SJVN Ltd Q1 FY2023 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/86cgwg2me2ns4b362gqcaboy.pdf

Key Takeaways


Arun-3: Delay, Progress & Tariff

N. L. Sharma: "This is the maximum tariff and we are hopeful, we have worked out the different permutations and combinations of the project costs and expected increase in the project cost also because of various reasons. So, we will be comfortable in the rate in terms of the project costs, we are comfortable at this level of tariff."

Solar & Renewable Pipeline

N. L. Sharma: "This is a major RE project which SJVN and I think this is the largest project so far signed by any company in the solar sector."

Thermal & Pumped Storage

N. L. Sharma: "So, this is not the actual position. One year or two years of hydro test. So, even within six months also the project can be commissioned. Unit can be commissioned after the hydro test. All the components, if they are ready, then there is no such time requirement that only after one year prior to testing to that will be commissioned."

Financials: One-Time Gains & Structural Costs

N. L. Sharma: "Yes. They interest on the HRB the ECB, some portion was over INR30 crore but INR30 crore HRB on ECB, that will not be passed to the consumer."

Funding & Balance Sheet


Guidance & Commitments

CommitmentSpecificsTimeline
Arun-3 commissioningProject commissionedDecember 2023
Buxar thermal Unit 1Unit commissionedJune 2023
Buxar thermal Unit 2Unit commissionedJanuary 2024
FY23 CapEx₹8,000 crore achievedFY23
FY24 CapEx₹10,000 crore targetFY24
FY23 asset monetization₹2,000 crore raisedFY23
FY24 solar CapEx₹4,000–5,000 crore deployedFY24
Arun-3 HRT run rate250 meters/month averageOngoing through completion

Key Metrics

MetricQ1 FY23
Revenue from operations₹1,006 crore, +52% YoY
Total income₹1,070 crore, +52% YoY
Profit Before Tax₹650 crore, +53% YoY
Profit After Tax₹607 crore, +79% YoY
Total generation273.6 crore units, +12.29% YoY
Hydro generation (Nathpa Jhakri)209 crore units, vs 185.6 crore units last year
Hydro generation (Rampur)58.7 crore units, vs 52.3 crore units last year
Wind and Solar generation5.8 crore units, +25% YoY
Total other income₹64.25 crore, vs ₹38.72 crore last year
Late payments surcharge₹20.55 crore, marginally increased by 1.21% YoY
Total incentives earned₹87.59 crore, vs ₹71.55 crore last year
UI (deviation settlement mechanism) incentives₹24.25 crore, vs ₹9.7 crore last year
CapEx incurred₹1,990 crore, +320% YoY; vs target of ₹1,800 crore for the quarter
FY23 CapEx target₹8,000 crore, breakup: ~₹3,000 crore Solar, ₹2,500 crore Thermal, ~₹2,500 crore Hydro
FY24 CapEx target₹10,000 crore, Solar portion ₹4,000–5,000 crore
Asset monetization target (FY23)₹2,000 crore
ECB borrowingUSD 30 crore (~₹2,300 crore), entirely unhedged
Forex loss on ECB interestOver ₹30 crore, not passed to consumer
Arun-3 HRT excavation progress8.7 km excavated out of 11.8 km
Arun-3 expected tariff₹4.55 to ₹4.60 per unit
Bikaner 1,000 MW solar project awarded EPC cost₹5,491 crore, tariff ₹2.45 per unit, generation 250 crore units per year
Pumped storage project sites under explorationTotal capacity more than 13,000 MW, estimated capital cost more than ₹12 crore per MW