Key Takeaways
- Soft quarter, seasonal and cost-led: Rural demand was hit by unseasonal weather and a below-par monsoon, while high raw material prices and rupee depreciation compressed performance in H1.
- Capacity utilization is climbing: Overall utilization rose to 79% in H1 FY24 from 71% a year ago, and the Perundurai plant is now stabilizing toward steady-state operations.
- The Odisha project anchors the growth story: Land acquisition is underway, with commercial production targeted for FY25-26, supporting the stated ambition to reach INR 1,000 crores in revenue over three to four years.
- Margin relief is expected, not promised: Imported raw material prices are stabilizing and cement cost pressure should subside, but management declined to forecast steady-state margins or give segment-level detail.
- What to watch next quarter: Whether the expected H2 demand recovery materializes, any price hikes in Q3/Q4, and progress on the Maharashtra capacity ramp-up targeted for Q4 FY25.
Demand & Operating Environment
- Rural weakness: Unseasonal weather and a below-par monsoon in certain geographies hurt the rural economy, and Q2 is typically a challenging quarter for the roofing business. Elevated inflation continues to weigh on rural consumer spending.
- Roofing demand baseline: Management expects the industry's average growth of 6% to 8% to hold in FY25, implying no structural demand shock despite the soft quarter.
- H2 optimism: H2 is always better than Q1, and management expects H2 to be better than last year, though no quantification was offered.
- Regional pricing gap: Prices in the West are higher than in the South, and the company has not reduced prices. The largest competitor's Pan-India presence gives it an advantage in other markets that Sahyadri does not have.
Capacity & Expansion
- Utilization improving: Overall capacity utilization moved from 71% in H1 FY23 to 79% in H1 FY24. The Perundurai plant is stabilizing on a steady-state basis, and utilization is expected to inch up gradually.
- Maharashtra ramp-up: Capacity ramp-up at the Maharashtra facility is expected in Q4 FY25.
- Odisha greenfield: Land acquisition is ongoing, and commercial production is expected to commence around FY25-26. As a new entrant in the East, margins would initially be low compared to existing players but should converge after one or two years.
Maheshwari: "the land acquisition is going on and we expect it would be around 2025-2026. In the FY '25- '26, it may commence the production."
Margins & Costs
- Raw material and forex drag: High raw material prices and rupee depreciation in H1 FY24 versus H1 FY23 pressured margins. Imported raw material prices are now stabilizing, and other than forex impact, prices are not expected to increase.
- Cement cost: Cement prices have recently increased, but management expects that impact to subside going forward.
- Margin outlook: Going forward, margins should be a little better than what has been seen, though management declined to give any forecast on steady-state margins or bifurcation by segment.
- Competitive margin comparison: The difference in EBITDA margins between Sahyadri and the largest player is more or less the same in terms of reduction percentage. The largest player's Pan-India footprint gives it an advantage in markets where Sahyadri is not present.
- East margin trajectory: As a new entrant in Odisha, margins would definitely be low compared to existing players, but after one or two years, they would be more or less the same.
Maheshwari: "See margin definitely We would be new entrants, so our margin would definitely be low compared to them. But going forward, after one year or two years gap it would be more or less same."
Pricing & Realization
- Price hikes possible: There could be some increase in prices in Q3 and Q4, depending on how the market behaves. No commitment was made on timing or magnitude.
- Fibre price fixing: Fibre prices are fixed for the next year, generally in November and December, providing some cost visibility for a key input.
- Realization and volume undisclosed: Management declined to share realization per meter, volume numbers, or quantity data, calling realization a confidential number.
Maheshwari: "Fiber prices are fixed for the next year, which is going to happen now because generally they fix somewhere in November and December."
Balance Sheet & Working Capital
- Short-term borrowings up: The increase is driven by two factors: the company is not drawing any amount from the bank for capex, and it had to start building inventory of fibre and finished goods for the coming season. Inventory build is a seasonal phenomenon.
- Debtor days improving: Debtors are now at 15 days for H1, down from 18 days last year and 20 days at March ending. The company actively controls debtors to avoid outstanding in the market.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue target | Reach INR 1,000 crores | Next three to four years |
| Odisha commercial production | Commence production post land acquisition | FY25-26 |
| Maharashtra capacity ramp-up | Capacity ramp-up at the facility | Q4 FY25 |
| Roofing demand growth | Industry-average growth of 6% to 8% | FY25 |
| H2 performance | H2 expected to be better than last year | H2 FY25 |
| East margin convergence | Margins to become more or less same as existing players | One to two years after Odisha entry |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Consolidated total income (H1 FY24) | ₹347.3 cr, grew 13.6% vs ₹305.8 cr in H1 FY23 |
| EBITDA (H1 FY24) | ₹42 cr, EBITDA margin of 12.1% |
| Profit after tax (H1 FY24) | ₹18.9 cr |
| Gross debt | ₹139.3 cr as on 30 Sep 2023, including short-term borrowings of ₹101.2 cr |
| Debt to equity | 0.39 as on 30 Sep 2023 |
| Cash and bank balance | ₹2.8 cr |
| Capex incurred (H1 FY24) | ₹45 cr, with ~₹20 cr more expected for full year |
| Roofing demand growth outlook | 6% to 8% average annual growth, expected to continue in FY25 |
| Revenue aspiration | ₹1,000 cr over the next three to four years |
| Capacity utilization (H1 FY24) | 79%, up from 71% in H1 FY23 |
| Sheet capacity | 50,000 tons |
| Asbestos vs Non-Asbestos revenue share (H1 FY24) | 80% Asbestos, 20% Non-Asbestos |
| Debtor days (H1 FY24) | 15 days, improved from 18 days in H1 FY23 and 20 days at March ending |
| Odisha plant commercial production timeline | FY25-26 |
| Maharashtra facility capacity ramp-up timeline | Q4 FY25 |