Key Takeaways
- Strong revenue, margin miss: Revenue surged 40% YoY to ₹697 crore, but EBITDA margin contracted to 10.25% from 12.39% as the company spent heavily to accelerate completion of its large UP projects.
- Order book shrinks on fast execution: The outstanding order book fell 12% YoY to ₹4,443 crore, a direct consequence of record quarterly execution outpacing new order inflow.
- The Surat Diamond Bourse overhang: ₹150 crore in certified bills remain unpaid as the client withholds payment to force a compromise on a separate ₹500 crore claim, driving up debt and delaying a potential equity raise.
- Precast is a margin lever, not yet a margin driver: The precast business is EBITDA-positive but below corporate margins at 40-50% utilization; management sees a path to 11-12% margins at 80% utilization and a potential 3-4% premium once the technology is widely adopted.
- What to watch next quarter: The outcome of the SDB Section 9 hearing by early March, any conciliation progress that unlocks cash and reduces debt, and whether Q4 margins rebound as the drag from UP project completion costs rolls off.
Revenue & Margin Performance
- UP projects drove the top line: Execution on UP government projects contributed ₹250 crore in the quarter, pushing total revenue to ₹697 crore. The company moved aggressively to complete major projects by December and all by March, incurring an extra ₹4-5 crore in labor and management costs to accelerate work.
- Cost structure swelled across the board: Employee costs rose on appraisals processed in Q3, finance costs climbed on higher short-term borrowings and bill discounting, and depreciation increased from ₹34 crore in fixed asset additions. Other expenses jumped from ₹5.2 crore to ₹8.51 crore, largely due to a ₹3 crore ECL provision on trade receivables.
- Margin guidance narrowed, not abandoned: Management now frames 11-12% as the conservative range, down from a previously cited 11-13%, attributing the 1-1.5% band of uncertainty to the inherent difficulty of pricing EPC risks within a 20-25 day bid window.
- Q4 recovery hinges on UP completion: With only ₹60+ crore of work left on UP projects, management expects margins to return to the original expected range, though it declined to give a firm Q4 commitment.
P.S. Patel: "It is very difficult for a contracting firm when we are working more on an EPC project to envisage the exact margin what will happen because there are so many uncertainty in EPC project. Sometimes, you get a benefit of 1% or 1.5% and sometimes you get a loss of 1-1.5% because you are not able to envisage the whole project within 20 - 25 days of bidding."
Surat Diamond Bourse: The Balance Sheet Anchor
- The core dispute: SDB was completed in March 2020 with virtual completion by June 2022. The client certified and approved some bills but, upon reviewing the ₹500 crore claim in detail, began withholding existing payments of ₹150 crore to pressure the company into a compromise. Management insists its claims are clear and approved, with only certification pending on the ₹150 crore.
- Debt has risen since March 2022 primarily because money is stuck in SDB and UP projects. If both are recovered, management says there will not be much requirement for debt to go up further.
- Section 9 hearing is about protection, not payment: The company filed for interim relief to safeguard its money before arbitration. The hearing, expected to conclude before March 5, will determine how much the client must withhold or secure via bank guarantee, not release cash immediately.
- No provision taken: The SDB amount stands in the books as the company remains hopeful of recovery.
- Conciliation vs. arbitration fork: If conciliation succeeds, a resolution could come by March; if not, arbitration will take a minimum of one year. Management is inclined toward conciliation but not at a deeply discounted figure like ₹50 crore, insisting its stance depends on the client's intention and the strength of its contractual claims.
P.S. Patel: "They are trying to push in a way that I come to compromise easily for the 500 crores claim, that must be the reason."
Order Book & Bid Pipeline
- Order book declined on execution velocity: The outstanding order book fell 12% YoY to ₹4,443 crore as the company completed seven projects in Q3, including a residential project for Adani Realty and multiple precast industrial warehousing and box culvert projects. Only two new projects were awarded in the quarter.
- FY24 order book target intact: Management reiterated its ₹3,000 crore order book target for FY24, stating it is still on track.
- Bid pipeline stands at ₹6,000 crore excluding the cancelled Delhi railway station tender, spread across Madhya Pradesh, Odisha, Delhi, and UP. The company is getting pre-qualified for larger projects as part of a strategic move up the value chain.
