Synergy Green Industries Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/1gged1nms91ifq8ftgsvpzsh.pdf

Key Takeaways


The Quarter's Damage: A Self-Inflicted Wound

Reddy: "Fundamentally, nothing has changed. I do know there is an expectation has to happen on q-o-q and other things. But there are certain things, we are going through the transformation period... Under the revenue, I think it's a temporary thing. There is no reason why results should be lagging."

The Capex Bet: Doubling Capacity and Bringing Machining Home

Reddy: "If you look at the capex, historically, in the last 13 years, we've done about 200 crores capex. This year alone, we are doing 200 crores capex. Means, it's a 15 years' worth capex we are doing in one year."

Margin Bridge: The 4% Hit and the Recovery Path


Order Book and Customer Development

Reddy: "They are asking 40,000 Tonnes, 35,000 Tonnes kind of numbers. Boss, I'm telling first to use the 10,000 Tonnes, we'll talk about the 30-40,000 Tonnes."

Export Competitiveness and the Tariff Wildcard

Reddy: "Soon after the waiver of tariff was announced, I got an immediate call from some of the US clients, so I'm expecting a big order book. Now, he's saying, don't stop the production, please go ahead with the full speed."

Domestic Wind Tailwinds and Non-Wind Diversification


Guidance & Commitments

CommitmentSpecificsTimeline
FY26 revenueFull-year revenue growth of 5% over previous year; executable order book projection ~₹380 croresFY26
FY26 PBDIT marginAround 14% for the full yearFY26
Foundry expansion completionEquipment commissioning completedQ4 FY26
Automated moulding lineSecond line (automated) completedMarch-end (Q4 FY26)
Machining phase 2Machines commissionedQ1 FY27
FY27 revenue₹500 crores-plusFY27
FY27 marginMinimum 16% plus; H2 FY27 may clock 18-20% on weighted average basisFY27, with H2 skew
Envision serial supply₹30 crores spilled business begins; 10,000 tonnes annual take-offQ1 FY27 onward
L&T/BHEL conventional power20-25 crores annual business after ~6 months developmentH2 FY27
Adani 3.3MW platformDevelopment activity completed; ₹60-80 crores revenue potentialDevelopment completes next month; revenue timeline unstated
Capacity utilisation90%-plus from Q1; 90-95% achievable with current order bookQ1 FY27 onward
Margin exit rateCloser to 20% with full capacity and machining in placeQ4 FY27
Finance cost ratioNot to exceed 3-4% of revenue; early loan repayment possibleQ3 FY27 prospect changes significantly

Key Metrics

MetricQ3 FY26
Total incomeDropped 4.8% over same period previous year
PBDIT₹9.62 cr, around 34% drop over same period previous year
PBDIT margin10.32%
9-month total income₹252.92 cr, a 4.8% drop
9-month PBDIT₹34.48 cr, a 10.2% drop
9-month PBDIT margin13.63%, down from 14.44% in 9M FY25
Full-year FY26 revenue growth guidance~5% increase over previous year
Full-year FY26 executable order book~₹380 cr
Full-year FY26 PBDIT margin guidance~14%
Capacity utilization89% as of Dec 31, 2025, based on 30,000 tonnes per annum capacity
Highest monthly production~2,800 tonnes, historically 10% higher than previous best
Installed capacity30,000 metric tonnes per annum, upgrading to 45,000 metric tonnes
Order bookWell above ₹500 cr; customer projections exceed ₹650-700 cr
FY27 revenue guidance₹500 cr plus, intact
FY27 margin expectation16% plus; second half could clock 18-20%
Solar savings₹60-70 lakhs per month in electricity bill
Envision business spillover~₹30 cr anticipated in current year, shifted to Q1 FY27
Outsourcing impact600-700 tonnes outsourced in Q3; ~1% of margin eaten away
Commodity price increase8-10% from January onwards; ₹3,000-4,000 per ton in last 4 weeks
Debt-equity ratioCloser to 1:2
Maharashtra government incentive~₹29 cr sanctioned, claimed over 10 years, ~₹2.9 cr per year