The Ramco Cements Ltd Q3 FY2024 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/sur0lvdo9oxa1ufbfvzrr3aw.pdf

Key Takeaways


Volume & Demand

Management: "Prices have corrected very sharply... we are confident that prices will come back."

Pricing & Costs


Capacity Expansion & Projects

M F Farooqui: "Normally the companies will add all these capacities over a period of time and not the day number one... even though for first phase we spend over 3,000 Crores, for the same capacity second phase is going to be only 1,250 Crores because already all the infrastructures we have created."

Capex & Funding


Balance Sheet & Leverage

Management: "Last 50 years not even single day there was a delay in repayment of loan."

Guidance & Commitments

CommitmentSpecificsTimeline
Q4 FY24 volumeAround 0.5 crore tonsQ4 FY24
Full-year FY24 volume1.75 crore tonsFY24
FY25 volume1.9 to 2 crore tonsFY25
Net debt ceilingNot to exceed Rs.5,000 CroresOngoing
Kolimigundla expansionDouble clinker to 6.30 MTPA, cement to 3 MTPA at Rs.1,250 CrFY2026
Kurnool Line-2Completion at ₹750 Cr (included in FY25 capex)End of FY2026
RR Nagar WHRS10 MW commissioned at Rs.153 CrBy March 2025
FY2025 capexRs.1,700 Crores, funded predominantly through internal accrualsFY2025
Bommanahalli plant announcementAfter Board approval, following land acquisitionMinimum 12–18 months

Key Metrics

MetricQ3 FY24
Net revenueGrew by 5% YoY
EBITDA₹402 cr, up from ₹294 cr in the corresponding period
EBITDA margin19%, up from 15% in the corresponding period
Blended EBITDA per ton₹1,007, up 25% from ₹808 in the corresponding period
Cement sales volume growth10% YoY for Q3; 25% for 9M FY24
Cement utilization rate74%, up from 70% in the corresponding period
Share of premium products27%, up from 26% in the corresponding period
Kilocalorie costDeclined to 1.64
Pet coke consumption51% of fuel mix
Spot CIF price of pet coke\$118 to \$120
Net debt₹4,993 cr as of December 31, 2023, including working capital borrowings
Net debt to EBITDA3.22 times
Average cost of debt7.82% for 9M FY24, up from 6.16% in 9M FY23
Capex incurred during Q3₹385 cr
FY2024 capex guidance₹2,000 cr, revised up from ₹1,600 cr and originally ₹900 cr
FY2025 capex guidance₹1,700 cr, to be funded predominantly through internal accruals
FY2024 full-year volume guidance1.75 crore tons, implying ~0.5 crore tons in Q4
FY2025 volume guidance1.9 to 2 crore tons
Installed clinker capacity16 MTPA, after 0.65 MTPA addition at Kolimigundla and 0.35 MTPA at Ariyalur
Installed cement capacity2.2 crore tons (22 MTPA)
Planned aggregate clinker capacity by FY202619 MTPA
Planned aggregate cement capacity by FY202626 MTPA
Planned aggregate WHRS capacity by FY202553 MW, up from 43 MW
Planned aggregate WHRS capacity by FY202668 MW
Expected free cash flow in FY25~₹1,700 cr
Non-core asset monetization potential₹500-600 cr, if right value received
Volume lost in Q3 due to cyclone, rains, and holidays~3 lac tons
Price drop across markets₹5 to ₹10 per bag