Key Takeaways
- Record revenue, two-speed growth: Revenue hit a quarterly high of ₹113.07 crores (+15.74% YoY), but the shunt division grew only 8.97% while bimetal surged 22.45%, reflecting post-COVID inventory normalization and energy-cost headwinds in export markets.
- Capacity expansion is now operational: The new plant received its certification and is in trials, with the full mill process taking 18–20 months; management says business materialization is already in advanced stages and the capacity increase process is "completely set up and working."
- Smart meter boom is a Q3 story: Less than 1% of the 25 crore target has been deployed, and the real push is expected from Q4 2023 or January 2024, with the shunt business boom materializing from Q3 FY24 onward as relay manufacturing bases are set up in India.
- Revenue guidance hedged but confident: Management is hopeful of 25% growth; if global factors intervene, "strong growth of 15% to 20%" is the floor, which it still considers strong in the current environment.
- What to watch next quarter: Whether the promised Q3 shunt demand recovery begins to show in order books, the pace of customer scaling in the shunt resistor business, and any inorganic move given management is "assessing" opportunities.
Top-Line Performance & Divisional Split
- Record quarter with divergence: Consolidated revenue of ₹113.07 crores was the highest ever, with gross profit at ₹56.31 crores (+14.97% YoY) and EBITDA at ₹28.99 crores (+19.60% YoY), driven by operational efficiency and innovation.
- Bimetal strength: The bimetal division grew 22.45%, contributing to India's electrification transformation, with strong domestic demand offsetting slower-than-anticipated export growth.
- Shunt softness: The shunt division grew only 8.97%, held back by post-COVID inventory rebalancing as supply chains normalized, the Ukraine war's energy-cost impact on European and North American manufacturing, and inflation and interest rate hikes weakening demand.
- Shunt mix stable for now: Automotive and metering currently have almost the same split within shunt; that ratio is expected to remain similar for another few years before automotive may take over, though it is hard to split EV from non-EV because certain common shunts are used in both applications.
- Customer scaling is deliberately slow: Large automotive customers start with 5% share for one year, then 10%, then 15%; even after 3–4 years of approval, real scaling happens only after trust is built beyond a certain number of years, and the company has made inroads to many big customers rather than depending on one or two.
Kanav Anand: "We are very hopeful. We are very confident and we are looking at number even if it's not 25%, we are looking at a strong growth, anything between 15% to 20% which will keeping in mind the current situation that we see globally will still be a very strong, I would say growth for Shivalik."
Capacity Expansion & New Plant
- New plant certified: The new factory received its certification, triggering a procedural exchange disclosure; the plant was already in trials and continuation, with equipment installed and commissioned earlier but official factory licenses obtained more recently.
- Mill process timeline: Setting up the mill process takes 18–20 months; full CAPEX completion is about 18 months from today.
- Capacity nearly tripled: Expansion has nearly tripled capacity; sampling was done with existing processes, and customers gave opportunities once installed capacity was confirmed.
- Business materialization underway: Materialization of business has already happened and is in advanced stages; management expects bimetal output to increase by 50% to 60% from added capacity, with stronger growth in coming quarters and years because the capacity increase process is now completely set up and working.
- Electrical contacts reset: The electrical contacts business was a joint venture until about a year ago; now being a wholly owned subsidiary, the method of working has become totally different. The existing plant is running at full capacity and a new plant is under construction, expected to be running in about 12 to 14 months.
- Contacts capacity fill-rate split: For about 50%–60% of product categories, as soon as capacity is added, it should fill up with business because existing customers want more supply; for the other half, revalidation and testing requirements after moving to the new plant will take longer.
Sumer Ghumman: "I can confidently say about half of that business can be increased by just adding capacity."
Smart Meter Opportunity
- Deployment still negligible: Out of the 25 crore smart meters targeted, roughly 0.2 crore have been deployed so far, less than 1% of the program.
- Real push timing: The real push toward smart meter deployment is expected in Q4 2023 or January 2024; the real boom for Shivalik's shunt business from smart meters is expected to start materializing from Q3 FY24 onward, as relay manufacturing bases are being set up in India.
- Realistic completion timeline: The government's optimistic plan is FY26, but realistically, looking at capacities installed and the speed of installation and service (since contracts bundle all three), it would take 6 to 7 years to complete the installation.
- Target market share: Management is targeting 60% to 70% market share on the shunt side for smart meters, similar to the current share in single-phase meters.
