Key Takeaways
- A difficult year, a resetting base: FY25 revenue of Rs. 2,468 crores missed guidance as project delays wiped out over Rs. 300 crores of planned top-line, while the closure of seven UP medical college projects concentrated Rs. 62 crores of additional costs, dragging EBITDA to Rs. 178 crores.
- The UP chapter is nearly closed: Only two medical colleges remain ongoing, and management expects minimal further cost leakage, removing the single largest drag on profitability as the company enters FY26.
- Adani integration is the FY26 story: With SEBI approval received and the open offer running, the definitive agreement is set to close shortly; management guides for 80-90% of FY26 order inflow to come from the Adani Group, targeting Rs. 4,000-5,000 crores of new orders.
- Margin guidance reset to 8-9%: Management lowered its band from 9-10%, citing labour availability, industry conditions, and a deliberate choice to be "a little bit safer" after two years of underperformance.
- What to watch next quarter: The pace at which Adani projects move from diaphragm wall and excavation into billable execution, the Q1 FY26 revenue run-rate that will firm up the "beyond Rs. 3,000 crores" guidance, and any residual UP cost surprises.
The UP Overhang: What Happened and What Remains
- Cost concentration at handover: Seven greenfield medical college and hospital projects entered their closure and handover phase in FY25, concentrating Rs. 62 crores of additional expenses that crushed reported margins. The adjusted EBITDA margin excluding these one-time costs was 9.7%, in line with the original profitability guidance.
- Q4 was the peak of the pain: Q4 FY25 EBITDA margin fell to 4.65% as Rs. 9 crores of additional UP expenses, Rs. 2 crores of asset write-offs, an Rs. 1.87 crore ECL provision for Badayu retention, and an Rs. 8.02 crore invoked bank guarantee all hit the P&L simultaneously.
- The Badayu project is fully closed: The client terminated PSP's scope and may retender the work; the Rs. 8 crore performance bank guarantee was invoked and expensed in Q4, and management does not expect further write-offs from this or any other project.
- Residual risk is small but real: Only two medical colleges remain ongoing, and the remaining work is renovation of existing hospitals rather than greenfield construction. Still, management acknowledged its own forecasting weakness on these costs.
P.S. Patel: "But every now and then I say -- last quarter also, I was saying about INR5 crores, but I ended up with INR9 crores."
The Adani Transaction: Structure, Pipeline, and Implications
- Deal timeline: SEBI approval for the open offer has been received; the tendering period runs from 22 May to 4 June 2025, after which the acquisition becomes effective.
- Order book concentration: Management guided that 80-90% of FY26 order inflow, targeted at Rs. 4,000-5,000 crores, will come from the Adani Group. An Rs. 10,000 crore pipeline of Adani opportunities is on track, with projects materializing into orders one by one.
- Early wins are already in hand: A Medicity and Research Center at Ahmedabad and a Leadership Guest House at Shantigram have been awarded, both with 18-month completion timelines. MIAL has initiated a small Rs. 50 crore building at T1, and two Dharavi relocation projects are under discussion.
- Execution independence is the stated deal logic: Management emphasized that the Adani Group will not interfere in execution for the next five years, handling only the financial side, because PSP was brought in specifically for its construction execution capability.
- Personnel cost of the transition: Two key managerial personnel, each with 15 years of tenure, left voluntarily, citing pressure from the Adani agreement, the size of the order book, and execution challenges including labour availability.
P.S. Patel: "The whole coalition has been done on the baseline that we will be the only person who understand execution and execution pace and how to manage a construction company. So the group doesn't want to enter into the execution part at all."
FY26 Guidance: Revenue, Margins, and the Shape of Recovery
- Revenue guidance is directional for now: Management expects to close FY26 with "beyond Rs. 3,000 crores" of revenue but will firm up the number by the end of Q1 FY26, once Adani projects move past the diaphragm wall and excavation stage and post-monsoon visibility improves.
- Order book conversion math: 30-40% of the existing order book is expected to convert in FY26; new orders won after Q1 will contribute only Rs. 400-500 crores of revenue within the year, so the FY26 top-line depends heavily on the opening backlog.
- Margin guidance lowered to 8-9%: The revision down from 9-10% reflects project-specific performance over the past year, labour availability constraints, and a broader construction industry crisis over the last 1.5-2 years. Management framed the cut as being "a little bit safer" rather than signaling new structural pressure.
- Historical context: Margins were 16% when materials were supplied free and there was no GST or service tax; they stabilized at 11-12% over the last three years before the UP projects dragged reported profitability to 4%. Adding back the Rs. 60 crores of UP costs to the Rs. 170 crores of EBITDA puts the underlying business in the 9% range.
- Capex stays contained: Guidance is 3-4% of revenue, possibly a little more than 4% but not exceeding 5%.
Balance Sheet: Receivables and Working Capital
- Receivables ballooned: Gross receivables crossed Rs. 500 crores, up from Rs. 335 crores last year, driven by government project dues, outstanding UP payments, and the addition of SDB receivables that were not in the prior-year base.
