Rajputana Stainless Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- Listing on NSE and BSE within three working days of allotment
Delivered - The DRHP (Mar 2026) stated the company would apply for final listing and trading approvals within three working days of the Bid/Offer Closing Date. The IPO ran 9-16 March 2026, raising ₹178.73 crore, and the company listed on BSE/NSE with effect from 19 March 2026.
- Creditor holding period around 45 days for FY25, FY26 and FY27
Delivered - The DRHP (Mar 2026) anticipated a creditor holding period of around 45 days for Fiscal 2025, 2026 and 2027, against actuals of 50 days in FY24. FY26 payables stood at 47 days, though management flagged on the Q2 FY27 call that payables were probably lower than 10 days.
- Debtor holding period around 40 days for FY25 and FY26, 46 days for FY27
Missed - The DRHP (Mar 2026) anticipated a debtor holding period of around 40 days for Fiscal 2025 and 2026, rising to 46 days for Fiscal 2027 on the new facility's operations, versus 35 days in FY24. FY26 debtors came in at 50 days, and receivables ran about 52 days on the Q2 FY27 call.
- IPO proceeds - ₹44.64 cr for General Corporate Purposes
Delivered - The DRHP (Mar 2026) proposed deploying ₹44.64 crore towards General Corporate Purpose, 24.98% of Net Proceeds, within a 25% of Gross Proceeds cap. ₹44.21 crore was utilised in Q4FY26 and ₹0.26 crore in Q1FY27, with no GCP utilisation in Q2FY27.
- IPO proceeds - ₹98 cr for debt repayment by FY26
Delivered - The DRHP (Mar 2026) committed ₹76.5 cr for repayment/prepayment of borrowings in Fiscal 2026, with the offer document allocating ₹98.00 crore for full or part repayment. Repayment of ₹96.01 crore completed on 04/04/2026, the first week of April on lender procedures, leaving ₹1.99 crore unutilised; debt-free status was achieved on 8 April 2026.
- IPO proceeds - ₹18.57 cr for seamless pipe capex, ₹5.57 cr in FY26
Partial - The DRHP (Mar 2026) committed ₹18.31 cr for Proposed Facility capex in Fiscal 2026, with the offer document stating ₹5.57 crore utilised in FY26 and the balance ₹13.00 crore in FY27. Monitoring agency reports confirm zero utilisation through Q1 and Q2 FY27, with ₹18.57 crore unutilized as of 30 Sep 2026; contractor work is expected from next quarter.
- Power cost optimization - annual electricity savings of \~₹12 Cr
On track - The Q2 FY27 PPT (Nov 2026) stated the finalized 2.1 MW windmill and 8 MW (DC) solar project is expected to deliver annual electricity cost savings of \~INR 12 Cr. Solar is committed from 1 January 2027 and the windmill targeting end of March 2027, so no savings have been realized as of 4 Nov 2026.
- Amalgamation of Citizen Solar Private Limited - lowering power costs
Pending - The Q2 FY27 PPT (Nov 2026) states the amalgamation of Citizen Solar Private Limited is aimed at lowering power costs and strengthening renewable energy capabilities. No amalgamation completion has been disclosed as of 4 Nov 2026; renewable investments in solar and wind are made.
- Debt-free shift - annual interest cost savings of ₹12-13 Cr
Delivered - The Q2 FY27 PPT (Nov 2026) stated the debt-free shift is expected to deliver annual interest cost savings of INR 12-13 Cr. The company went debt-free on 8 April 2026 by repaying ₹96.01 Cr; borrowings fell to ₹11.4 Cr by 30 Sep 2026 and H1 FY27 finance cost dropped 69% YoY to ₹3.2 Cr.
- Value-added share of revenue - 58% by FY29
On track - The Q2 FY27 PPT (Nov 2026) guides value-added share of revenue to 58% by FY29, from 33% in FY26. The recorded trend has risen steadily - 7% in FY23, 17% in FY24, 24% in FY25 and 33% in FY26 - with no FY27 figure yet.
