Key Takeaways
- A quarter hit by shutdowns, not demand collapse: Revenue fell to INR967 crore and operating EBITDA to INR281 crore, but the primary drivers were a two-month maintenance shutdown of the Sarda Metals plant and a delayed monsoon, not a structural demand failure.
- Captive raw materials are the margin shield: Captive coal, captive iron ore pellet consumption (35-40%), and a natural forex hedge insulated the company from the worst of rising input costs, falling steel prices, and currency volatility.
- Ferro alloys poised for a volume rebound: The 36 MVA Vizag expansion is mechanically complete, trial runs are imminent, and management expects to return to historical sales volumes of over 40,000 tons in Q3, even as European demand remains constrained.
- The growth pipeline is approvals-heavy: A coal mining capacity increase, a new coal mine, and a hydropower capacity upgrade all advanced through the regulatory process, but each requires further clearances before capex translates into production.
- What to watch next quarter: Whether the Vizag ferro alloys expansion achieves commercial production on schedule, the trajectory of ferro alloy prices which management calls "fluid," and any government movement on steel export duty reductions.
Operational Performance: The Shutdown Quarter
- Maintenance, not market, drove the top-line dip: A two-month captive power plant shutdown at the Visakhapatnam subsidiary halted ferro alloy production, while a separate maintenance shutdown at the Raipur power unit curtailed steel and power output. The company partly offset the power deficit by importing from the grid.
- Hydropower was a mixed bag: The Sikkim project achieved a strong ~63% PLF in H1 as an extended monsoon into October compensated for an initial delay. The Gullu project underperformed, generating 4.44 crore units vs 7 crore units in H1 FY22, due to scattered rains.
- Record production in pockets: Despite the shutdowns, the company delivered its highest-ever quarterly production of HB wire and highest-ever half-yearly production of pellet and HB wire.
- Profit held up better than revenue: Consolidated PAT rose to INR181 crore in Q2 FY23 from INR170 crore in Q1 FY23, even as revenue and EBITDA declined. A divergence between consolidated segment realization and profit was attributed to low-margin trading activities in coal and other goods.
- Credit quality improved across the group: Chhattisgarh Hydropower LLP's long-term rating was upgraded from ICRA 'A-' to ICRA 'A', and all operating subsidiaries saw external credit rating upgrades during the year.
Pankaj Sarda: "It seems like that. But nothing is sure in this market."
Ferro Alloys: Expansion Meets a Divided Demand Picture
- Domestic demand is robust, Europe is the problem: Management described Indian ferro alloy demand as "quite strong and firm," with Middle East and Asian demand at similar levels. The weakness is concentrated in Europe, where steel plants have cut production due to high electricity costs driven by the Ukraine-Russia war.
- A supply-side opportunity is emerging: European ferro alloy production centers are shutting down, with management citing a specific plant closure in Slovakia due to high electricity costs. The company expects this to open up demand from America, which was previously served by European plants, creating a new avenue for Indian ferro manganese.
- The Vizag expansion is at the inflection point: Installation of the 36 MVA ferro alloys expansion project is complete. The company has applied for consent to operate, expects trial runs to start by November-end 2022, and targets full commercial production from Q4 FY23.
- Volume guidance signals confidence: Management expects to maintain historical sales volumes of more than 40,000 tons in Q3 FY23, though it may sell more tonnages domestically if European demand constraints persist. The company is "hopeful of selling all production from Vizag once it ramps up."
- Pricing remains the wildcard: Ferro alloy prices have started rising again after a correction from oversupply, and higher energy prices in other parts of the world may help improve realizations. Management characterized the pricing environment as "little fluid right now."
Manish Sarda: "Domestic demand is quite robust and we are not seeing any major issues in the domestic markets. What we are facing issues are with the international markets where the war is still continuing between Ukraine and Russia."
Steel: Margin Pressure Absorbed by Structural Advantages
- The industry took a policy hit: The domestic steel industry softened after the imposition of export duties, while increased coal prices put pressure on margins. India's steel production degrew 2.9% QoQ, exports halved, and imports increased, though domestic consumption rose from 2.74 to 2.79 crore metric tons.
