Key Takeaways
- Record FY22, but order inflow halved: Revenue grew 41% YoY to ₹1,749 Crores and net profit nearly doubled, yet FY22 order inflow fell to ₹1,802 Crores from ₹2,441 Crores as project awards were delayed and the company turned selective.
- Margin spike is not the new normal: EBITDA margin hit 14.67%, boosted by one-off dispute resolutions on completing private projects; management guides a conservative 11–12% for FY23, citing commodity pressure and projects without price escalation.
- Surat Diamond Bourse unlocks the next tier: The completion certificate, received just after the last tender closed, now makes PSP eligible to bid for Central Vista and projects above ₹2,000 Crores, a gate it could not previously pass.
- Two legacy projects remain a drag: Bhiwandi and Pandharpur are at a standstill; Bhiwandi’s revival hinges on an arbitration outcome and cost escalation to ₹1,050 Crores, while Pandharpur may require legal action to recover ~₹17 Crores in overdue payments.
- What to watch next quarter: Whether the ~₹500 Crores of Q1FY23 order wins converts the guided 20–25% inflow growth into a visible backlog build, and whether the Bhiwandi arbitration in June delivers a path to revival.
FY22 Performance: A Record Year With a Caveat
- Top-line surge: FY2022 revenue of ₹1,749 Crores, up 41% YoY, was the highest ever, driven by strong execution across the portfolio.
- Profitability leap: EBITDA grew 90% YoY to ₹257 Crores and net profit nearly doubled to ₹161 Crores; PAT margin expanded from 6.4% to 9.1%.
- The margin quality question: The 14.67% EBITDA margin ran 1–2% above normal because 17 projects were completed, mostly private-sector ones where cement, steel and materials were pass-through, so raw-material cost pressure was limited; additionally, long-standing small disputes on Surat Diamond Bourse, BSE Forum and Kashi Vishwanath were resolved before completion, pulling in revenue that was previously uncertain.
- Q4 gross margin spike: Gross margin exceeded 22% in Q4, driven by the same completion of major private projects and dispute resolutions on high-level turnkey jobs.
- Employee cost step-up: Q4 employee cost rose to ~₹25 Crores because annual increments and increased managerial remuneration were included; this run rate is expected to continue going forward.
Patel: "Yes, if everything normalized, we can expect 12% to 13%. There is no doubt about it."
Order Book & Inflow: A Thin Pipeline Demands a Strong FY23
- Record order book, but inflow weakened: The closing order book reached an all-time high of ₹4,324 Crores, yet FY2022 order inflow fell to ₹1,802 Crores from ₹2,441 Crores in FY2021 because of delays in project awarding and the company being selective about opportunities targeted for FY2023.
- FY23 inflow guidance: Management expects 20–25% growth over FY2022 inflows, implying more than ₹2,000 Crores, with ~₹500 Crores of orders already announced in Q1FY23.
- Central Vista gate now open: PSP received the Surat Diamond Bourse completion certificate just after the last Central Vista tender closed, which disqualified it at the time; the certificate is now in hand and the company will participate in the re-tender, while also becoming eligible to bid for projects above ₹2,000 Crores.
- Outstanding bid pipeline: The Central Vista bid pipeline of ₹1,172 Crores sits separate from the broader ₹4,500 Crores outstanding bid pipeline.
Patel: "That certificate was available to us just before the end of the closure the last time, so we could not bid that time, so we were disqualified, but that certificate we received just after the closure of that tender."
Key Project Updates: One Finishing, Two Stalled, Seven Starting
- Surat Diamond Bourse in handover: Towers were handed over 25 days ago; the spine connecting all nine towers is to be concluded by month-end, with remaining infrastructure activities to be completed by June 15, 2022; cumulative revenue stands at ₹1,803 Crores out of the ₹1,850 Crores revised order value.
- UP Medical College projects mobilized: All seven projects have started; two were delayed because foundation work required decisions on pile versus raft foundation and whether to include a basement, causing design changes; finishing and MEP material orders are placed, with a target to complete by March 2023.
- Bhiwandi at standstill, arbitration underway: The project is stuck; discussions with the Municipal Corporation are ongoing for revival at an escalated cost of ₹1,050 Crores; an arbitration hearing is set for June, and management is hopeful of a fruitful outcome, though if cost escalation is not granted, ₹600 Crores of value will not materialize in any profits; a provision of ₹9.64 Crores has been made for expenses.
