Key Takeaways
- Revenue doubled, H1 already beats FY25: Consolidated revenue grew 112% YoY and 13% sequentially, with the first six months of FY26 exceeding all of last year's revenue.
- Historic HVDC wins anchor the order book: The company won smoothing reactors for India's Rihand-Dadri LCC HVDC corridor and converter reactors for a VSC HVDC project in a G20 nation, alongside multiple global STATCOM and FACTS orders.
- Margins are healthy but deliberately capped: EBITDA margin came in at 22.5% as the company invests ahead of the curve in manpower, systems and infrastructure for a capacity expansion that will multiply current scale by over 9x.
- Supply chain is the binding constraint: BIS licensing has slowed HVDC magnet wire imports while Indian capacity is booked out for a year, and insulators and bushings remain tight globally; every existing factory is already running above 100% utilization.
- What to watch next quarter: Whether the Q3 revenue run-rate forces an upward revision to the INR 700–800 crore guidance, the pace of Mehru's margin march toward 15%, and any inorganic deal announcement in the next one to two quarters.
Revenue & Profitability
- Broad-based growth engine: Revenue growth was driven across FACTS, HVDC and high-voltage power segments, with EBITDA up over 200% YoY.
- Gross margin improved despite short-term material cost volatility from copper, aluminum, and imported raw materials that carry dollar costs, import duties, freight and BIS regulatory charges.
- Trade receivables swelled with scale: Receivables rose from INR 136 crores to INR 207 crores on incremental sales across all subsidiaries; larger utility and steel projects carry 10–15% retention money until commissioning, while internal discipline including at Mehru is enforced at 60 days.
- Hedging the commodity book: The company is increasing export shares so imports are naturally hedged by exports, and ensures the order book never stretches beyond 12 months so raw material hits are not prolonged.
- Consolidation optics depress margins: Consolidated margin guidance of 20% looks lower than the sum of parts because Quality Power and Endoks are guided at 25% margins, Mehru is improving each quarter, and Sukrut enters at very low margin, creating quarter-to-quarter volatility in the blended number.
Pandyan: "Our intention is always to keep it slightly conservative."
Order Book & Project Wins
- HVDC breakthrough: The company won high-voltage smoothing reactors from the Rihand-Dadri LCC HVDC project, described as one of India's most critical transmission corridors, and converter reactors for a VSC HVDC project in a G20 nation.
- FACTS orders stacking up globally: Multiple STATCOM and FACTS orders were secured, including a large grid stabilization project for a steel facility in Sweden.
- Order backlog visibility: Current order backlog is expected to be at least 95% completed by Q2 FY2027.
- Tailwinds have a long runway: Management stated that tailwinds at high voltage, especially for HVDC and FACTS, will persist for at least five years, if not more.
Mehru: The Margin & Capacity Story
- Margins climbing from a low base: Mehru delivered significant operational margin improvement to about 12%, driven by higher capacity utilization, product mix optimization and operational discipline; the internal target is to reach 15% before scaling further.
- Capacity, not demand, is the bottleneck: Mehru is currently constrained by capacity rather than order book; equipment has been ordered and is being installed monthly, with 45% more capacity from the same facility expected by March.
- GIS product line being carved out: Machines for the GIS project have been ordered within the existing Mehru facility, and a portion of the factory has been allocated for GIS despite near-term revenue pressures; the partnership with Hyosung brings gas-insulated instrument transformer technology to India.
- Long-term margin ambition: Management intends to bring Mehru to similar margin levels as the parent, around 25%+, in about three to four years.
- Instrument transformer consolidation underway: The high-voltage instrument transformer product line has been consolidated at Mehru, while the medium-voltage portion remains at Quality Power.
Pandyan: "These are R&D products, cannot we have like a D-day because it's a development story... We have guided the market by a year. We should be able to have a commercial product on the market."
Supply Chain: The Real Constraint
- HVDC magnet wire bottleneck: HVDC magnet wires now require a BIS license, which has slowed import approvals since Indian capacity is already booked out for the next year.
- Insulators and bushings tight globally: These critical inputs remain in short supply across the global supply chain.
- Capacity utilization at breaking point: All facilities are already at 100% and above; every corner of every factory is being used, with machines being installed wherever space allows.
