Ravindra Energy Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- Total capex of ₹3,500-4,000 Cr over 3 years (by FY 2029-30)
Pending - At the Q1 FY27 PPT, management guided total capex of ₹3,500-4,000 Cr over 3 years (by FY 2029-30), with equity of ₹800-1,000 Cr over 3 years. No deployment read yet; CWIP declined from ₹129 cr in FY25 to ₹21.88 cr in FY26 to ₹4.87 cr in the latest period.
- FY 2029-30 deployment - 160 swap stations, 6,000 trucks, 7,280 battery packs, 400 MWp solar
Pending - In the Q1 FY27 PPT, management guided by FY 2029-30 deployment of 160 swap stations, 6,000 trucks, 7,280 battery packs and 400 MWp solar. As of Q2 FY27, 8 swap stations were operational and 452 e-tractors had been invoiced by September 2026; the horizon is not reached.
- Under-development/pipeline solar CoD FY27E - MSKVY-3 (156.00 MWp) and Karnataka-2 (71.30 MWp)
On track - In the Q3 FY26 PPT, management guided CoD FY27E for MSKVY-3 (156.00 MWp, March 2027) and Karnataka-2 (71.30 MWp, January 2027); Q1 FY27 revised MSKVY-3 COD to September 2027. By Q1 FY27, both had PPAs signed, with land acquired for 10 of 23 and 11 of 13 projects respectively; no commissioning read yet.
- 8 upcoming charging/swapping stations in FY26E - vs 2 operating
Partial - In the Q3 FY26 PPT, EIM guided 8 upcoming charging/swapping stations in FY26E versus 2 operating, with LOIs issued for land on 5 and for all 8 to the vendor. By July 2026, six heavy-duty swap stations were commissioned in Delhi-NCR and JNPA; 8 stations were operational by Q2 FY27 - roughly a quarter late.
- Rights issue ₹200.53 crore - objects completion by Fiscal 2027
On track - In June 2026, a rights issue of up to 19,854,940 shares at ₹101 per share aggregating ₹200.53 crore was launched, with the ₹150 crore EIM investment targeted Fiscal 2027 and GCP of ₹48.93 crore targeted Fiscal 2027. By the August 2026 Monitoring Agency Report, the EIM investment was completed with no delay; GCP and expenses were on-going with Nil GCP utilization.
- CATL battery supply - 0.5 GWh of LFP cells and pack kits
On track - In August 2026, CATL agreed to supply 0.5 GWh (500 MWh) of advanced LFP battery cells and pack kits for EIM's Ashwa 4×2 e-tractors, to be assembled at the Talegaon plant. At the Q2 FY27 call, management confirmed the tie-up, stating kits come from China later this quarter with start hoped in January.
- NSFT fleet electrification - entire vehicle fleet by end of FY 2026-27
On track - In May 2026, EIM was working with NSFT to electrify their entire vehicle fleet by end of FY 2026-27. Commercial operations began at the largest heavy-vehicle battery swapping/charging station within JNPA, serving upwards of 160 vehicles per day with 3 MW capacity, and 130+ EIM-Foton EVs at Nhava Sheva have begun availing the service.
- EIM MoU for 500 electric heavy commercial vehicles across key corridors
Pending - In September 2026, EIM signed an MoU with Oil Field Warehouse & Services Ltd and Radiance Green Mobility for deployment of 500 electric heavy commercial vehicles, with 50 vehicles on Mumbai-Pune from October 2026. No disclosure yet on that deployment; EIM has MOUs with transporters totaling almost 1,500 vehicles, to be delivered in phases as the network is commissioned.
- Electricity generation/sales of ₹140-150 crores for FY27
On track - At the Q2 FY27 call, management guided electricity generation/sales of close to about INR 140-150 crores for the full year, against INR 89 crores last year. Q2 FY27 generation revenue was INR 31 crores, with H1 FY27 generation of 145 million units; no full-year read yet.
- EPC revenue of \~₹600 crores for FY27
On track - At the Q2 FY27 call, management guided \~200 MW of EPC capacity addition for the full year, implying EPC revenue of close to about INR 600 crores, of which INR 200 crores booked in H1. H1 FY27 total revenue was INR 310 crores and Q2 EPC/service concession equipment revenue was INR 133 crores; no full-year read yet.
- Heavy-duty tipper and one other product - launch within 12 months
Pending - At the Q2 FY27 call, management stated they expect to launch two other products in the next 12 months, the first being a heavy-duty tipper. The Q1 FY27 PPT lists upcoming products: Heavy e-Tipper with swappable battery and Rigid e-truck with fixed battery pack; no launch has been disclosed as of the record date.
