Scan Steels Ltd Growth Catalysts - SOIC x StockScans Report

as of Jul 2026

  1. Billet debottlenecking to 3 LTPA - The MS Billet capacity expansion from 2.0 to 3.0 LTPA is on track for completion by September 2026, removing the bottleneck that has kept the existing 3.0 LTPA TMT rolling mill running at only 2.0 LTPA. Management expects this to add ₹22 Cr to EBITDA in FY27, a \~45% lift on the current ₹49 Cr base, from capacity that is already built and funded.
  2. Pipe mill & galvanizing facility (2 LTPA) - A 2.0 LTPA pipe mill with hot-dip galvanizing and epoxy coating is under construction at an estimated capex of \~₹80 Cr, with completion expected by Q3 FY28. The project targets NHAI, transmission, and Jal Jeevan Mission demand and is guided to contribute ₹73 Cr to EBITDA in FY28, more than doubling the current group EBITDA.
  3. Bindals Sponge acquisition & revival - The NCLT-approved acquisition of Bindals Sponge Industries (1.0 LTPA billet capacity, 350 TPD DRI kiln, 12.5 MW captive power) was settled with ₹20 Cr infused by Scan and ₹20 Cr infused by KAII, with Scan holding operational control upon reconstitution. Operations are expected to resume by March 2028, adding a third production site with integrated DRI-to-billet capability at a fraction of greenfield cost.
  4. Greenfield integrated steel complex - Odisha - A greenfield complex comprising a 12 LTPA pellet plant, 2.5 LTPA DRI unit, 1.0 LTPA billet/SMS, 12 LTPA coal washery, and 50 MW captive power is planned with \~₹850 Cr capex and commissioning targeted for Q3 FY31. Management projects this will take group EBITDA to ₹575 Cr in FY31, funded by ₹500 Cr of fresh equity and ₹350 Cr of internal accruals with no term debt.
  5. Captive power expansion to 58 MW - Captive power capacity is expanding from the current 8 MW (100% utilized in FY26) to 58 MW, with the 50 MW greenfield addition tied to the Odisha complex and a separate 30 MW plant at Unit-II Gangajal scheduled for FY27. The waste-heat-recovery component alone is expected to deliver power at \~₹2/kWh against grid power at \~₹6.80/kWh, directly widening per-tonne margins.
  6. Hot charging & per-tonne margin uplift - Hot charging for the rolling mill was commissioned in FY26, and management has laid out a per-tonne cost roadmap targeting blended EBITDA of \~₹8,525/T by FY31, up from ₹3,013/T in FY26. Each ₹1,000/T improvement on current volumes of \~164,000 MT adds roughly ₹16 Cr to EBITDA, making the margin path a meaningful earnings driver even before new capacities come online.