Key Takeaways
- Record revenue, margin masked by one-off: Q3 FY26 delivered the best-ever quarterly revenue of ₹771 crores, but reported EBITDA margin of 6.73% absorbed a ~1% hit from a one-time ₹8 crore employee benefit provision tied to the new Labour Code.
- Order book reset, not a collapse: The order book fell from ₹9,900 crores to ₹9,200 crores due to ₹800 crores in combined cancellations and scope revisions, a cleanup that management frames as a one-time adjustment rather than a demand signal.
- FY27 ambition is aggressive: Management guided FY27 revenue of ₹4,000–4,500 crores minimum, a leap from FY26's ₹3,100–3,200 crores, anchored on Adani Group commitments and a ₹7,000–8,000 crore annual order inflow run-rate.
- Adani concentration is the strategy: The firm is deliberately steering toward a 75–80% Adani Group, 15–20% non-Adani mix, stepping away from smaller government bids and betting its future on the Group's pipeline.
- What to watch next quarter: Whether the ₹3,000 crores of orders under discussion actually close by March, the Ambaji Corridor letter of intent arrives, and if the Dharavi Matunga block (~₹2,000 crores) is signed before year-end.
Revenue & Margin Performance
- Top line: ₹771 crores in quarterly revenue, the highest ever, driven by better workfront availability and improved labor deployment across active sites.
- EBITDA margin: Reported at 6.73% but would have been ~7.71% without the ₹8 crore one-time provision for gratuity and leave encashments triggered by the new Labour Code notified in November 2025.
- Gross margin: Declined 70 bps QoQ, attributed by the CFO to newly started projects still in their initial execution stage, which typically carry lower early-phase margins.
- Depreciation: Rose from ₹19 crores to ₹24 crores sequentially, reflecting asset additions during the current financial year.
- Net margin path: Management sees 1.5% to 2% improvement on the existing 2.14% net margin as finance costs ease and depreciation stabilizes, targeting 3.5% to 4% net.
Prahaladbhai Patel: "So what we told you that we'll be near to 7% to 8% this quarter and probably on an average 8% to 9%, that's still achievable. So, though it shows 6.71%, but that is an impact of 1% directly because of this New Labor Code."
Order Book & Inflow Dynamics
- Order book drawdown: The book shrank from ₹9,900 crores to ₹9,200 crores. Management first characterized the reduction as ₹100–150 crores, then acknowledged the total impact of cancellations and scope revisions was ₹800 crores when pressed by an analyst.
- Q4 inflow target: ₹3,000 crores of orders are under discussion, excluding the ₹965 crore Ambaji Corridor project where PSP is the lowest bidder but awaiting a formal order.
- March order book target: Management expects to exit FY26 with an order book of ₹11,000–12,000 crores, down from an earlier guided range of ₹14,000–15,000 crores.
- FY27 inflow run-rate: A minimum of ₹7,000–8,000 crores from the Adani Group is the working assumption, calibrated to support the ₹4,500 crore revenue target at a 1.5x to 2x book-to-bill.
- Project closures: Five projects were completed in Q3, including the Veer Savarkar Sports Complex (targeted for Commonwealth 2030 and Olympics 2036), Ahmedabad Airport forecourt development, a CEPT University studio building, and an industrial tea processing facility for Waghbakri Group.
Prahaladbhai Patel: "See present outstanding order book is to the tune of INR9,100 crores. So probably if we had INR2,000 crores to INR3,000 crores, which we are expecting by March, so probably that will be in the range of INR12,000 crores minus the quarter. So may not reach to INR14,000 crores, but will be in the range of INR11,000 crores to INR12,000 crores."
Adani Concentration & Strategic Direction
- Deliberate tilt: Management is actively steering the portfolio to 75–80% Adani Group and 15–20% non-Adani, explicitly choosing not to bid for smaller government projects.
- Subsidiary activation: PSP Projects & Proactive subsidiary is taking on more MEP orders bundled with new construction, and some projects are being split into labor and material components with supplier orders routed through the subsidiary.
- Commodity protection: Adani Group contracts carry 100% pass-through on rising commodity prices, while government fixed-price contracts are covered by price variation clauses indexed to the RBI index.
- Precast captive demand: The precast facility runs at 80–90% utilization for captive and Adani projects, with some external orders from L&T and other corporates.