- Exports - 9 to 25 countries, 10.2% of revenue by FY30
Pending - The Q2 FY27 PPT (Nov 2026) targets exports growing from 9 to 25 countries and 10.2% of total revenue from international markets by FY30, with management citing direct exports via seamless pipes by removing the mediator. The company is currently present in 9 countries, with no export revenue share disclosed for FY27.
- Market expansion - 14 to 20 states and 2-4 UTs by FY28
Pending - The Q2 FY27 PPT (Nov 2026) targets expansion from 14 to 20 states and 2-4 UTs by FY28. No state or UT count has been disclosed as of 4 Nov 2026; the company profile cites 370 customers and presence in 9 countries.
- Long-term capacity target - 2 lakh tons by 2031
On track - At the Q2 FY27 call (Sep 2026), management reiterated a long-term target of 2 lakh tons of stainless steel specialty product by 2031, confirmed at 2,00,000 MTPA in the PPT Chairman's message. Current capacity is 48,000 MTPA, expanding to 60,000 MTPA in FY27, to be established in the most profitable areas first.
- Free cash flow positive for FY27
On track - At the Q2 FY27 call (Sep 2026), management confirmed "Yes. The free cash flow will be positive" for the whole year. H1 FY27 operating cash flow was \~INR 4.5 crores against PAT of INR 43.9 crores, the gap attributed to receivables investment from the end-user shift, with trade receivables up from 137 to 232.
- 80% power cost coverage via captive solar + wind by 2027
Pending - At the Q2 FY27 call (Sep 2026), management stated 80% of the company's power cost will be covered by captive solar and wind, directly improving profitability. As of 4 Nov 2026 this is unreached: solar savings begin 1 Jan 2027 and windmills end-March 2027, with the PPT confirming finalized renewable capacity.
- Windmill - production from end of March 2027
On track - At the Q2 FY27 call (Sep 2026), management committed to targeting end of March (presumably March 2027) to kickstart windmill production. The 2.1 MW windmill project is finalized as part of the renewable investment, with no production start reported as of 4 Nov 2026.
- Solar plants - operational from 1 January 2027
On track - At the Q2 FY27 call (Sep 2026), management committed the solar plants will come into action from the 1st of January 2027, bringing power/production costs down dramatically, with facility commencement by end of 2026. The 2.1 MW windmill and 8 MW (DC) solar project is finalized with \~INR 12 Cr expected annual savings; renewable capacity is cited as 7.5 MW (solar 3 MW, windmill 4.2 MW) on one PPT page and 7.2 MW on another.
- No new fund raising for capacity expansion and seamless pipe entry
On track - At the Q2 FY27 call (Sep 2026), management stated the seamless pipe vertical needs about INR 20 crores, funded through IPO proceeds, and capacity expansion capex through internal accruals - "we will not be raising funds". As of 30 Sep 2026, ₹18.57 crores of IPO proceeds remain unutilized and borrowings are down to ₹11.4 Cr, with no new fund raising disclosed.
- Seamless pipe plant - commercial operations from 1 April 2027, ₹18.57 cr IPO proceeds
On track - The DRHP (Mar 2026) expected the Proposed Facility to commence commercial operations in Fiscal 2027; the Q2 FY27 PPT (Nov 2026) specifies 1 April 2027, with management acknowledging "a little more time than expected". The ₹18.57 crores earmarked remains unutilized as of 30 Sep 2026, but quotations, layout and designs are obtained, and the ₹57.47 Cr project is funded via ₹39.16 Cr internal accruals and ₹18.31 Cr IPO proceeds.
- Melting capacity expansion - 48,000 to 60,000 MTPA, commissioning Q4 FY27
On track - At the Q2 FY27 call (Sep 2026), management guided melting capacity to increase from 48,000 tons to 60,000 tons (25% increase), with commissioning expected in Q4 FY2026-27; the PPT confirms capacity already installed, pending commissioning. Capacity is installed as of the Q2 FY27 PPT, commissioning not yet reported as of 4 Nov 2026, with the existing 48,000 tons at full 100% utilization.