Key Takeaways
- Brutal margin compression, cost-led: EBITDA/ton collapsed ~1,600 bps YoY as pet coke and coal prices stayed stubbornly high; management expects costs to stay flat in Q2, with real relief only from mid-Q3 onward.
- Volume growth masks pain: Revenue rose 42% YoY on new capacity, but realizations were stable at best and did not cover input inflation, leaving the quarter's headline growth optically strong but operationally weak.
- New plants are a drag, not yet a contributor: Jeerabad hit full utilization only in late June and Jajpur is sub-10%; both are expected to turn contributory only as the year progresses, with Jeerabad targeting EBITDA breakeven around Q4.
- Acquisition ambition is live but opaque: The Board approved a bid for Andhra Cement under NCLT, but management declined to share valuation, timeline, or post-acquisition CapEx, calling it "too soon" and "very strategic."
- What to watch next quarter: Whether Q2 costs actually stay flat as guided, the pace of Jeerabad and Jajpur ramp-up post-monsoon, and any concrete detail on the Andhra Cement resolution plan.
Cost Structure & Margin Pressure
- Power & fuel, the core wound: Cost per ton surged to ₹1,827 from ₹1,017 YoY, driven by pet coke prices that spiked from ₹7,000-8,000 to ₹22,000 and stayed there through most of Q1.
- Pet coke exposure is concentrated: The Madhya Pradesh plant runs 100% on pet coke, with limited use at Gudipadu and Mattampally also adding pressure; the company uses no imported coal at all.
- Freight cost rose despite shorter hauls: Lead distance fell from 283 km to 268 km, yet freight cost per ton increased ~3% because transport contractors were compensated for inflationary pressures beyond diesel, including manpower and tollage.
- The relief timeline is back-ended: Pet coke prices dropped 10% only in the middle to end of June; because of high-cost inventory already on hand, the real benefit flows from mid-to-end Q3, with full benefit only from Q4.
- Inventory strategy shifted shorter: Fuel inventory holding has been cut from six months to close to four months or 3.5 months to avoid locking in high prices that could fall further; management wants to return to six months once pricing stabilizes.
Sreekanth Reddy: "At least for one quarter we can keep our neck out sir. Beyond that, again, is a challenge. But for the next quarter, we believe it is going to be flat for us."
New Capacity Ramp-Up
- Jeerabad, late but accelerating: The plant touched 100% capacity utilization only in the second fortnight of June, and its waste heat recovery system was commissioned in the last week of June; post-monsoon ramp-up is expected much faster than initially indicated.
- Jajpur, waiting on approvals: Utilization is sub-10% while the plant awaits product approvals for composite cement; adhoc BIS permission has been received, and post-season utilization is targeted at 35-40%.
- Consolidated margin drag: Standalone EBITDA/ton was 650+ while consolidated was lower, because Jeerabad and Jajpur did not ramp up in time; both are expected to stabilize and start contributing rather than being a drag in the current year.
- Jeerabad breakeven math: At 50% capacity utilization, the plant should be EBITDA positive; management expects to be close to 40% utilization in Q4 if conditions hold, implying breakeven is within reach by year-end.
Demand & Pricing Environment
- Demand is stable but lackluster: Volumes held steady, but demand is described as "on-and-off," creating pricing pressure whenever orders are absent for a couple of days; the monsoon arrived 15-20 days early, softening July demand further.
- Realizations are stuck: Average realizations remained stable and did not move downward, but they failed to cover inflationary input prices; management internally believes prices must rise for sustainable survival, given input costs are still ~3x year-ago levels.
- Pockets of realization strength: Orissa saw realization improvement; Maharashtra gained 6% partly from product mix and distance changes; Andhra Pradesh government supply prices increased by ₹15 per bag.
- South region structurally oversupplied: Management acknowledges supply probably exceeds demand in the South for the next 10 years, but argues nameplate capacities overstate real clinker capability; the real gap may not exceed 10-15%, and over a 5-10 year horizon should narrow to low single digits.
- Election cycle as a demand catalyst: Past experience shows demand shoots up 1-1.5 to 2 years before elections; most players are gearing up for that, with elections roughly 24-28 months away.
Sreekanth Reddy: "We internally believe that the realizations should go up for us to sustainably survive in this particular market. That's what we internally think. And we strongly believe that it has to move up to catch up with the inflationary kind of the thing."
Andhra Cement Acquisition
- The bid is live: The Board approved participation in the resolution plan for Andhra Cement, which is under NCLT; the resolution plan must be submitted before 18th August 2022, with clearances expected around end-September to early-October 2022.
- Post-acquisition timeline: The asset may need three months of maintenance before production can start; revenue could begin flowing after that three-month period.
- Management declined all financial detail: Questions on valuation, existing capacity, and post-acquisition CapEx were deflected as "too soon" and "very strategic," leaving investors with no visibility into deal economics.
- Debt is already drawn: The entire ₹500 cr acquisition debt has been fully drawn, and the full ₹350 cr from Premji for equity participation has been received; debt could rise by another ₹100 cr, taking total debt close to ₹1,500 cr including working capital, if the acquisition closes.
- Capacity milestone contingent on the deal: If the acquisition closes, capacity would reach 10+ million tons (1 crore ton) by end of FY23, hitting the stated doubling target ahead of the original 2025 timeline.
