Key Takeaways
- H1 on plan, H2-weighted year: ~₹3,800 crore of sales booked (~38–40% of the ₹10,000 crore target) with only one large launch, keeping the company on track for its planned 40:60 H1:H2 split and making management "more confident" on the full year.
- Realizations crossed ₹17,000/sq ft, a portfolio-level record driven by mix shift toward premium product and single-digit site-level price escalations, even as the pace of price rise slowed.
- Balance sheet absorbed ~1 crore sq ft of land addition (Farrukhnagar, Sohna, Sector 71/37D) while net debt stayed flat at ~₹450 crore, because most additions were structured as collaborations and funded by operating cash flows.
- Margins swung sharply with completion mix: Q2 gross margin hit ~36% and EBITDA margin ~18% (vs H1 averages of 31% and 13%) as completions tilted toward mid-income projects; the full-year margin story depends on H2’s lumpy delivery mix.
- What to watch next quarter: Whether H2 launches on SPR and Dwarka Expressway convert to sales at the guided pace, the trajectory of construction spend (guided to more than double H1’s ₹880 crore), and any update on the unanswered inventory and Lamborghini launch-value questions.
Sales & Launch Phasing
- H1 was deliberately launch-light: only the Tonino Lamborghini Residences (>800 units, Sector 71) opened, yet sales still hit the ~40% H1 target, implying steady absorption from existing inventory.
- H2 pipeline is concentrated on three fronts: a Sector 71 launch (>0.2 crore sq ft), an adjacent plot to Lamborghini Residences (>0.2 crore sq ft), and a single tower on Dwarka Expressway (Sector 37D, ~300,000–400,000 sq ft).
- Sohna (Dakshin) holds a further ~400 units that may launch this year subject to approvals, adding a fourth potential H2 driver.
- No unsold inventory build-up flagged: management characterized H1 sales as in line with the business plan and did not signal any overhang going into the heavier launch half.
- Market tailwind from constrained secondary supply: much of the middle-income stock launched post-2022 is yet to be handed over, limiting resale availability and pushing secondary prices up, which supports primary absorption.
Rajat Kathuria: "If you really look at the actual supply, it is still very low because whatever has been launched over the last three to four years, you could say post-2022, in terms of middle-income housing, a lot of it is yet to be handed over to customers, due to which there is only limited amount of secondary stock available for purchase, which is driving up prices of the secondary stock, and hence having a positive rub-off on the primary stock."
Land & Business Development
- Farrukhnagar (194 acres) is the headline addition: 25 acres acquired, 169 acres via collaboration, in a new micro-market ~15 minutes from Dwarka Expressway, planned as a farmhouse/villa community with a small resort.
- Delhi Master Plan tailwind: Delhi now requires a minimum 2.5 acres for a legal farmhouse; management sees Farrukhnagar’s ability to offer organized-developer farmhouses above 1 acre in Gurugram as a competitive moat.
- Sohna addition of ~31 acres (collaboration) sits near the existing 125-acre Project Dakshin, adding ~0.27 crore sq ft of developable area, with more Sohna additions flagged for H2.
- Smaller infill parcels in Sector 71 and Sector 37D rounded out the ~1 crore sq ft of gross H1 area addition; net addition after ~0.16 crore sq ft sold was ~0.84 crore sq ft.
- BD spend matched to operating cash flows: full-year business development outlay expected to land between ₹1,200 crore and ₹1,500 crore, roughly equal to the guided full-year operating cash surplus, implying no material debt increase from land buying.
Rajat Kathuria: "This is like a massive land situation which we have created in the company, and the balance sheet still looks very hale and hearty."
Margins & Costs
- Q2 margin jump was a mix story, not a structural shift: completions in Q2 were skewed toward mid-income projects, lifting gross margin to ~36% (vs 31% H1 average) and EBITDA margin to ~18% (vs 13% H1 average); affordable-housing-heavy quarters compress margins.
- Construction spend dipped YoY in H1 (₹880 crore vs ₹970 crore) because two large plotted developments (City of Colours, Dakshin industrial plotting) are nearing completion and plotted projects carry lower construction intensity.
- Full-year construction cost guided to more than double H1’s run-rate but stay below ₹2,000 crore, with annual cost escalation expected in the late single digits (7–9%), not double digits.
- GRAP construction bans are built into the cost plan: the company assumes ~10 working months per year, treating recurring NGT-imposed bans as a permanent feature of operating in NCR.
Rajat Kathuria: "The way we plan is to work for about 10 months in a year, and we are always assuming that these NGT ban on construction activity will arise every year. This is not going away anytime soon."
