SJVN Ltd Q2 FY2023 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/le9mbx6ppa1z1t5txhj7prk7.pdf

Key Takeaways


Quarterly Performance: The Headline Miss and the Underlying Story

Nand Lal Sharma: "I would also like to share that this half yearly profit is again more than the last year's total profit of Rs. 977 crore."

The FX Bite: How a Strong Dollar Hit the P&L


Project Pipeline: Wins, Commissioning Starts, and Approvals

Nand Lal Sharma: "this is in record 11 months that any hydro project DPR has been cleared by CEA"

Arun-3 and Buxar: The Two Giant Timelines


The PPA Problem: Hydro's Structural Disadvantage

Nand Lal Sharma: "They say that after 10 years, there will be some other person in power or other party in power. So, why to think of the persons or the state or the people after 10 years or of the policymaker."
Nand Lal Sharma: "In case of hydro projects, the PPA signing in the beginning has been a difficulty in the past also and is also a difficulty at present also because it is not certain that hydro project will come say, in 5 years or 7 years or 10 years."

Capital Structure, Modules, and the Renewable Subsidiary


Kholongchhu: The Bhutan JV Unwind

Nand Lal Sharma: "If they want to construct it at their own, then naturally we will exit from that. But in that we have put the condition that then they have to pay back our equity contribution, which SJVN has made along with a reasonable rate of interest."

Guidance & Commitments

CommitmentSpecificsTimeline
Parasan solar full commissioning75 MW (31 MW synchronized as of late Oct)"A couple of weeks" from Nov 11, 2022
Naitwar-Mori hydro commissioning60 MWFebruary-March 2023 (FY23)
FY23 renewable capacity addition~205 MW (75 MW solar + 60 MW hydro + 70 MW solar)FY23
FY24 solar commissioning~1,700 MWFY24
Remaining ~3,600 MW portfolio completionBalance of won portfolioFY25
Arun-3 commissioning (aspirational)Management "doing its best" to complete ahead of official Feb 2025 dateMarch 2024
Buxar thermal commissioningPlant up and runningFY24, around same time as Arun-3
Lower Arun hydro construction start669 MW, Nepal; DPR approved, moving for investment approval3-4 months from Nov 2022
Sunni hydro award and construction start382 MW; L1 identified, awaits CCEA investment approvalUpon CCEA approval (undated)
Renewable subsidiary listingListing of green renewable subsidiary once operational portfolio builtEnd of FY24 or FY25
Naitwar-Mori PPA fallbackIf no PPA by commissioning, power sold on open market/exchangeBy Feb-Mar 2023
Kholongchhu exit conditionRepayment of equity contribution plus reasonable interest if Bhutan proceeds under IG modeSubject to GoI-level discussions

Key Metrics

MetricQ2 FY23
Revenue from operations₹880.74 cr, decrease of ~₹3 cr YoY from ₹883 cr
Total income₹921.26 cr, decrease of ₹5.73 cr YoY from ₹926.99 cr
Total expenses₹386.43 cr, increase of ₹79 cr YoY from ₹307.23 cr
Profit before tax₹534.83 cr, decline of ₹84 cr YoY from ₹619.76 cr
Profit after tax₹451 cr, increase of 11% YoY from ₹406 cr
Earnings per share₹1.15, up from ₹1.03 YoY
Net worth increase~₹621 cr over the period
H1 revenue from operations₹1,886 cr, up 22% YoY from ₹1,547 cr
H1 profit after tax₹1,058 cr, up 42% YoY from ₹746 cr; exceeds full-year FY22 PAT of ₹977 cr
Generation432.7 cr units, down 1.7% YoY from 440.4 cr units
Plant availability factor>109%
Finance cost increase (H1)₹101 cr, of which ₹80 cr is FERV
Net foreign exchange impact₹30 cr unrecovered, after ₹50 cr pass-through to beneficiaries
Incentives earned₹73 cr in Q2; H1 ₹161 cr vs H1 FY22 ₹147.97 cr
Under-construction renewable capacity~1,500–1,600 MW won, expected revenue ~₹875–900 cr, CAPEX ~₹7,500–8,000 cr
Arun-3 HRT progress9.54 km heading completed of 11.8 km; avg 300 m/month in last 3 months