Sagar Cements Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/mo4qmtw916wj5xc9x3oj4z0z.pdf

Key Takeaways


Profitability Bridge: The Inventory Mask

Sreekanth Reddy: "I would keep my neck out to assume that prices may not drop. Prices may remain flat for the Q3 and start picking up at least from early part of Q4, might sustain till end of February to early part of March and probably small correction for year-end kind of a push."

Andhra Cement Turnaround


Demand & Pricing Outlook

Sreekanth Reddy: "We are very, very hopeful and very positive that demand is likely to be sustained in a similar kind of double-digit growth over the next couple of years, especially in Andhra."

Capacity Expansion & Capex


Vizag Land Sale & Fundraising

Sreekanth Reddy: "Probably there could be a shift of a quarter to six months in the overall sale process. But the good news that we can always celebrate is that Vizag with all the activities that is happening, likely that we might get a better realisation than what we anticipated than before."

Cost Structure & Plant Performance


Guidance & Commitments

CommitmentSpecificsTimeline
FY26 volume~0.6 crore tonnes (6 MTPA) overall sales volumeFY26
FY26 EBITDA per tonne₹600/tonne targetFY26
Jeerabad expansion0.5 MTPA grinding capacity commissionedBefore March 2026
Dachepalli cement capacityCommissioningEnd of Q1 FY27
Gudipadu WHR4.35 MW waste heat recovery project commissionedEnd of FY26
Capacity target1.2 crore tonnes (12 MTPA)End of FY27
Capex₹250 crore balance FY26; ₹250–₹275 crore FY27 including maintenanceFY26 and FY27
Andhra Cement breakevenBreakeven at 50% utilisation; ₹500–₹600/tonne EBITDA at ~60% utilisationNext year
Rights issue / OFSCompletionBefore current financial year end
Vizag land saleApproval process conclusion; sale may shift by a quarter to six monthsCurrent financial year (approval); sale possibly later
Staff cost run-rate~₹36.5 crore per quarterOngoing from Q2 FY26

Key Metrics

MetricQ2 FY26
Revenue₹602 crore, +27% YoY from ₹475 crore in Q2 FY25
EBITDA₹51 crore, up from ₹20 crore in Q2 FY25
EBITDA margin9%, up from 4% in Q2 FY25
EBITDA per tonne₹377; would have been ~₹530 excluding inventory adjustment (per an analyst's math)
Loss after tax₹44 crore
Volume growth~17% YoY
FY26 volume guidance~0.6 crore tonnes
Realisation change3% to 4% decline QoQ, primarily on account of seasonality and non-trade
Power and fuel cost per tonne₹1,428, vs ₹1,446 in Q2 FY25
Freight cost per tonne₹855, vs ₹830 in Q2 FY25
Gross debt₹1,610 crore as on 30 Sep 2025; long-term debt ₹1,216 crore, rest working capital
Net worth (consolidated)₹1,758 crore as on 30 Sep 2025
Debt-equity ratio0.69:1
Cash and bank balances₹175 crore as on 30 Sep 2025
Plant utilisation – Jeerabad94%
Plant utilisation – Gudipadu82%
Plant utilisation – Bayyavaram63%
Plant utilisation – Mattampally48%
Plant utilisation – Jajpur34%
Plant utilisation – Dachepalli32%
Incentives received in Q2₹11 crore; total ₹45 crore received in FY26 so far
Employee cost quarterly run rate~₹36.5 crore going forward, post ~10% annual increment
FY26 capex~₹450 crore expected, up from original ~₹360 crore; ₹180 crore spent in 1H
FY27 capex₹250 crore to ₹275 crore expected, including maintenance capex
Andhra Cement utilisation32%; breakeven expected at 50% utilisation; optimal at 60% with ₹500–₹600 EBITDA per tonne
Jeerabad expansion0.05 crore tonnes addition, commissioning by March 2026
Waste heat recovery project4.35 MW at Gudipadu, commissioning by end of FY26; capex ₹84-odd crore
South industry demand outlook FY26High-single digit; Andhra and Telangana could inch up to low-double digit
South industry demand outlook FY27~15%+ YoY for Andhra and Telangana; 5%–10% Tamil Nadu; 3%–5% Karnataka