Shyam Metalics & Energy Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/lkqz3i6tkkg0vet2kc8vbcsm.pdf

Key Takeaways


Volume & Revenue Drivers

Brij Bhushan Agarwal: "It's basically a multi-bagger metal basket when we call it as a Shyam Metalics. So we have to make sure that we have to grow by 20%, 25% every year."

Margin & Cost Structure

Deepak Agarwal: "We changed our depreciation methodology, the shifting from written-down value method to straight-line method, which is in line with the industry practice to provide a more representative, and true and fair picture of the company's financial performance."

Capex Pipeline & Project Updates


Maharashtra Project

Brij Bhushan Agarwal: "So for next 1.5, 2 years, there is no such decision on the execution of this project is going to be mature. These are all the preliminary homework what we have to do to set up the bigger plants."

Capital Allocation & Balance Sheet

Brij Bhushan Agarwal: "We don't put everything in one basket at one time. ... Till we are not 1,000% sure, we don't take any project further till we are very comfortable."

Strategic Positioning & Competitive Moat

Brij Bhushan Agarwal: "You can't survive in the long term without your HR. You need to have your HR. This is not going to be a business like before that you buy an HR as you make color-coated. So the kind of business what we are building up, we are building from end-to-end from ore to colors. And we don't have to look back."

Guidance & Commitments

CommitmentSpecificsTimeline
Stainless steel EBITDA~₹1,100 crores EBITDA from stainless steel businessBy FY31
SBQ EBITDA~₹1,000 crores EBITDA from SBQ businessBy FY31
Return targetsRoE of 16% and RoCE of 24%By 2031
Planned capex deployment~₹8,864 crores deployed, funded through internal accrualOver next 2–3 years
Stainless steel expansion₹2,700 crores Odisha plant with downstream processing and SBQ plant commissionedBy March 2029
HR plant commissioningJamuria HR flat product plantBy 2028
Coal block productionPhutamura coal block production start; incremental EBITDA of ~₹400 croresBy July 2027; by FY31
Value-added revenue mix70–80% of revenue from value-added products, ~20% from basic suppliesIn next 2 years
Maharashtra land acquisitionGovernment to acquire and hand over landNext 1–1.5 years
Maharashtra major capexMajor capex begins only after existing capex is capitalizedAfter FY29–30
Overall EBITDA marginMove from 11.5–12% to 14.5–16%No date (ambition stated)
Net debtRemain more or less at current levels after ongoing expansionThrough expansion cycle

Key Metrics

MetricQ2 FY27
Revenue from operations₹5,960 cr, up 33.4% YoY and 9.3% QoQ
EBITDA₹857 cr, up 40.9% YoY and 5.5% QoQ; margin 14.4%
Operating EBITDA (excl. other income)₹823 cr, up 52.6% YoY and 7.5% QoQ; margin 13.8%, expanded 170 bps YoY
Profit after tax₹511 cr, up 96.2% YoY and 45.7% QoQ
H1 FY27 revenue₹11,415 cr, up 28.4% YoY
H1 FY27 EBITDA₹1,670 cr, up 34.4% YoY; margin 14.6%
H1 FY27 PAT₹862 cr, up 56.4% YoY; PAT margin 7.5%
Total sales volume15.49 lakh tons, up 26% YoY
Carbon steel flat product sales volume~81,500 tons, more than double YoY
Stainless steel sales volume~29,850 tons, up 20.7% YoY; realization up 35.2% YoY
Specialty alloy volumeUp 4.7% YoY; realization up 18.4% YoY
Aluminum volumeUp 3% YoY; realization up 27.7% YoY
Operating cash flow (H1 FY27)₹1,544 cr, covering capex of ₹1,291 cr
Net debt₹192 cr as of Sep 2026
Working capital daysNegative 16 days as of Sep 2026
RoE14% as of Sep 2026; target 16% by FY31
RoCE20% as of Sep 2026; target 24% by FY31
Capex incurred in Q2₹716 cr
Balance planned capex~₹8,864 cr, to be deployed over next 2–3 years
CWIP in asset base~₹3,000 cr, earning potential not yet reflected
Aluminum foil capacity~42,000 tpa after commissioning 18,000 tpa in July
Mittal Corp capacity utilization~85%
Mittal Corp EBITDA per ton~₹10,000
Stainless steel EBITDA per ton₹13,000–15,000
Carbon steel EBITDA per ton₹6,000–7,000 on average
Aluminum EBITDA per ton~₹40,000
Raw material cost~71% of revenue in Q2
Maharashtra MOU planned capacity0.9 crore tons crude steel, over 8–10 years; first phase 0.45–0.5 crore tons
Maharashtra MOU investment₹50,000 cr (per an analyst's math)