Sagar Cements Ltd Q2 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/gx36uf0m4k0irgio89xct9iz.pdf

Key Takeaways


Cost Structure & Margin Pressure

Sreekanth Reddy: "I think the minute we get aligned, which is not very far that once we get aligned with most of our peers in terms of same blended cement ratios as they would, our power and fuel cost also would be looking at a lot lower than the other sir."

Volume & Realization Outlook

Sreekanth Reddy: "The realizations have been in range of anywhere between ₹15 to ₹20 on an average per bag. So ₹200 to ₹250 per ton can be expected if it remains in a similar kind of a thing, but this is not enough. Yeah, a lot more has to happen."

Andhra Cement Acquisition

Sreekanth Reddy: "We are more than hopeful that, at an NCLT, the Andhra transaction should get concluded or there is a possibility that it should get concluded before end of Q3 is what is the impression that we have."

Capacity Expansion & Optionality

Sreekanth Reddy: "In Mattampally, scope is huge, but we have taken a conscious call that we would only do it after some time because given the South adding a Brownfield or a Greenfield in South not only would put pressure on us, but also on the market."

Regional Demand Dynamics

Sreekanth Reddy: "...contrary to what most of the people think South did grow sir, it's not that it remains stagnant, but supply also had caught up with it."

Logistics & Operational Efficiency

Sreekanth Reddy: "...most of this infrastructure is happening with tollages sir. So, there is a net negative effect on the overall kind of cost even on that... this could be a short term, but medium to long-term, we definitely think it will save quite a bit."

Guidance & Commitments

CommitmentSpecificsTimeline
Full-year volume0.5 crore tons (worst case not below 0.48 crore tons)FY23
Power and fuel cost savingMinimum ₹250/ton reductionQ3 FY23
Andhra Cement NCLT resolutionTransaction concluded in Sagar's favorBefore end of Q3 FY23
Maintenance capexNot exceeding ₹30 croreFull-year FY23
Trade mix normalizationRevert to 65:35 trade:non-tradeGoing forward
Blended cement mix70% blended, 30% OPCOver next couple of years
Lead distance275 kmNo date (target stated)
Full-year EBITDA"A lot lower" than ~₹400 crore indicated at start of year; quantum to be determined laterFY23

Key Metrics

MetricQ2 FY23
Revenue₹475 cr, up 29% YoY from ₹369 cr
EBITDA₹6 cr, down 91% YoY from ₹61 cr
EBITDA margin1%, vs ~16% in Q2 FY22; raw material surge compressed margin by ~1,500 bps
Loss after tax₹49 cr, vs profit of ₹20 cr in Q2 FY22
Average fuel cost₹2,066 per ton, vs ₹1,263 per ton in Q2 FY22
Freight cost₹797 per ton, vs ₹795 per ton in Q2 FY22
Overall capacity utilization~49%
Mattampally utilization50%
Gudipadu utilization93%
Bayyavaram utilization64%
Jeerabad utilization30%
Jajpur utilization10%
Trade share55–57%, expected to revert to 65:35 trade:non-trade mix
Lead distance271 km
Gross debt₹1,486 cr, of which ₹1,275 cr long-term, remainder working capital
Net worth (consolidated)₹1,581 cr
Debt-equity ratio0.81:1
Cash and bank balances₹308 cr
Full-year volume guidance0.5 cr tons maintained, worst case not below 0.48 cr tons; H1 achieved 0.22 cr tons
Full-year EBITDA guidanceRevised downward from earlier ~₹400 cr; quantum to be determined
Expected fuel cost saving in Q3Minimum ₹250 per ton on power and fuel
Price increase observed (exit Sep–mid Oct)₹15–₹25 per bag across most markets; Hyderabad +₹18–20, Vizag +₹15, Bangalore +₹25, Tamil Nadu +₹25, Maharashtra +₹20, Odisha +₹10
Blended cement mix target70:30 blended to OPC over next couple of years; historically sub-40% blended
Andhra Cement acquisition capacity0.26 cr tons (per diligence)
Andhra Cement limestone reserves~16.5 crore tons
Market share (India)~0.9% to 1%, on ~42.5 cr ton base