- Normalization target: Excluding SDB and other slow-moving items, management believes normal receivables at the current turnover level should be around Rs. 400 crores and expects to reach that number by March 2026.
- SDB receivable has a hard deadline: Rs. 90 crores is due by October 2025 per the agreement, and the company is actively following up.
- Inventory is stable: Inventory of Rs. 322 crores is broadly in line with last year's ~Rs. 300 crores; Rs. 21 crores of finished goods relates to precast products.
Order Book and Project Updates
- FY25 awards were diversified: Major wins included airport and city-side development with hotels, a Coca-Cola project at Sanand, a Medicity and Research Center at Ahmedabad, two commercial and one hotel building in Bangalore, the "Siban" residential project at GIFT City, a repeat order for Palladium Mall at Surat, and precast technology projects at Shantigram.
- Key ongoing projects are progressing: The Coca-Cola structure is nearly complete with infra and finishing underway; the Surat Municipal Corporation high-rise has reached the 14th storey with facade work starting; the Sports Complex main work is done with a Rs. 20 crore warmup pool addition ongoing.
- Gati Shakti Vishwavidyalaya has slipped: Basement work is complete across all buildings and superstructure merger works are in progress, but the project is running 1.5 to 2 months behind due to seasonal labour shortages in April and May.
- Dharavi mobilization has begun: Work has started at Mahim for 5,200 relocation houses on the outskirts, not on the Dharavi land itself; two additional projects are under discussion.
- No infrastructure pivot: Management explicitly ruled out entering bridge or road building, stating the company has no expertise in that segment and rejecting the premise that those segments offer better margins.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue | Close FY26 with "beyond Rs. 3,000 crores"; firm guidance after Q1 | FY26, with Q1 FY26 update |
| EBITDA margin | Stabilized at 8% to 9% | FY26 |
| Order inflow | Rs. 4,000 to 5,000 crores, 80-90% from Adani Group | FY26 |
| Capex | 3-4% of revenue, not more than 5% | FY26 |
| Receivables normalization | Ex-SDB and slow-moving items to ~Rs. 400 crores | By March 2026 |
| SDB receivable | Rs. 90 crores due per agreement | October 2025 |
| UP project costs | No further material spend expected; chapter "almost over" | From Q1 FY26 onward |
| Adani project pipeline | Rs. 10,000 crores of opportunities converting to orders | Over next 1.5 years, subject to execution capacity |
| Medicity and Guesthouse orders | 18-month completion | Within 18 months from award |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Revenue from operations | ₹655 cr, up 1% YoY from ₹649 cr |
| EBITDA | ₹30 cr, down 41% YoY from ₹52 cr |
| EBITDA margin | 4.65%, vs 7.98% in Q4 FY24 |
| Net profit | ₹4.8 cr, down 68% YoY from ₹15 cr |
| PAT margin | 0.7%, vs 2% in Q4 FY24 |
| Adjusted EBITDA margin (FY25, ex-UP one-time costs) | 9.7%, reflecting underlying operational strength |
| Revenue from operations (FY25) | ₹2,468 cr, flat YoY |
| EBITDA (FY25) | ₹178 cr, vs ₹260 cr in FY24 |
| Order book | ₹7,266 cr, up 20% YoY |
| Order inflow (FY25) | ₹3,506 cr (excluding GST), highest ever |
| Revenue guidance (FY26) | Beyond ₹3,000 cr, previously ₹4,000 cr; clearer view after Q1 |
| EBITDA margin guidance (FY26) | 8% to 9%, revised from 9% to 10% |
| Order inflow guidance (FY26) | ₹4,000 cr to ₹5,000 cr, 80% to 90% from Adani Group |
| Capex (Q4 FY25) | ₹16 cr; FY25 total ₹61 cr |
| Gross block | ₹599 cr; net block ₹307 cr as of March 31, 2025 |
| Long-term borrowings | ₹52 cr including short-term maturities of ₹34 cr |
| Short-term borrowings | ₹219 cr excluding short-term maturities of ₹36 cr |
| Net unbilled revenue | ₹522 cr |
| Retention receivables | ₹175 cr |
| Mobilisation advance | ₹335 cr |
| Inventories | ₹322 cr (construction materials ₹145 cr, WIP ₹156 cr, finished goods ₹21 cr) |
| Credit facilities utilisation | ₹1,001 cr utilised out of ₹1,497 cr sanctioned; ₹496 cr available |
| Total fixed deposits | ₹265 cr (lien-free ₹60 cr, under lien ₹180 cr, security deposit ₹25 cr) |
| Receivables | More than ₹500 cr, up from ₹335 cr last year; normalised level around ₹400 cr |
| UP projects additional expense (Q4 FY25) | ₹9 cr; FY25 total ₹62 cr |
| Badayu project PBG invoked | ₹8.02 cr expensed in Q4; incremental loss exposure ₹4 cr |
| Bid book | ₹7,100 cr, about 70% from Adani Group |
| Existing order book conversion expected in FY26 | 30% to 40% |
| Revenue expected from new orders in FY26 | ₹400 cr to ₹500 cr |