Prahaladbhai Patel: "We would like to maintain our presence in the market by thinking about 15% to 20% non-Adani and 75% to 80% from Adani group. And that's how we are not also bidding for the smaller projects of the government side."
Key Project Updates
- Dharavi: Excavation is nearly complete despite difficult conditions (no blasting beyond 6 meters in Mumbai); foundation work is expected to start within 1–1.5 months. Management deflected a question on BMC election impact, saying it is a group-level call and not their concern.
- Dharavi Matunga block: A new ~₹2,000 crore project under discussion, expected to close before March.
- Maharashtra (Mahim): Sheet piling is done, excavation is at the last layer, and foundation work is expected to start by March, which will begin generating meaningful revenue.
- Ahmedabad Airport: Both inside and outside projects are running at full pace, with 75% out of the basement and ground-floor work underway at some levels.
- Ambaji Corridor: PSP is the lowest bidder for the ₹965 crore temple development project but is still waiting for the formal order.
- UP projects: Cost overruns that plagued the last 2–3 quarters have been streamlined; no overruns were recorded in Q3.
Balance Sheet & Capital Allocation
- Bhiwandi arbitration award: PSP won a favorable award of ₹61.44 crores principal plus 9% interest p.a. (11% after 60 days); the arbitration process is concluded and payment is due within the 60-day window unless the client appeals.
- SDB receivables: Stuck at ₹90 crores, unchanged from last quarter; management says it will be paid with interest as committed but offered no timeline.
- QIP proceeds: The QIP completed two years ago has been deployed into working capital; ₹150 crores of capex was incurred this year without taking long-term term loans against equipment, improving fund-based facility utilization.
- Capex: ~₹200 crores total for FY26, with ₹40–50 crores more expected in Q4. For FY27 and FY28, capex is expected to moderate to 3–4% of revenue.
- Depreciation run-rate: ₹24–25 crores per quarter is expected to persist, reflecting the ₹153 crores in asset additions during the current year.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 revenue | ₹3,100–3,200 crores | FY26 (March 2026) |
| FY27 revenue | ₹4,000–4,500 crores minimum | FY27 |
| Q4 FY26 EBITDA margin | 7–8% (8–9% long-term average still achievable) | Q4 FY26 |
| Order book exit | ₹11,000–12,000 crores | March 2026 |
| FY27 order inflow | ₹7,000–8,000 crores from Adani Group | FY27 |
| Dharavi foundation start | Foundation work to begin | Within 1–1.5 months |
| Dharavi Matunga project close | ~₹2,000 crore project signing | Before March 2026 |
| Bhiwandi award payment | ₹61.44 crores + interest due within 60 days unless appealed | ~March 2026 |
| Net margin | 3.5–4% (1.5–2% improvement from current 2.14%) | No date; tied to lower finance cost |
| Capex intensity | 3–4% of revenue | FY27 and FY28 |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue from operations | ₹771 cr, +24% YoY and +11% QoQ |
| 9M FY26 revenue | ₹1,978 cr, +9% YoY |
| EBITDA | ₹52 cr, +47% YoY |
| EBITDA margin | 6.73%, vs 5.67% in Q3 FY25; one-time labour code provision of ~₹8 cr impacted margin by ~1 ppt |
| Net profit | ₹16 cr, +159% YoY |
| FY26 revenue guidance | ₹3,100 cr to ₹3,200 cr, reaffirmed |
| FY27 revenue guidance | ₹4,000 cr to ₹4,500 cr minimum, early indication |
| Order inflow | ₹957 cr, +151% YoY |
| Outstanding order book | ₹9,178 cr, +43% YoY; 59% group projects, 41% external |
| Bid book | ₹6,600 cr, 60% group projects, 40% external; emerged lowest bidder for Ambaji Corridor at ₹965 cr |
| FY27 order inflow guidance | ₹7,000 cr to ₹8,000 cr minimum from group projects |
| Capex incurred during Q3 | ₹80 cr; YTD capex ₹153 cr; full-year FY26 target ~₹200 cr |
| Gross block | ₹762 cr; net block ₹414 cr as of Dec 31, 2025 |
| Net unbilled revenue | ₹648 cr |
| Trade receivables | ₹635 cr |
| Arbitral award (Bhiwandi) | ₹61.44 cr principal awarded, plus 9% interest; total ~₹79 cr as of Jan 30, 2026 |