Key Takeaways
- A quarter of one-time hits, not structural damage: Revenue fell 10.6% QoQ and the company posted a net loss of Rs. 9.5 crores, but Rs. 25.26 crores of the damage came from identifiable, non-operational items: forex loss on equipment imports, a tariff settlement, and start-up losses in Mexico and the JV.
- Management is calling the bottom with unusual force: The phrase "worst is behind us" was used explicitly, and Q3 is described as "significantly better" with H2 results promised to be "extremely surprising and extremely on the upside."
- The order book provides a visible ramp to FY'28: An aggregate order book of Rs. 6,000-7,000 crores, plus new wins of Rs. 1,116 crores this quarter, supports a safe annual revenue estimate of ~Rs. 1,000 crores plus from these orders alone by FY'28.
- Tariff disruption is being offset by new customer wins: U.S. demand dropped when tariffs moved from 25% to 50% and customers refused to absorb the pass-through, but management expects new North American customer wins to pull back the dollars lost from existing accounts.
- What to watch next quarter: Whether the promised H2 surge materializes in reported numbers, the pace of debt reduction toward the Rs. 500-600 crore target by March '26, and any further forex hits from JV equipment still not put to use.
The Quarter's Damage: One-Time vs. Real
- Net loss of Rs. 9.5 crores was driven by a cumulative Rs. 25.26 crores in identifiable hits: forex loss on equipment imports (Rs. 6.77 cr), a tariff settlement impact (Rs. 10.75 cr), Mexico operations loss (Rs. 3 cr), and JV forex loss on imported equipment (Rs. 4.84 cr).
- EBITDA margin compressed 110 bps QoQ to 13.5%, with the Rs. 25 crores in notional and one-time hits plus lower exports doing the damage. Management stated explicitly there is no pricing pressure.
- Debt rose ~Rs. 600 crores in H1 from a triple hit: muted profit generating no cash accrual, Rs. 400 crores in capex, and a Rs. 200 crores reduction in creditors. Recovery is expected in H2 via promoter infusion (Rs. 150 cr), an income tax refund (Rs. 150 cr), and improved operating leverage.
- Further forex risk is not closed: JV equipment is still not put to use, so additional notional forex hits remain possible until March '26, and management reminded that currency is not in their control.
Naresh Jalan: "I can only tell you we are back to normal, and I think third and fourth quarter is going to be extremely surprising and extremely on the upside of the results."
Tariffs, Exports & the Demand Reset
- U.S. tariff confusion froze demand: The reciprocal tariff took the automotive rate from 25% to 50%, and clarity only arrived in mid-September when the U.S. government confirmed automotive tariffs would stay at 25%. Through that uncertain period, customers were not prepared to pass on anything beyond 25%, and overall U.S. demand dropped drastically beyond customer projections.
- Mexico felt the demand shock directly: The company chose not to continue shipping and parking material in warehouses to protect cash flows when U.S. demand collapsed.
- The offset strategy is new customer wins: Management's thesis is that new order wins and new customer additions in North America will pull back the dollars being lost from existing customers due to demand disruption. Shipping has already started this quarter for several new order books.
- Europe orders phase in from next year: Rs. 927 crores in European orders were won in H1, but the entire order book only gets into full production from FY'28 onwards.
Naresh Jalan: "Tariff has disrupted demand also in North America. But at RKFL, because of our new order wins and new customer wins over there, we will be able to mitigate the demand disruption in our existing customer with the addition of new customers, wherein we will be able to pull back all those dollars, which we are losing in our current customers because of the demand issue from the new customers."
Order Book & Capacity: The FY'28 Bridge
- Rs. 1,116 crores in new orders were won this quarter with a 4-year life, excluding railways. The split: 69% automotive, 27% railway, 4% non-auto. Excluding railways, all order wins came from international geographies.
- The aggregate order book stands at Rs. 6,000-7,000 crores, from which management estimates a safe annual revenue number of ~Rs. 1,000 crores plus by FY'28.
- Most capex is now complete: Capacity was in place by 30th September, and FY'27 capex is expected to be negligible at less than Rs. 100 crores. The peak revenue from current capacity is estimated at Rs. 6,200-6,500 crores by end of calendar year 2027, depending on commodity pricing.
- Cold forging is ramping: Already generating revenue at 40% utilization, with bugs being settled. Expected to reach 60%+ next quarter and peak at 80-85% in FY'27.
- Aluminium forging is starting now: Samples and PPAP have been accepted, and revenue generation begins this month.
- The casting facility is nearly sold out: The entire 45,000 tonnes of capacity is installed and will be up by the end of this quarter, with 80-85% utilization expected next year across a mix of railways, domestic, and exports.
Railways: The Growth Engine Firing Now
- Bogey frame dispatches have commenced: Fully finished assembled bogey frames for Indian Railways are now shipping in bulk, with all required approvals in place.
- Railway castings are a new vertical that made a promising start this quarter and is positioned to scale up meaningfully. Products are being integrated into bogey assemblies.