- SEML's structural hedges worked: The company does not export any steel products, so it was not directly hit by export duties. Captive consumption of 35-40% of iron ore pellets, captive coal providing lower and stable fuel and power costs, and a correction in market-sourced iron ore prices all cushioned the impact of falling steel prices.
- Low net debt provided insulation: The company's low net debt position insulated it from rising interest rates, a benefit management explicitly highlighted.
- The demand outlook is constructive: With the end of the monsoon, management expects steel demand in India to improve in H2 FY23, driven by government spending, construction revival, and auto sector recovery. Any relaxation in export duties would be an additional positive for pricing and demand.
- India as a China alternative: Management expressed strong optimism about Indian steel demand, positioning India as a beneficiary of the vacuum left by European steel production cuts and reduced Chinese exports.
Manish Sarda: "We are very optimistic that the markets in India are very, very good. And globally also the Indian steel demand will be good because in the absence of the European steel and the absence of exports from China, we are seeing that India will have an opportunity and everybody is looking towards India as an alternative good option to replace China."
Coal & Power: The Captive Advantage Deepens
- Captive coal is the competitive moat: Captive coal provides lower fuel cost for own consumption and better margins on coal sales, a structural advantage management emphasized as a key differentiator.
- Mine approvals are stacking up: The government approved the mining plan for the Shahpur West coal mine in Madhya Pradesh and approved an increase in mining capacity of Gare Palma IV/7 from 0.12 crore tons to 0.18 crore tons. Environmental clearances are in process. The company plans to eventually increase Gare Palma IV/7 capacity to 0.3 crore tons per annum.
- Thermal coal prices seen as range-bound: Management expects thermal coal pricing to remain "more or less subdued for the next three months" and not head upwards.
- Vizag power plant sourcing strategy: The company primarily aims to use own coal from captive mines, blended with Indonesian and RB3 coal for economical consumption.
- Grid power costs are a headwind for the industry, not SEML: Grid power prices increased across most state utilities due to compulsory mixing of imported coal, reducing margins for steel and ferro alloy manufacturers who rely on the grid. SEML's captive power generation insulates it from this pressure.
Hydropower: Steady Cash Flows, Slow Capacity Build
- Sikkim delivered despite a delayed start: The Sikkim hydropower project achieved ~63% PLF in H1 FY23, as a delayed but extended monsoon into October "majorly compensated" for the initial generation loss.
- Gullu and Uttarakhand underperformed modestly: Gullu generated 4.44 crore units in H1 FY23 vs 7 crore units in H1 FY22 due to delayed and scattered rains. Uttarakhand generated 1.2 crore units vs 1.38 crore units in H1 FY22.
- Q3 is the lean season: Management noted that while October was reasonably good, November and December are the off-season with capacity utilization dropping to ~20-25%. Rainfall in the catchment area was normal and comparatively better than other years.
- Capacity expansion is approvals-gated: The government approved increasing the Uttarakhand hydropower project capacity from 4.8 MW to 8.3 MW, but the company must now secure further approvals before execution can begin.
- Rehar is on track for FY24-25: The 25 MW Rehar hydro project is progressing as per schedule, with orders placed for long delivery items, and completion expected before the end of FY24-25.
P.K. Jain: "Since government has approved the expansion of the capacity, now we have to go for other approvals for execution of the project. So, it will take some more time before we start work on the project."
Macro & Policy: Waiting on Export Duty Relief
- Export duty reduction is a matter of "when," not "if": Management is hopeful the government will take a lenient view on export duties, stating it is "only a matter of time" before some form of reductions materializes. Once duties ease, a firm recovery is expected because European steel plants are not at full capacity and will need imports from India.
- The war is the macro wildcard: Management identified the Ukraine-Russia war as a major factor determining India's economic trajectory, not just for direct trade disruption but because energy costing has an impact on the overall global economic situation.
- Rupee depreciation is a net neutral: The company has a natural hedge because it exports ferro alloys and imports coal and manganese ore, so currency exposure is limited. Management expects the rupee to remain range-bound between 81.5-83.5 and the pound between 93-96.