- Near-term labor disruption: Immediate elections after Diwali and Chhath Pujas have meant suppliers have faced labor issues, which may impact the supply chain this quarter.
- Backward integration as the answer: The company is pursuing backward integration because of the scale at which it will operate next year with new facilities at more than 9x current capacity, aiming to reduce reliance on the outward supply chain.
- People being stockpiled: Over 140 to 150 people were added in the last quarter to ramp up and train them ahead of the shift to new facilities; these are small incremental costs expected to stabilize as revenue rises.
Pandyan: "HVDC magnet wires now require BIS license, which has slowed import approval since the Indian capacity is already booked out for the next year, while insulators and bushings remain tight in global supply."
New Capacity: The Coil Factory & Sukrut
- Coil factory on track for mid-2026: Public guidance points to operational status by the end of the second quarter of 2026 (June 2026); order intake will begin at the start of Q2 2026, with raw material lead times of two to three months.
- Revenue conversion timeline: Cycle time from order to revenue booking is about six to nine months, so revenue from the coil factory is expected by the end of the calendar year.
- No pre-committed customers yet: Currently there are no pre-committed customers for the coil factory; capacity allocation discussions will happen once the factory is ready.
- HVDC magnet wire capacity: The first stage of magnet wire capacity should be available by Q3 of next year.
- Sukrut's strategic role: The joint venture with Yash High Voltage, in which Quality Power holds about 50% ownership, brings over 1,000 customers in the transformer business; once internal demand for magnet wires is fulfilled in about two to three years, the Sukrut customer base will help push magnet wires into other categories.
Strategy & Competitive Landscape
- Inorganic growth imminent: Management is looking at exciting opportunities in the industry and sector, and expects some good news in the next one or two quarters.
- Growth markets prioritized: Europe, Australia, the Middle East and Southeast Asia are the expected growth markets, with India next; the US would become the number one market if tariffs and negativity rise.
- The China question: Chinese competitors remain the primary strategic concern because they operate on global domination logic rather than margin logic.
- Guidance discipline as a principle: Management explicitly stated it wants to start the relationship with the market on a foundation of conservative, stick-to-able guidance.
Pandyan: "Always it what keep us awake in the night is Chinese, because Chinese are not working on margins. They are working on global domination."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 consolidated revenue | INR 700–800 crores | FY26 (Q3 will determine whether guidance is revised upward) |
| FY26 consolidated EBITDA margin | About 20% | FY26 |
| Mehru operational margin | Reach 15% level | Before scaling to next level |
| Mehru long-term margin | Bring to 25%+ (parent-level margins) | About three to four years |
| Mehru capacity expansion | 45% more capacity from same facility | By March |
| Coil factory operational | Begin taking orders | Q2 2026 (June 2026) |
| Coil factory first revenue | Revenue booking from coil factory | End of calendar 2026 |
| HVDC magnet wire capacity | First stage of capacity available | Q3 of next year |
| Order backlog completion | At least 95% of current backlog completed | By Q2 FY2027 |
| Long-term guidance | Provide detailed long-term guidance | Q4 of this year, once orders, clearances and visibility are confirmed |
| Inorganic growth | Expect some good news | Next one to two quarters |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Consolidated revenue | ₹218.9 cr, +112% YoY and +13% QoQ |
| Consolidated EBITDA | ₹49.4 cr, +200% YoY; margin at 22.5% |
| PBT | ₹44.3 cr |
| PAT | ₹35.2 cr |
| H1 FY26 revenue | ₹413 cr, +126% YoY |
| H1 FY26 EBITDA | ₹97.7 cr, +67% YoY |
| H1 FY26 gross margin | 40% |
| Full-year revenue guidance | ₹700–800 cr |
| Full-year EBITDA margin guidance | ~20% |
| Order book | ~₹830 cr |
| Mehru order book | >₹375 cr |
| Mehru Q2 revenue | ₹78 cr |
| Mehru Q2 EBITDA margin | ~12%, up from 9.5% in Q1 and 8.2% in Q4 FY25 |
| Endoks Q2 revenue | ₹73 cr |
| Standalone parent H1 FY26 revenue | ₹92 cr |
| Group cash position | >₹200 cr, net debt near zero |
| Capacity utilization | 100% across all facilities |
| Headcount addition in Q2 | 140–150 people |