- Silver contact add-on: With smart meters coming in, there is added opportunity in the silver contact business because relays will use silver contacts; the faster India can adopt manufacturing of those relays, the higher the opportunity.
- Growth driver sequencing: In the initial few years, the growth driver will probably come more from smart meters due to the government push; in 3 to 4 years, EVs and hybrids are expected to become the driver of growth.
Kanav Anand: "The optimistic plan, yes, as per the government, is of FY26. But realistically, we feel that looking at the capacities installed and the speed because it's not just as I was explaining, it's not just making meters, but it also includes installation and service providing because all these contracts are including that. So, it would take almost, according to us, anything between 6 to 7 years to complete this installation."
Inventory, Margins & Capital Allocation
- Inventory days reduced significantly: Inventory days came down due to conscious inventory management efficiency measures, a shift from "just in case" to "just in time," and increased reliance on local resources; management says the level is sustainable at approximately 200 days.
- Margin expansion at scale: At ₹1,500 crore plus scale, operational efficiency will give at least 2% to 3% additional EBITDA margin; at ₹1,600 crores revenue, EBITDA margin could reach 28%–29%.
- Capital raise not imminent: No proposal is currently on the table; management is looking at various inorganic opportunities and assessing them, and a capital raise may be considered if a situation arises and a project demands it.
Demand Recovery & Near-Term Outlook
- Shunt demand recovery expected H2: Q1 and Q2 may be slower, but strong demand is anticipated in Q3 and Q4.
- Domestic market strong: Domestic market demand is strong, and international presence is strengthening; export business growth is not as much as anticipated, but since it is a smaller percentage, the impact is limited.
- Full capacity utilization distant: Full utilization of the ₹1,600 crores revenue potential across three units is expected in 5 to 7 years, depending on various factors.
Sumer Ghumman: "I feel that this utilization and this number of the capacity that you just mentioned, we are looking at that and anywhere between a 5-to-7-year kind of a period depending on various factors."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 15% to 20% growth as the floor; hopeful of 25% | FY24 |
| Smart meter shunt boom | Real business push to begin materializing | Q3 FY24 onward |
| Smart meter deployment push | Government deployment push to begin | Q4 2023 or January 2024 |
| Bimetal output increase | 50% to 60% increase from added capacity | Coming quarters and years |
| Full CAPEX completion | All CAPEX completed | ~18 months from Q1 FY24 |
| Electrical contacts new plant | New plant running and capacity added | 12 to 14 months |
| Full capacity utilization | ₹1,600 crores revenue potential across 3 units | 5 to 7 years |
| Smart meter program completion | 25 crore smart meters installed (realistic estimate) | 6 to 7 years |
| EBITDA margin at scale | 28%–29% EBITDA margin | At ₹1,600 crores revenue |
| Shunt growth driver shift | EVs and hybrids become primary growth driver | 3 to 4 years |
Key Metrics
| Metric | Q1 FY24 |
|---|---|
| Revenue | ₹113.07 cr, +15.74% YoY, highest quarterly figure in company history |
| Gross profit | ₹56.31 cr, +14.97% YoY |
| EBITDA | ₹28.99 cr, +19.60% YoY |
| EBITDA margin | 23% to 26%, maintained at this range currently |
| Bimetal division growth | +22.45% YoY |
| Shunt registered division growth | +8.97% YoY |
| Full-year revenue growth guidance | 15% to 20%, management confident of strong growth though global factors remain a variable |
| Revenue potential at full capacity utilization | ~₹1,600 cr across 3 units, 5-to-7-year timeline to reach full utilization |
| CAPEX completion | ~80% completed, remaining expected in ~18 months |
| Inventory days | ~200 days, sustainable level achieved through inventory management efficiency |
| Domestic smart meter revenue contribution | ~4% to 5% of total revenue, overall metering is 24% to 26% of total revenue |
| Market share in domestic single-phase meter shunts | 65% to 70% |
| Opportunity per smart meter | ~₹150 total per meter, shunt component ~₹45 to ₹50 |
| BMS shunts as percentage of automotive revenue | ~45% of total automotive revenue |
| Shunt business mix | 75% to 80% from automotive and metering combined, balance from energy storage and inverter applications |
| Export resistor business Tier-1 supplier share | 25% to 30% Tier-1, 65% to 70% Tier-2 |
| Electrical contacts capacity expansion | ~100% increase in first phase within 12 to 14 months, another ~100% in subsequent phase |