- European demand recovery is a high-upside scenario: If the war eases and European steel plants restart, management believes demand will be "actually quite huge."
- A share split is under consideration: Management acknowledged an investor request for a share split to increase market float and said it will "definitely" consider it.
Manish Sarda: "We are hopeful that the government will take a lenient view on the export duties also, which they've been working on. And it's only a matter of time that we hear some form of reductions in the export duty so that the domestic market is also protected and the international markets are also serviced by the Indian companies."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Vizag ferro alloys commercial operation | Trial runs to start November-end 2022; full production thereafter | Q4 FY23 |
| Ferro alloys sales volume | Maintain historical number of more than 40,000 tons | Q3 FY23 |
| Rehar hydro project completion | 25 MW project construction progressing as per schedule | Before end of FY24-25 |
| Gare Palma IV/7 mining capacity | Increase from 0.12 crore tons to 0.18 crore tons (environmental clearances in process); eventual target 0.3 crore tons | Undated |
| Uttarakhand hydro capacity expansion | Increase from 4.8 MW to 8.3 MW approved; further approvals required before execution | Undated |
| Shahpur West coal mine | Mining plan approved; environmental clearances in process | Undated |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Consolidated revenue | ₹967 cr, vs ₹1,261 cr QoQ and ₹1,025 cr YoY |
| Operating EBITDA | ₹281 cr, vs ₹365 cr QoQ and ₹404 cr YoY |
| Consolidated PAT | ₹181 cr, vs ₹170 cr QoQ and ₹256 cr YoY |
| Consolidated gross debt | ₹1,380 cr as on 30 Sep 2022 |
| Net debt (net of cash and current investments) | ~₹700 cr as on 30 Sep 2022 |
| Net debt (net of loans given as treasury operations) | ~₹350 cr as on 30 Sep 2022 |
| Loans repayable within 1 year | ₹166 cr |
| Standalone net debt status | Net debt-free with surplus funds |
| Ferro alloys export volume | 16,740 metric tons, vs 26,300 QoQ and 24,131 YoY |
| Ferro alloys export value | ~₹175 cr, vs ₹338 cr QoQ and ₹255 cr YoY |
| Sikkim hydropower project H1 FY23 PLF | ~63% at generation bus level |
| Sikkim hydropower project H1 FY23 billing | 31.2 cr units |
| Gullu hydropower plant H1 FY23 generation | 4.44 cr units, vs 7 cr units YoY |
| Uttarakhand hydropower project H1 FY23 generation | 1.2 cr units, vs 1.38 cr units YoY |
| Ferro alloys current capacity | 111 MVA, expanding to 147 MVA |
| Ferro alloys tonnage capacity (ferro manganese) | ~240,000 tons |
| Vizag ferro alloys expansion capacity addition | ~40,000 tons per annum, ~10,000 tonnes per quarter |
| Captive iron ore pellet consumption | 35% to 40% of production |
| Raipur coal consumption from captive mines | ~60% of ~0.1 cr tons per annum |
| India steel production Q2 FY23 | 3.01 cr metric tons, degrowth 2.9% QoQ, growth 4.15% YoY |
| Global steel production Q2 FY23 | 45.2 cr metric tons, degrowth 9% QoQ and 1.2% YoY |
| India steel exports Q2 FY23 | 0.18 cr tons, vs 0.28 cr tons QoQ |
| Domestic steel consumption Q2 FY23 | 2.79 cr metric tons, vs 2.74 cr metric tons QoQ |
| Gare Palma IV/7 coal mine approved capacity increase | 0.12 cr ton to 0.18 cr ton, future plan to 0.3 cr tons per annum |
| Rehar hydro project capacity | 25 MW, expected completion before end of FY25 |
| Uttarakhand hydropower capacity increase permission | 4.8 MW to 8.3 MW |
| Hydropower capacity utilization in Q3 lean season | ~20–25%, declining further until 15 March |
| Thermal coal price drop (South African grade) | $10–$15 in the last week |
| Rupee expected range | 81.5–83.5 |