- Merger of EIM with Ravindra Energy - completion by Q2-Q3 FY28
On track - At the Q2 FY27 call, management announced the merger of EIM with Ravindra Energy, expecting all legal formalities by Q2-Q3 FY28, with SEBI process of 3-4 months and September 2027 as the likely completion timeline. The scheme was filed with the stock exchange in September 2026 and is in 21-day public review, being moved toward SEBI; REL is to be renamed Energy In Motion Limited.
- EIM to turn positive (profitable) - FY28
Pending - At the Q2 FY27 call, management set a company target for EIM to turn positive (profitable) in the next financial year, FY28. EIM losses have narrowed as volumes picked up, with Q2 FY27 losses narrower than Q1 and narrowing expected over the next two quarters; EIM reported turnover of 180.69 crore in FY2025-26. No profitability read yet.
- EIM swapping stations - 15 by December 2026, 40 by March 2027
On track - At the Q2 FY27 call, management guided EIM from 8 swapping stations to 15 by December 2026 and 40 by March 2027, building on the earlier 40-stations-by-March-2027 target. As of Q2 FY27, 8 stations were operational, with 6 commissioned in Delhi-NCR and JNPA by July 2026 and 2 of the 8 working at more than 75% capacity daily.
- 500 MW operating renewable portfolio - by March 2027
On track - At the Q2 FY27 call, management stated they are on track to reach a 500 MW operating renewable portfolio by March 2027. Currently \~300 MW operates with 226 MW under construction; Q4 FY27 operating capacity is guided at about 400 MW. The Q1 FY27 PPT shows 261.21 MWp operating and 231.10 MWp under construction/development, totaling 492.31 MWp.
- Battery pack assembly facility at Pune complex - commissioned next quarter (Q3 FY27)
Pending - At the Q2 FY27 call, management stated the battery pack assembly facility at the Pune complex was to be commissioned next quarter. The Q1 FY27 PPT shows the Talegaon plant at 2.40 GWh/year capacity; commissioning is hoped by the analyst/investor day, with CATL kits from China later this quarter and start hoped in January. No commissioning disclosed yet.
- Talegaon e-tractor facility - 5,000 units p.a., commissioned within H1 FY27
On track - In the Letter of Offer, management guided the Talegaon facility with annual capacity of over 5,000 e-tractor units to be commissioned within the first half of Fiscal 2027. At the Q2 FY27 call, the plant was ready with trial production of a few CKD kits underway and full-scale production from January at about 200 vehicles per month guided.
- Remaining \~80 MW of 135 MW Rural Agri Feeder PPA - commissioned by September 2025
Partial - In May 2025, management stated the remaining \~80 MW of the 135 MW Rural Agri Feeder PPA project was on schedule for commissioning by September 2025, with 55 MW already commissioned. The Q3 FY26 PPT shows MSKVY-1 (19 projects, 135.80 MWp) fully in the operating portfolio with COD October 2025 - commissioning was completed about one month after the stated target.
- Sale of Wardha solar park (110 MW) and Karnataka park (65 MW) - by September 2025
Missed - In May 2025, management stated the sale of the Wardha solar park (110 MW) and Karnataka park (65 MW) was expected by September 2025. No completion of these sales is disclosed by September 2025 or thereafter; the Q3 FY26 PPT still lists Karnataka (14 projects, 34.15 MWp) as an operating asset, and the assets remain in the operating portfolio.
- 44 MW MSEDCL KUSUM C Letter to Award - scheduled commissioning July 2026
Delivered - In February 2025, management guided a 44 MW Letter to Award received from MSEDCL under the KUSUM C Scheme with scheduled commissioning in July 2026. By Q1 FY27, MSKVY-2 stood at 58.71 MWp with COD June 2026, having been shown with SCOD March 2026 at Q3 FY26 - the 44 MW was commissioned ahead of the July 2026 schedule.
- 10 MW C&I PPA - targeted commissioning July 2025
Partial - In February 2025, management guided a 10 MW PPA signed with various C&I customers with targeted commissioning in July 2025. The Q3 FY26 PPT shows Open Access projects (3 projects, 11.04 MWp) with COD October 2025; by Q1 FY27, Open Access stood at 26.19 MWp - commissioning occurred about one quarter after target.
- 40 MWp of 130 MWp MSEDCL KUSUM C project - commissioned by March 2025
Partial - In February 2025, management guided that 40 MWp of the 130 MWp MSEDCL KUSUM C project was expected to be commissioned by March 2025. The March 2025 commissioning of 40 MWp is not separately disclosed in our record; the Q3 FY26 PPT shows MSKVY-1 (19 projects, 135.80 MWp) with COD October 2025 - the full project landed about two quarters late.
- 50 MW electricity trading portfolio - within 12 months of Sept 2023 AGM
Delivered - At the September 2023 AGM, management set a target to build an electricity trading portfolio of about 50 MW within the next 12 months. No specific read exists at the 12-month mark, but trading started in June 2023 and by Q2 FY27 Ravindra Energy was doing close to about 120 MW of electricity trading every month, well beyond 50 MW.