & Balance Sheet
- Employee costs jumped YoY: Rose from ₹33 crores to ₹50 crores, mainly on annual increments and a larger workforce. Depreciation increased from ₹20 crores to ₹26 crores YoY, attributable to asset block additions during H1.
- Capex is measured and growth-linked: FY27 capex is pegged at ~₹190 crore total (~₹90 crore incurred in H1 plus ~₹100 crore in H2). FY28 capex is guided at 3–4% of revenue annually to sustain 25–35% growth. Precast capacity enhancement is underway given visible demand, but no major capex is planned there: only ₹5–10 crore for machines and molds, with infrastructure (sheds) already in place to double capacity.
- Credit limits trimmed: The company reduced sanctioned credit limits by ₹110 crores as they were no longer required.
- ECL provision is a recurring, modest drag: An ₹8 crore provision was taken in Q2 FY27 based on Ind AS metrics and trade receivable aging. A recurring annual ECL addition of ₹3–4 crore is expected going forward.
- UP receivables are a near-term collection item: ~₹20–25 crore has been received, with the remainder expected by Q3 FY27. Surat Diamond Bourse, however, has no commitment received yet; management is hoping project data comes through to enable payment.
Project Execution & Operational Milestones
- Project Ninety was a speed landmark: The RCC structure (3 basements plus ground plus 18 upper floors) was completed in 121 days, making it one of the fastest precast high-rise projects executed in Gujarat. A new corporate house adjacent to it was completed in 240 days including MEP and interior fit-out, with operations commencing November 4, 2026.
- 17 projects completed during the quarter: These included precast concrete cable ducts and noise barriers for NHSRCL (for L&T in Gujarat) and SITC work for Navbharat Mega Developers.
- RVNL project nearing completion: Two out of three buildings (lab and lab building) have been successfully handed over; the hostel building is in progress with flooring, MEP, interior, and facade work underway.
- New opportunities in discussion: A medical college and hospital project in Navi Mumbai is under discussion.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue growth | 30–35% YoY; internal target beyond 30% | FY27 |
| FY27 order inflow | Minimum ₹4,000–5,000 crores; maintained at ₹5,000 crore plus | FY27 |
| FY27 EBITDA margin | ~7%; H2 expected closer to 7% when adjusting for ECL provisions | FY27 |
| FY28 EBITDA margin | 7% | FY28 |
| 3-year top-line CAGR | 25% | FY27–FY29 |
| Order book execution | Entire ₹12,872 crore order book executed within 2.5 to at most 3 years | Within 36 months |
| FY27 capex | ~₹190 crore total | FY27 |
| FY28 capex | 3–4% of revenue annually | FY28 |
| UP project receivables | Remainder expected | Q3 FY27 |
| H2 FY27 EBITDA margin range | Same range as H1, plus/minus 1%; can go up to 7.5% | H2 FY27 |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from operations | ₹1,113 cr, +58% YoY |
| H1 FY27 revenue | ₹1,967 cr, +61% YoY |
| EBITDA | ₹69 cr, +38% YoY |
| EBITDA margin | 6.21%, vs 7.10% in Q2 FY26 |
| Profit after tax | ₹30 cr, +87% YoY |
| Net profit margin | 2.69%, vs 2.28% in Q2 FY26 |
| H1 FY27 EBITDA margin | 6.30%, vs 6.12% in H1 FY26 |
| Outstanding order book | ₹12,872 cr, +30% YoY; 72% group projects, 28% external |
| Order inflow | ₹675 cr in Q2; ₹1,305 cr in H1 FY27 |
| FY27 revenue growth guidance | 30% to 35% YoY; internal target beyond 30% |
| FY27 order inflow guidance | ₹5,000 cr plus for full year |
| Full-year FY27 EBITDA margin guidance | ~7% |
| Current bid pipeline | ₹7,800+ cr, 52% group projects, 48% external |
| Total workforce | 23,000 to 25,000, up from ~11,000 last quarter |
| Precast maximum annual revenue potential | ₹250 cr, operating at full potential |
| Net unbilled revenue | ₹632 cr |
| Trade receivables | ₹809 cr |
| Mobilization advance | ₹933 cr |
| Capex incurred | ₹62 cr in Q2; ₹91 cr in H1 FY27; further ~₹100 cr expected in H2 |
| Expected credit loss provision | ~₹8 cr in Q2 FY27 |
| Surat Diamond Bourse receivables | ₹90 cr outstanding, no recovery |