Key Takeaways
- Subdued rural demand compressed margins: Gross margin fell from 48.5% in Q2 to 44.25% in Q3 as elevated raw material costs could not be passed through in a weak rural demand environment.
- Capacity utilization improved YoY but remains seasonal: 9M FY24 utilization reached 76% vs 66% a year ago, though Q3 dipped to 68% on normal seasonality and finished goods inventory build.
- Capex timelines pushed out across the board: The Odisha plant moved to FY27 and the Wada non-asbestos plant to FY26, with land acquisition still incomplete for both.
- Raw material costs have bottomed, but relief is delayed: Negotiated asbestos fibre prices for CY24 are lower, yet the company carries 6-7 months of inventory, so the benefit will only flow through from Q3 to Q4 onward.
- What to watch next quarter: Whether the post-election demand environment and monsoon allow the targeted 80-82% capacity utilization, and if gross margins begin recovering as lower-cost inventory works through.
Demand & Rural Economy
- Rural weakness is the core drag: Over 80% of the business depends on the rural economy, which remained subdued through Q3, mirroring the pressure seen across FMCG companies.
- Pricing power absent: The company could not pass elevated raw material costs to consumers because of the demand scenario, an industry-wide problem that management says affected all players.
- Election and monsoon as swing factors: The upcoming general election will disrupt March-April activity, while the monsoon remains a "hanging sword" for a business so heavily tied to rural spending.
- Government scheme tailwind is conditional: The PM Awas Yojana's 2 crore additional houses and alignment of Rajasthan, MP and Chhattisgarh with the central government post state elections are positives, but the impact will only materialize when actual spending begins.
- Current quarter still subdued: Management is not seeing demand improvement in the current quarter, though one and a half months remain and things may change positively.
Maheshwari: "One is the demand has to increase. Second is the government impetus on the rural economy that should continue. But post this general election, how the things are going to work out that is also one has to look into. And third, always we have hanging sword of monsoon."
Margins & Cost Structure
- Gross margin compressed sharply: Gross profit margin declined from 48.5% in Q2 to 44.25% in Q3, below the prior-year average of 46.6%, driven by elevated asbestos fibre costs that could not be passed on.
- Raw material relief is in the pipeline but not immediate: Negotiated fibre prices for calendar year 2024 are lower than CY23 and prices have bottomed out, but the company carries 6-7 months of inventory, so the P&L benefit will only appear from Q3 to Q4.
- No pass-through of procurement savings: Management does not expect to pass raw material savings on to customers in the present circumstances, implying the margin recovery will be retained when it arrives.
- Cost-side actions largely done: Management stated that whatever had to happen from the cost front has already happened and does not see much more on that side going forward.
- Finance cost uptick is modest: The quarter-on-quarter increase in finance cost was only INR 20 lakhs (from 3.1 to 3.3), attributed to higher working capital utilization, and described as normal.
Maheshwari: "In the present circumstances, I don't see whatever the saving we are going to do in raw material purchasing will be passed on no."
Capacity & Capex
- Utilization trending up year-on-year but seasonal: 9M FY24 utilization improved to 76% from 66% in 9M FY23, though Q3 alone was 68% as the company builds finished goods inventory ahead of the season.
- Near-term utilization target: Management aims to achieve 80-82% capacity utilization by the end of Q4.
- Odisha plant delayed to FY27: Land acquisition is not yet complete; once done, the asbestos plant must still go through public hearing and pollution board NOC, pushing the timeline out.
- Wada non-asbestos plant delayed to FY26: Land acquisition remains incomplete; construction will begin once that is resolved. The plant will be dedicated to non-asbestos products.
- Southern unit stabilized: The Perundurai plant has sorted out all initial hiccups, the product is well accepted by the market, and utilization is expected to reach 80% next year.
- No diversification into metal roofing: Management is not looking at other roofing categories like metal roofing, prioritizing pan-India expansion of the existing portfolio first.
Product & Market Development
- Non-asbestos gaining traction: The non-asbestos business is gaining traction and expected to continue growing, with ongoing product development work and the future Wada plant dedicated to this segment.
- Asbestos sheet remains the rural staple: The industry projects growth to US$5.6 billion by 2028, with asbestos roofing sheets retaining preference in rural areas due to low cost and high durability.
- Southern and western market split disclosed: Management provided revenue percentage splits for southern and western markets but declined to give a margin breakup by region.
- Price hike possibility in Q1 next year: Q1 is generally a good quarter seasonally; management hopes for some price increase, though the quantum depends on demand and supply and was not quantified.
Management Posture & Disclosure
- Volume data withheld: Management declined to provide volume figures or a volume-vs-value growth breakup, stating "We generally don't give a volume. It is a value."
- FY25 outlook declined: When asked for a volume growth outlook for FY25, management declined to give a forecast and directed the analyst to estimate from historical trends.
- Peer comparison disputed: An analyst's assertion that other building material companies delivered substantial EBITDA upside while Sahyadri lagged was firmly rejected; management stated they are "among the highest in the growth in terms of revenue as well as in the profitability" and that the raw material cost issue is industry-wide.
- Rating update timing: The rating rationale will be published after the year closes, around June-July.
Maheshwari: "We generally don't give a volume. It is a value."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity utilization | Achieve 80-82% utilization | By end of Q4 FY24 |
| EBITDA margin maintenance | Maintain ~10% EBITDA margin | Ongoing, contingent on normal geopolitical and market conditions |
| Gross margin improvement | Better in coming quarters | Contingent on demand increase, forex normalization, and government rural schemes |
| Odisha plant commissioning | Plant operational | FY27, subject to land acquisition, public hearing, and NOC |
| Wada non-asbestos plant commissioning | Plant operational | FY26, subject to land acquisition completion |
| Southern unit utilization | Reach 80% capacity utilization | Next year (FY25) |
| Raw material cost benefit in P&L | Lower-cost inventory flows through | Q3 to Q4 FY24 onward, given 6-7 month inventory lag |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Consolidated total income | ₹136.3 cr, +10.2% YoY |
| EBITDA | ₹13.8 cr, margin 10.1% |
| Profit after tax | ₹3.2 cr |
| 9M FY24 consolidated total income | ₹483.7 cr, +12.6% YoY |
| 9M FY24 EBITDA | ₹55.8 cr, margin 11.5% |
| 9M FY24 profit after tax | ₹22.1 cr |
| Building material segment revenue growth | +13% YoY, +15% QoQ |
| Building material segment EBIT growth | +29% YoY, +150% QoQ |
| Overall capacity utilization | 68% for Q3, improved from 66% in 9M FY23 to 76% in 9M FY24 |
| Capacity utilization target for Q4 FY24 | 80%–82% |
| Gross profit margin | 44.25%, declined from 48.5% in Q2 FY24 and 49% in Q3 FY23 |
| Market share in West | 35%–37% |
| Market share in South | 18%–20% |
| Total debt | ₹140 cr, comprising ₹45 cr long-term and ₹100 cr short-term working capital |
| Blended cost of funds | ~8% |
| Credit rating | A- |
| Perundurai (Southern) plant capacity utilization | 60%, expected to reach 80% next year |
| Asbestos fibre price decline negotiated for CY24 | ~2% lower than CY23 |
| Capex spent on Odisha and Wada plants | ₹45 cr |
| Capex timeline: Wada plant | Delayed to FY26 |
| Capex timeline: Odisha plant | Delayed to FY27 |