- Pandharpur stuck on payments: Work has stopped due to ~₹17 Crores in long-overdue payments; management is still discussing with the Municipal Corporation but may have to pursue legal action if there is no resolution.
- Provisioning completed: A total of ₹9 Crores was expensed across Bhiwandi and Pandharpur, with an additional ₹3 Crores provision taken in Q4, completing the provisioning.
Precast Business: Early Traction, Modest Scale
- Revenue and orders: The precast segment generated ₹15 Crores in revenue in Q4FY22 and recorded order inflow of ₹59 Crores during FY2022.
- Factory commissioned: Installation and commissioning of the precast factory was completed during the year, with total capex of ₹110 Crores.
- Enquiry pipeline building: Enquiries are increasing from Reliance, warehousing, city redevelopment projects, and the L&T bullet train infrastructure project; the bullet train order is expected to be included in the near future.
Margins & Costs: Conservative Guidance With Upside If Commodities Cool
- FY23 EBITDA margin guided at 11–12%: Management is explicit that this is conservative, factoring in commodity price pressure and the completion stage of projects without price escalation clauses, such as the UP Medical College projects.
- Steel duty a tailwind: The Union government’s imposition of a 15% export duty on finished steel products in May 2022 is expected to increase domestic supply and exert downward pressure on steel prices; management expressed happiness with the news and said it keeps margins within the company’s expectation range.
- Normalization upside: If commodity costs normalize, EBITDA margin can reach 12–13%, per management.
- No further capex planned: Management guided no further capex until further orders, with an average annual capex of 3–4%.
Patel: "It was not a decline but every time I really say 11% and 12% this always go plus 1% so you can consider that we are little bit conservative and at the same time the projects which are not showing any price escalation in the future like UP project may get affected also so this is how we project our EBITDA margin for this year."
Balance Sheet & Subsidiary Clean-Up
- PP&E increase: The rise in property, plant and equipment was mainly due to the precast factory installation, reflecting the ₹110 Crores capex.
- US entity exit completed: Disinvestment was completed for ₹6.69 lakhs and the outstanding loan of ₹25 Crores was fully repaid; the investment was nullified and the ₹2.14 Crores provision from the prior year was reversed.
- Mobilization advances up: Mobilization advances increased by ₹105 Crores, mainly from the UP Medical College projects.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Order inflow growth | 20–25% growth over FY2022 inflows (more than ₹2,000 Crores) | FY2023 |
| Revenue growth | 20–25% plus growth | FY2023 |
| EBITDA margin | 11–12% (conservative; 12–13% if commodity costs normalize) | FY2023 |
| UP Medical College completion | All seven projects completed | By March 2023 |
| Surat Diamond Bourse final completion | Final completion certificate received | By end of June 2022 |
| Bhiwandi arbitration | Hearing and hoped-for conclusion on cost escalation | June 2022 |
| Capex | No further capex until further orders; 3–4% average annually | FY2023 |
Key Metrics
| Metric | Q4 FY22 |
|---|---|
| Revenue | ₹555 cr, +11% YoY |
| EBITDA | ₹88 cr, +42% YoY |
| EBITDA margin | 15.87%, vs 12.39% in Q4 FY21 |
| Net profit | ₹52 cr, +28% YoY |
| PAT margin | 9.36%, vs 8.1% in Q4 FY21 |
| Order book | ₹4,324 cr as of Mar 31, 2022, highest ever |
| FY22 order inflow | ₹1,802 cr, vs ₹2,441 cr in FY21 |
| FY23 order inflow guidance | 20% to 25% growth over FY22 inflow, implying more than ₹2,000 cr |
| FY23 revenue growth guidance | 20% to 25% plus |
| FY23 EBITDA margin guidance | 11% to 12%, conservative; management notes it usually goes plus 1% |
| Bid pipeline | ~₹4,500 cr, 52% private, 48% government; excludes Central Vista |
| Surat Diamond Bourse Q4 revenue | ₹146 cr; cumulative ₹1,803 cr out of revised order value of ₹1,850 cr |
| UP projects Q4 revenue | ₹85 cr; cumulative ₹149 cr till Mar 2022 |
| Precast facility Q4 revenue | ₹15 cr |
| Bhiwandi project provision | ₹9.64 cr total expense provisioned during FY22, ₹3 cr in Q4 |
| Working capital days | 28 days (annual basis); debtor days 65, creditor days 54, inventory days 70 |
| Employee cost quarterly run rate | ~₹25 cr going forward, includes annual increment and managerial remuneration increase |