- The railway wheels JV is on the near-term horizon: Trial runs start in January, with commercial production expected from March '26. The FY'27 target is 40,000 wheels at ~30% utilization, scaling to 80-85% utilization in FY'28 for revenue of Rs. 1,600-1,700 crores and EBITDA margins of 17-18%.
- Defence is deferred, not abandoned: Management will focus on defence only after the railways growth story is done, calling it a likelihood going forward but confirming nothing big is being worked on immediately.
Naresh Jalan: "Defence is also a likelihood going forward, but we are not immediately working anything big on defence to make investors aware. I think at the right opportune time post we are done with railways in terms of our growth, we would like to focus on defence." [15-16]
Margins: The Path Back to Normal
- Standalone margin ambition: Management is optimistic about returning to 20% margins by Q4 or possibly Q1 FY'27. On a blended basis including castings and forgings, the target is 17-18%. [14-15]
- The domestic market has bounced back sharply post-GST cut, and Q2 numbers already show domestic growth, which supports the margin recovery thesis by improving mix and operating leverage.
- Management declined to give a specific EBITDA margin number for Q3 or Q4 when asked directly, offering only the qualitative framing of "back to normal" and results that will be "extremely on the upside."
- Utilization is the margin lever: With capacity now in place and capex largely done, the path to margin recovery runs through utilization moving from current levels to ~85% by FY'27, which pulls operating leverage through the P&L.
Balance Sheet & Promoter Actions
- Debt reduction of Rs. 500-600 crores is targeted by March '26, driven by the promoter warrant infusion, an income tax refund, and improved operating leverage from higher sales and profitability in H2.
- Warrant allotment is underway: The board approved 9,75,000 warrants to a promoter entity in August '25, with 25% (Rs. 51.19 crores) paid upfront and the balance due before March '26.
- Promoter share pledge is to Tata Capital only: Management explicitly denied any pledge to Jio Finance, stating the pledge to Tata Capital was solely to fund the warrant subscription.
- No funding challenges exist: The company has Rs. 700-800 crores in lines available and has faced no institutional issues or working capital concerns from bankers.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Full-year revenue growth | Double-digit growth for FY26 | Full year FY26 |
| Q3 vs Q2 performance | Q3 "significantly better" than Q2 | Q3 FY26 |
| Debt reduction | Rs. 500-600 crores reduction | By March '26 |
| Railway wheels JV commercial production | Commercial production begins | March '26 onwards |
| Cold forging utilization | 60%+ utilization | Next quarter (Q3 FY26) |
| Cold forging peak utilization | 80-85% utilization | FY'27 |
| Casting facility utilization | 80-85% utilization | Next year (FY'27) |
| Standalone EBITDA margin | Return to 20% margins | Q4 FY26 or Q1 FY'27 [14-15] |
| Blended EBITDA margin (castings + forgings) | 17-18% margin | Not dated; stated as target |
| Peak revenue from current capacity | Rs. 6,200-6,500 crores | End of calendar year 2027 |
| Railway wheels JV revenue and margin | Rs. 1,600-1,700 cr revenue, 17-18% EBITDA margin at 80-85% utilization | FY'28 |
| FY'27 capex | Negligible, less than Rs. 100 crores | FY'27 |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Consolidated revenue | ₹907.53 cr, lower by 10.6% QoQ vs ₹1,015 cr in Q1 FY26 |
| EBITDA (excl. other income) | ₹122.54 cr, lower by 17.5% QoQ vs ₹148.61 cr in Q1 FY26 |
| EBITDA margin | 13.5%, lower by 110 bps QoQ |
| Profit after tax (consolidated) | Loss of ₹9.5 cr, impacted by one-off items totaling ~₹25.26 cr |
| One-off impact on profitability | ₹25.26 cr cumulative, comprising forex loss on equipment imports (₹6.77 cr), tariff settlement impact (₹10.75 cr), Mexico operations loss (₹3 cr), and JV forex loss (₹4.84 cr) |
| New orders secured | ₹1,116 cr with program life of 4 years, excluding railway segment |
| Automotive order wins | ₹777 cr, 69% of total new orders |
| Railway order wins | ₹296 cr, 27% of total new orders; includes fully finished assembled bogey frames |
| Non-auto order wins | ₹43 cr, 4% of total new orders |
| Gross debt | Close to ₹2,400 cr as of Sep '25, increased ~₹600 cr in H1; ₹500-600 cr reduction expected by Mar '26 |
| Consolidated capex (H1 FY26) | ~₹485 cr; H2 FY26 capex expected below ₹100 cr |
| Capacity utilization | 60%, down from 69% in Q1 FY26 |
| Cold forging utilization | 40% currently; expected to reach 60%+ next quarter and 80-85% in FY27 |
| Railway wheels JV target (FY27) | 40,000 wheels, ~30% utilization; commercial production expected from Mar '26 |
| Peak revenue potential (current capacity) | ₹6,200-6,500 cr, achievable by end of CY27 with right product mix |