Sreekanth Reddy: "It is too soon for us to comment on the realization front and as well as the additional CapEx as and when it is appropriate, we'd be more than happy to come back to you on that front sir. It's very strategic for us."
Balance Sheet & Financial Position
- Interest cost is elevated but partly temporary: Interest cost looks high because it includes debt borrowed for the acquisition; once the acquisition is concluded, that portion will get capitalized; current trends are expected to continue into Q3 until an asset is acquired.
- Other income spike is one-off: The jump from ~₹4 cr to ₹12 cr+ includes one-off items and should not be factored into run-rate expectations.
- Tax status reset: With the merger of Gudipadu completed, the company is back under MAT, inclusive of deferred tax.
- Other expenses declined: The ₹10 cr decrease is due to the ramp-up of new plants being mostly completed, with some one-off legal and acquisition expenditures now largely behind them.
- Debt repayment structure undisclosed: Management described the debt as long-tenure with multiple loans each having their own tenure and a "long-drawn kind of a schedule," but declined to provide specific repayment tenures.
Sreekanth Reddy: "We are cognizant of not overstretching our balance sheet in our pursuit of changing scale. And we'll continue to work towards maintaining the right balance between the two."
Strategic Outlook & Long-Term Bets
- Volume guidance maintained: FY23 volume outlook stays at 5 MTPA; Q1 was very close to that run-rate, with ~0.36-0.37 crore from existing assets and ~0.13-0.14 crore from Jeerabad and Jajpur.
- Blended cement target intact: The 60% blended cement target remains; ramp-up at Jajpur and Jeerabad should help achieve that number.
- Capacity doubling ambition: 1 crore tons by 2025 and 2 crore tons by 2035 remains the stated target.
- Long-term demand conviction: Management points to reservoirs being nearly full months ahead of schedule as a positive sign for agriculture and the economy; historically, cement demand has doubled every 10 years, and the medium-to-long-term gap between demand and supply should narrow.
- South volume expectations are muted: Existing operating areas are expected to deliver flat volumes because the market itself is growing at a slower pace; incremental volume will come from newly commissioned assets, with any South growth upside treated as a bonus.
Sreekanth Reddy: "Historically, the cement demand doubled every 10 years. So, if it has to double 10 years, I'm sure we will be falling short of the capacity. So, for some period there could be optically looking like an excess kind of a supply. But we are reasonably confident that on a medium to long-term horizon, the gap should actually narrow down or the demand probably should shoot slightly ahead of supply."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Q2 FY23 cost | Total costing expected to be flat and "very, very similar" to Q1 | Q2 FY23 |
| Q2 FY23 pricing | Similar structure to Q1, with a marginal increase expected | Q2 FY23 |
| Pet coke/coal price benefit | Real benefit from price drops flows through | Mid-to-end Q3 FY23 onward; full benefit Q4 FY23 |
| Jeerabad EBITDA breakeven | Close to 40% capacity utilization targeted; 50% would ensure EBITDA positive | Q4 FY23 |
| Jajpur capacity utilization | 35-40% utilization targeted post-season | Post-monsoon (H2 FY23) |
| FY23 volume | 5 MTPA | FY23 |
| Andhra Cement resolution plan | Submission deadline | Before 18th August 2022 |
| Andhra Cement clearances | NCLT and related approvals expected | End-September to early-October 2022 |
| Andhra Cement production start | Three months of maintenance post-acquisition before production | ~Q4 FY23 / Q1 FY24 |
| Capacity milestone (if acquisition closes) | 10+ million tons (1 crore ton) | End of FY23 |
| Capacity doubling (organic target) | 1 crore ton | By 2025 |
| Long-term capacity target | 2 crore tons | By 2035 |
Key Metrics
| Metric | Q1 FY23 |
|---|---|
| Revenue | ₹558 cr, +42% YoY from ₹393 cr in Q1 FY22 |
| EBITDA | ₹61 cr, −43% YoY from ₹107 cr in Q1 FY22 |
| EBITDA margin | 11%, vs 27% in Q1 FY22; compression of ~1,600 bps YoY |
| Loss after tax | ₹13 cr, vs profit of ₹49 cr in Q1 FY22 |
| Average power and fuel cost per ton | ₹1,827, vs ₹1,017 in Q1 FY22 |
| Freight cost per ton | ₹798, vs ₹764 in Q1 FY22 |
| Realization growth | 5% QoQ |
| Volume guidance FY23 | 5 MTPA, unchanged |
| Capacity utilization (consolidated) | 57% |
| Trade share | 65% |
| Gross debt | ₹1,490 cr, of which ₹1,293 cr long-term and remainder working capital |
| Net debt | ₹1,208 cr, includes ~₹500 cr borrowed for acquisition |
| Net worth (consolidated) | ₹1,639 cr |
| Debt-equity ratio | 0.79:1 |
| Cash and bank balances | ₹282 cr |
| Lead distance | 268 km, reduced from ~283 km |
| Fuel mix | 70% domestic coal, 30% pet coke |
| Jeerabad capacity utilization | ~46% on volume front; touched 100% only in second fortnight of June |
| Jajpur capacity utilization | sub-10%; expected to reach 35–40% post-monsoon |
| Other income | ₹12 cr plus, up from ~₹4 cr (one-offs) |
| Maintenance capex | sub-₹30 cr |
| Principal repayment FY23 and FY24 | ~₹195 cr |