PSP Projects Ltd Q3 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/f6fn0lu9eooe9u28z89cvmqu.pdf

Key Takeaways


UP Projects: The Quarter's Bottleneck

P. S. Patel: "Lower execution is majorly at UP side... at the finishing stage, we have to get each and every material approved and at the MEP stage, each and every brand has to be approved. And that is the approval which comes from 3 sides - architect, PMC, and the client. So, there it took a little bit of time and that's the only reason for the lower execution."

Order Book & Bid Pipeline

The Surat Municipal Corporation project dominates the inflow story: awarded in January 2023 at ₹1,344.01 crore for two 27-storey high-rise office buildings, with a 36-month timeline. Land is clear (a vacated former jail site), pre-approvals are on track, and work is expected to start within 1 to 1.5 months, though the mobilization advance from the government has not yet been received.

OrderDetails
Surat Municipal Corporation (₹1,344 cr)Two 27-storey office towers; first-year revenue of ₹300–350 cr (mainly structure), remainder spread equally over next two years. Financing clarity from the government side is still awaited.
Gujarat Tourism (₹350 cr)Stood L1; order is in the approval stage after state elections and formation of a new government.
Existing private client (₹200–250 cr)Expected repeat order from a private client, contributing to the FY23 inflow target.
Other Q3 winsGujarat residential project, GIFT City project, an industrial project, a chocolate factory repeat order, and an Adani Airport order.
P. S. Patel: "This year also, we were expecting only Rs. 2,500 crores and it was a luck by chance that we get an opportunity to bid for large project of Sural Municipal Corporation."

Revenue & Growth Outlook

P. S. Patel: "We would like to expect the same growth of 20% to 25%. Even if we get a reduction of Rs. 100 crores this year, we would expect the same next year."

Margins & Costs

Margin walk (YoY)Impact
Employee expenses (appraisals, increments, new hires, managerial remuneration)Negative
Finance costs (higher fund-based limit utilization, higher interest rates, BGs for new projects)Negative
Other income (absence of ₹2 cr impairment reversal that benefited Q2)Negative
Net change: EBITDA margin 12.39% vs 15.25% YoY–286 bps
P. S. Patel: "I would like to say that EBITDA for a construction company to justify each and every project may vary from 1% to 2%. But yes, the confidence with which we bid the tender and confidence with which we execute the project, I think we should remain in that range only."

Balance Sheet & Cash Flow


Guidance & Commitments

CommitmentSpecificsTimeline
FY23 revenue~₹2,100 crore (implies ~₹900 crore in Q4)FY23 (March 2023)
FY23 order inflow₹3,800–4,000 crore, contingent on Gujarat Tourism and private-client ordersFY23 (March 2023)
FY24 revenue growth20–25% growth, implying ₹2,600–2,700 croreFY24
EBITDA marginRemain in 11–13% rangeOngoing
Surat project startWork to begin within 1–1.5 months; first-year revenue ₹300–350 croreStart by ~March 2023; FY24 for first-year revenue
UP project execution₹100 crore per month combined (₹300 crore in Q4)Q4 FY23
Debtor daysNot to exceed 60 days for the full yearFY23
Annual capex3–4% of revenue; could rise by 1% if extra orders come suddenlyOngoing

Key Metrics

MetricQ3 FY23
Revenue from operations₹497 cr, +2% YoY
EBITDA₹62 cr, -17% YoY
EBITDA margin12.39%, vs 15.25% in Q3 FY22
Net profit₹35.32 cr, -25% YoY
PAT margin7%, vs 9.5% in Q3 FY22
Order inflow (FY23 to date)₹3,294 cr, surpassing guidance of ₹2,500 cr
Outstanding order book₹6,418 cr as of Jan 2023, including SMC project of ₹1,344.01 cr
Work on hand₹5,075 cr as of 31 Dec 2022
FY23 revenue guidance~₹2,100 cr, implying ~₹900 cr in Q4
FY24 revenue guidance~₹2,600–2,700 cr, growth of 20–25%
FY23 order inflow guidance (revised)₹3,800–4,000 cr, up from ₹2,500 cr
Bid pipeline~₹4,500 cr, 60% private, ~25% from Gujarat
UP projects Q3 revenue₹165 cr, cumulative ₹417 cr till 31 Dec 2022
Net working capital days41 days, debtor days 79, creditor days 60, inventory days 22
Long-term borrowings₹51 cr, vs ₹46 cr in Q2 FY23
Short-term borrowings₹140 cr, vs ₹111 cr in Q2 FY23