SJVN Ltd Q4 FY2023 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/vwbfzrqrgtba9rrwzgk8xj3l.pdf

Key Takeaways


Hydrology & Generation

N.L. Sharma: "the Government of India has also written to the state, not only Himachal, but all the states, those who have levied such duties or cess on the generation of power, that this imposition of water cess or such levy is unconstitutional and beyond the scope of powers of the state, because this is ultimately, an additional tax, taxation."

Project Pipeline & Execution


Strategic Pivot: Hydro as a Peaking Asset

N.L. Sharma: "we will not go for long term PPAs because it has been seen that, the need of hydro, the necessity of hydro is going to be there in the times to come with the increase in the intermittent energy from solar and wind projects."

Regulatory & Cost Headwinds


Subsidiary & Financial Notes


Guidance & Commitments

CommitmentSpecificsTimeline
Buxar thermal Unit 1 commissioningFirst unit onlineMarch 2024
Buxar thermal Unit 2 commissioningSecond unit onlineMay/June 2024
Arun-III hydro commissioningFull 900 MW onlineMarch–September 2024
Naitwar Mori commissioning60 MW onlineJuly 2023 (Q2 FY24)
Lower Arun investment approvalCabinet approval for 669 MW project"In a month or two"
Lower Arun construction startGround-breakingCalendar year 2023
Solar capacity addition (FY24)1,500 MW commissionedCurrent financial year
Solar capacity addition (FY25)1,200 MW commissionedNext financial year
Sunni hydro commissioningProject onlineFY28–29
Shared vision capacity target25,000 MW portfolioBy 2030

Key Metrics

MetricQ4 FY23
Revenue from operations₹2,935 cr, up over 21% YoY
Total revenue₹3,298 cr, up over 25% YoY, highest ever
Profit before tax₹1,732 cr, up about 29% YoY
Profit after tax₹1,363 cr, up about 40% YoY
Earnings per share₹3.47, up from ₹2.49 in FY22
Net worth₹13,822 cr, up over 5% YoY
Total consolidated generation933.5 crore units, up over 1% YoY
Total incentives₹305 cr, up 2.2% YoY; capacity ₹210 cr, UI/DSM ₹43.63 cr, secondary energy ₹50.67 cr, REC ₹0.74 cr
Capex incurred₹8,240 cr, highest ever, 70% CAGR over six years
Regulated equity, commissioned projects₹6,193 cr
Regulated equity, under-construction projects~₹7,000 cr
Solar capacity under operation179 MW
Solar capacity under construction1,500 MW
Solar capacity in pipeline1,183 MW
Renewable capacity addition target, FY24~1,500 MW
Renewable capacity addition target, FY25~1,200 MW
Thermal project, Buxar, capex spent to date~₹7,500 cr
Hydro project, Arun-3 Nepal, capex spent to date₹4,200 cr
Pump storage projects indicated by GoI10 projects, 12,790 MW
Shared vision capacity target25,000 MW by 2040