- Two known cancellations: The Delhi railway station tender (₹4,800 crore) is confirmed cancelled. The dairy plant project in Rajkot (₹441 crore) was cancelled because bids exceeded the client's budget; a re-tender with reduced scope of ₹350-400 crore is expected by end of March or early April.
- Lulu Mall on the horizon: The company will participate in the Lulu Mall project, with the civil portion estimated at ₹500-1,000 crore and the tender expected after March.
Precast: Nascent Margins, Future Optionality
- Current state: The precast business is EBITDA-positive but not yet at the 11-12% corporate margin level, operating at 40-50% capacity utilization. The company delivered 12 lakh square feet of warehouse facilities and compound walls at a speed of 1 km per month over the last twelve months.
- The margin roadmap: At 80% utilization, management expects to achieve 11-12% margins. Longer-term, once the technology gains universal acceptance and demand outstrips supply, the company believes it can command a 3-4% margin premium for speed and reliability.
- Capex is measured: 9M capex of ₹142 crore included ₹74 crore for precast facilities. FY25 capex is expected at ₹100-100+ crore (3-4% of revenue), with no large precast outlays unless a major infrastructure order requiring new molds materializes.
P.S. Patel: "on the later stage, again, when this technology is universally accepted and there is a shortfall and people requiring works to be completed before time or on time, they will be paying us more. So, at that time we can increase our margins of 3% or 4% higher."
Capital Structure & Equity Raise
- Promoter stake reduced to 66.2% from 74% due to a personal requirement; management stated it will remain at this level for one year.
- Enabling resolution for ₹300 crore equity raise was approved by the board for growth capital, primarily to support bank guarantees on new orders. Management emphasized it is not urgent.
- SDB outcome dictates the QIP decision: If conciliation yields ₹300-350 crore, management will reconsider whether to proceed with a QIP. If arbitration drags on for another year, a QIP may become necessary to ease working capital and reduce interest costs.
- Debt reduction path: If SDB money of ₹300 crore arrives within one month before March, debt levels will fall below normal. Separately, a substantial reduction is expected once UP projects conclude in the next couple of quarters.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY24 order book | Achieve ₹3,000 crore order book | FY24 |
| FY25 revenue | Target ₹3,000 crore revenue | FY25 |
| FY25 order inflow | Order inflow of ₹3,500 crore | FY25 |
| EBITDA margin | Maintain 11-12% range | Ongoing, recovery expected from Q1 FY25 after UP projects end |
| Debt reduction | Substantial reduction once UP project is over | Next couple of quarters |
| SDB Section 9 outcome | Court decision on money protection mechanism | Before March 5, 2024 |
| SDB resolution | Conciliation could end the matter; otherwise arbitration | March 2024 (if conciliation); minimum one year (if arbitration) |
| Dairy plant re-tender | Client to issue new tender at ₹350-400 crore | End of March or first week of April 2024 |
| FY25 capex | ₹100-100+ crore (3-4% of revenue) | FY25 |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Revenue from operations | ₹697 cr, +40% YoY |
| EBITDA | ₹71 cr, +16% YoY |
| EBITDA margin | 10.25%, vs 12.39% in Q3 FY23; impacted by ~₹4–5 cr extra labour cost to speed up UP projects |
| PAT | ₹33 cr, -8% YoY |
| PAT margin | 4.63%, vs 7.01% in Q3 FY23 |
| Order inflow (Q3) | ₹1,060 cr (excl. GST); cumulative 9M inflow post LOA: ₹1,995 cr |
| L1 orders outstanding | ₹928 cr as of call date |
| Outstanding order book | ₹4,443 cr, -12% YoY; 49% private, 51% government |
| FY24 revenue guidance | ₹2,500+ cr |
| FY25 revenue target | ₹3,000 cr |
| FY25 order inflow guidance | ₹3,500 cr |
| EBITDA margin guidance | 11–12% going forward |
| Net working capital days | 38 days (debtor days: 63, creditor days: 60, inventory days: 35) |
| Gross debt (short-term + long-term) | ₹478 cr (long-term: ₹75 cr incl. ₹50 cr ST maturities; short-term: ₹403 cr excl. ST maturities) |
| Net unbilled revenue | ₹409 cr |
| Precast plant capacity utilisation | 40–50% of 30 lakh sq ft annual capacity |
| Surat Diamond Bourse total claim | ₹532 cr (₹140 cr booked + ₹392 cr disputed claims); Section 9 hearing underway |