SJVN Ltd Q3 FY2023 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/c75tbs8ie7g8v9s5zlgm42qh.pdf

Key Takeaways


Project Execution & Commissioning Pipeline

N L Sharma: "we are targeting the commissioning of this project by the end of next financial year FY2023 though there are many odds what we are trying to manage the things to our best."

Strategic Portfolio Reshaping

N L Sharma: "most of the issues were just not decided because of some stalemates. So that structure did not succeed"

Financial Health & Capital Management

N L Sharma: "...this is assured that we will at least pay what is required under the Government of India guidelines 5% of net worth or 30% of the PAT. We will surely meet that guideline."

Commercial Strategy: PPAs vs. Merchant Risk

N L Sharma: "We will commission, we are targeting by the end of March. So until unless the PPA is signed with any DISCOM or any other utility. We can sell the power through open exchange also."

Guidance & Commitments

CommitmentSpecificsTimeline
Installed capacity milestoneCross 5,000 MW total capacityEnd of FY2024
Buxar thermal projectCommission the projectEnd of FY2024
Arun-3 (Nepal) projectCommission the projectEnd of FY2024
Naitwar Mori projectCommission the 60 MW projectEnd of March 2023
Six renewable projects (1,385 MW)Commission all six projectsFY2024
Buxar labor forceRemaining ~3,000 laborers to return to siteNext 7–10 days
Final dividendAt least meet GoI guideline of 5% of net worth or 30% of PATBefore AGM

Key Metrics

MetricQ3 FY23
Revenue from operations₹551.67 cr, +0.2% YoY
Total income₹723 cr, +19% YoY
Profit before tax₹316 cr, +4.5% YoY
Profit after tax₹290.98 cr, +25% YoY
Net worth₹14,261 cr, up from ₹13,581 cr YoY
Exceptional item₹17.5 cr, interest portion of a ₹33 cr Rampur tribunal award
9M FY23 revenue from operations₹2,438 cr, +16% YoY
9M FY23 profit after tax₹1,349.8 cr, +38% YoY
Interim dividend per share₹1.15, same as last year
Total generation139.49 crore units, -5.7% YoY
9M FY23 total generation845.8 crore units, +1.6% YoY
Capacity incentives and UI₹71.89 cr, -3.3% YoY
Nathpa Jhakri plant availability factor10.22%, marginal increase YoY
Rampur plant availability factor109.98%
Installed capacity2,100 MW
Generation capacity under construction4,323 MW, across 12 generation projects
Renewable operational capacity179.5 MW, across 5 projects
Renewable capacity under construction1,385 MW, across 6 projects
Securitization amount raised₹1,000 cr
Current average cost of borrowing6.5%
Finance cost FERB component₹45 cr
Sunni Dam project estimated cost₹2,615 cr, 382 MW, investment approved
Kholongchhu project equity recovered₹240 cr equity plus ₹114 cr interest at 9%