Cash Flow & Balance Sheet
- H1 operating cash surplus of ~₹480 crore represented ~28% of collections, generated before land investment or debt repayments; management expects this to rise significantly in H2 as launches and completions accelerate.
- Full-year cash surplus guided at ₹1,200–1,500 crore, driven by improved H2 collections from new launches and project completions, though management noted this as a range it "can land up" at.
- Net debt held at ~₹450 crore despite the ~1 crore sq ft of business development, because most land additions were structured as collaboration agreements (not outright purchases) and funded from operating cash flows.
- CARE rating reaffirmed at A+ with stable outlook, consistent with the flat-debt, collaboration-heavy funding model.
- Collections steady at ~₹1,700 crore in H1; the 8–10 quarter trend remains ~₹1,000 crore per quarter, with H2 expected to run higher on delivery-linked milestones.
Project Pipeline & Completions
- H1 revenue recognition of ~₹1,400 crore was in line with the business plan; lumpy H2 completions are expected to deliver the bulk of the ~₹5,000 crore full-year target.
- ~0.9 crore sq ft of area is reaching delivery stage "fairly soon," which will drive both revenue recognition and the associated collection milestones.
- Launched portfolio GDV stands at ~₹35,000 crore across ~2.3 crore sq ft of projects launched since February 2024, providing multi-year revenue visibility.
- ~2.7 crore sq ft of developable area is in preparation for launch over the coming two years, with an estimated GDV of ₹30,000–35,000 crore.
- Plotted developments nearing completion: Dakshin/X Factor and City of Colours are awaiting government completion-related approvals within this year, which will unlock incremental collections and revenue.
- RMZ mixed-use project (0.56 crore sq ft, primarily office plus two hotels and retail) has KPF appointed as architect with master planning underway; bulk will be a yield portfolio with a small build-to-sell portion; not yet at launch stage.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Annual sales | ₹10,000 crore (10,000 crore) | FY27 |
| H2 sales phasing | ~60% of annual target, supported by SPR and Dwarka Expressway launches | H2 FY27 |
| Full-year cash surplus | ₹1,200–1,500 crore | FY27 |
| Full-year revenue recognition (completions) | ~₹5,000 crore | FY27 |
| Full-year construction cost | More than double H1’s ₹880 crore, but below ₹2,000 crore | FY27 |
| Annual construction cost escalation | Late single digits (7–9%), not double digits | FY27 |
| Business development spend | Match operating cash flows (₹1,200–1,500 crore) without significant debt impact | FY27 |
| Plotted development completions | Dakshin/X Factor and City of Colours government approvals expected | Within this year |
| Sohna (Dakshin) ~400-unit launch | Subject to approvals | May happen within this year |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Sales (H1 FY27) | ₹3,800 crore, ~675 units, ~0.16 crore sq ft; ~38–40% of full-year guidance of ₹10,000 crore |
| Collections (H1 FY27) | ~₹1,700 crore, steady at ~₹1,000 crore per quarter trend over last 8–10 quarters |
| Revenue recognized (H1 FY27) | ~₹1,400 crore from completed projects; full-year completions guidance ~₹5,000 crore |
| Gross profit margin | ~36% in Q2 FY27, up from ~31% in H1 FY27; driven by more mid-income completions vs affordable |
| EBITDA margin | ~18% in Q2 FY27, up from 13% in H1 FY27 |
| PAT (H1 FY27) | ~₹50 crore |
| Portfolio-level realizations | Crossed ₹17,000 per sq ft, higher than entire previous year realization |
| Cash surplus (H1 FY27) | ~₹480 crore, ~28% of collections; full-year expected ₹1,200–1,500 crore |
| Net debt | ~₹450 crore; gross debt ₹2,870 crore; cash on balance sheet ~₹2,400 crore+ |
| New business development (H1 FY27) | ~1 crore sq ft developable area added; net addition ~0.84 crore sq ft |
| Business development spend (H1 FY27) | ~₹500 crore including approvals; full-year expected ₹1,200–1,500 crore |
| Launched since Feb 2024 till date | ~2.3 crore sq ft; recently launched portfolio GDV ~₹35,000 crore |
| Forthcoming launches pipeline | ~2.7 crore sq ft in preparation over coming two years; GDV ₹30,000–35,000 crore |
| Construction cost incurred (H1 FY27) | ₹880 crore, vs ₹970 crore in H1 FY26; full-year expected below ₹2,000 crore |
| Credit rating | CARE A+ with stable outlook |